Question_12.doc
DOC document 39 KB Posted
- Attached to
- USS EMORY S. LAND (AS 39) Mid-Term Availability Federal contract opportunity
- Solicitation number
- N3220518R4552
About this file
Request for specification clarification 012 - answered.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR SPECIFICATION CLARIFICATION
SPECIFICATION ITEM NO.: 103
PARAGRAPH / SECTION NO: 7.2
TITLE: Watertight Door Repair
QUESTION:
Paragraph 7.2 The work area existing paint scheme may contain lead paint. The contractor shall invoke the lead abatement program anytime existing paint is going to be removed.
Are contractors required to include costs for abatement and disposal of hazardous materials in this work item or will this be determined and priced upon inspection.
ANSWER:
The lead abatement program and pricing is Work Item 0616, Lead Abatement.