RFP_QandA_No._1_SUPPLY_18-R-4251.docx

DOCX document 28 KB Posted

Attached to
USNS SUPPLY ROH/DD Federal contract opportunity
Solicitation number
N32205-18-R-4251
Issued by
Department of the Navy Military Sealift Command

About this file

Responses to Specification Clarifications

View the file

Other files for this federal contract opportunity

Other files attached to USNS SUPPLY ROH/DD, newest first.
File Type Posted
J_-_3_Category_B_Items_Amendment_6.xls XLS spreadsheet
N3220518R4251_Amendment_0006.docx DOCX document
J_-_2_Category_A_Items_Amendment_6.xls XLS spreadsheet
RFP_QandA_No._6_SUPPLY_18-R-4251.docx DOCX document
N32205-18-R-4251_Amendment_0005.docx DOCX document
J_-_2_Category_A_Items_Amendment_4_corrected.xls XLS spreadsheet
J_-_3_Category_B_Items_Amendment_4.xls XLS spreadsheet
J_-_2_Category_A_Items_Amendment_4.xls XLS spreadsheet
N32205-18-R-4251_Amendment_0004_SF30_released.docx DOCX document
N32205-18-R-4251_Amendment_0003.docx DOCX document
0000-N3220518R4251-ROH19-Index_-.docx DOCX document
N32205-18-R-4251_Amendment_0002.docx DOCX document
RFP_QandA_No._4_SUPPLY_18-R-4251.docx DOCX document
6361516_H.pdf PDF
Resilient_Mount_Photo's_WI_326_(5).jpg JPG image
Resilient_Mount_Photo's_WI_326_(2).jpg JPG image
Resilient_Mount_Photo's_WI_326_(3).jpg JPG image
NAVAIR_Air_Capable_Ship_Bulletin_1M_.pdf PDF
RFP_QandA_No._3_SUPPLY_18-R-4251.docx DOCX document
Resilient_Mount_Photo's_WI_326_(4).jpg JPG image
Resilient_Mount_Photo's_WI_326_(1).JPG JPG image
RFP_QandA_No._2_SUPPLY_18-R-4251.docx DOCX document
J_-_3_Category_B_Items-rev._1.xls XLS spreadsheet
N32205-18-R-4251_Amendment_0001.docx DOCX document
J_-_12_Past_Performance_Data.doc DOC document
J_-_9_Disclosure_of_Lobbying_Activities_SF-LLL.doc DOC document
J_-_13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
N32205-18-R-4251.docx DOCX document
J_-_10_Interport_Differential_East_Coast.doc DOC document
J_-_3_Category_B_Items.xls XLS spreadsheet
J_-_2_Category_A_Items.xls XLS spreadsheet
J-4_USNS_SUPPLY_ROH18.pdf PDF
J_-_8_Request_for_Spec_Clarification.doc DOC document
J_-_11_Dry_Dock_Evaluation_Form.docx DOCX document
J-15_Non-Mariner_Maintenance_Contractor_Vetting_Sheet_(Rev_8_(v4)_20_Sep_2017).xlsx XLSX spreadsheet
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-18-R-4251

USNS SUPPLY ROH/DD

QUESTIONS AND ANSWERS #1

The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.

1. SPECIFICATION ITEM NO.:901

PARA. NO.: 3.1 and 7.1.1 a.

TITLE: DRY-DOCKING AND UNDOCKING VESSEL

QUESTION: Contractor’s Dry-Dock is 751.4’ inside length overall with the caisson in the outer seal. It is currently our standard operating method to utilize the outer seal on a regular basis. We have attached a drawing of Dry-Dock #5, prepared by an outside engineering firm that documents the length and includes drawings and calculations for the successful drydocking of the USNS Supply.

Paragraph 3.1 lists the LENGTH OVERALL of the Vessel as 753 FT. – 8 1/2 IN. or 753.71’.

Paragraph 7.1.1 a. states that the Dock length overall is to be greater than the vessel’s LOA, regardless of type of dock used. It also allows for exceptions to the requirement to be considered on a case by case basis during the bid phase.

Contractor requests an exception for the use of our Dry-Dock #5 for the work required by RFP NO. N32205-18-R-4251. We base this request on previously successful Drydock and Repair Availabilities for MSC on the USNS Supply (T-AOE 6) as well as the sister ship USNS Arctic (T-AOE 8).

We request that a determination on this request be made as soon as possible so that we can commit the necessary resources to prepare a competitive bid for MSC.

ANSWER:

Based on several successful dockings in the past the government approves the requested exception.

2. SPECIFICATION ITEM NO.: 554

PARA. NO.: 4.3.1 and 7.10.1

TITLE: STEAM TO ELEC WTR HTR CONVERSION

QUESTION:

Para 4.3.1 indicates that the Hubbel Rep will be provided by the government. However, para 7.10.1 directs the contractor to provide the Hubbel Rep. Will the government or the contractor be responsible to provide the Hubbel Rep?

ANSWER:

Hubbel Rep will be provided by the contractor.

3. SPECIFICATION ITEM NO.: 910

PARA. NO.: 7.12

TITLE: UNDERWATER HULL CLEANING AND PAINTING

QUESTION:

Para 7.12 directs the contractor to estimate 20,000 square feet will require blasting to bare metal. Para 7.12.1 directs the contract to blast 40,000 square feet to near white metal. Should the contractor plan to blast 20,000 sq.ft. or 40,000 sq.ft?

ANSWER:

Contractor should plan on blasting 20,000 Sqft to bare metal (SSPC-SP10) or equivalent UHP specification