N3220518R4251_Amendment_0006.docx

DOCX document 34 KB Posted

Attached to
USNS SUPPLY ROH/DD Federal contract opportunity
Solicitation number
N32205-18-R-4251
Issued by
Department of the Navy Military Sealift Command

About this file

Amendment 0006

View the file

Other files for this federal contract opportunity

Other files attached to USNS SUPPLY ROH/DD, newest first.
File Type Posted
J_-_3_Category_B_Items_Amendment_6.xls XLS spreadsheet
J_-_2_Category_A_Items_Amendment_6.xls XLS spreadsheet
RFP_QandA_No._6_SUPPLY_18-R-4251.docx DOCX document
N32205-18-R-4251_Amendment_0005.docx DOCX document
J_-_2_Category_A_Items_Amendment_4_corrected.xls XLS spreadsheet
J_-_3_Category_B_Items_Amendment_4.xls XLS spreadsheet
J_-_2_Category_A_Items_Amendment_4.xls XLS spreadsheet
N32205-18-R-4251_Amendment_0004_SF30_released.docx DOCX document
N32205-18-R-4251_Amendment_0003.docx DOCX document
0000-N3220518R4251-ROH19-Index_-.docx DOCX document
N32205-18-R-4251_Amendment_0002.docx DOCX document
6361516_H.pdf PDF
RFP_QandA_No._4_SUPPLY_18-R-4251.docx DOCX document
Resilient_Mount_Photo's_WI_326_(2).jpg JPG image
Resilient_Mount_Photo's_WI_326_(5).jpg JPG image
Resilient_Mount_Photo's_WI_326_(3).jpg JPG image
NAVAIR_Air_Capable_Ship_Bulletin_1M_.pdf PDF
RFP_QandA_No._3_SUPPLY_18-R-4251.docx DOCX document
Resilient_Mount_Photo's_WI_326_(4).jpg JPG image
Resilient_Mount_Photo's_WI_326_(1).JPG JPG image
RFP_QandA_No._2_SUPPLY_18-R-4251.docx DOCX document
RFP_QandA_No._1_SUPPLY_18-R-4251.docx DOCX document
J_-_3_Category_B_Items-rev._1.xls XLS spreadsheet
N32205-18-R-4251_Amendment_0001.docx DOCX document
N32205-18-R-4251.docx DOCX document
J_-_10_Interport_Differential_East_Coast.doc DOC document
J_-_12_Past_Performance_Data.doc DOC document
J_-_9_Disclosure_of_Lobbying_Activities_SF-LLL.doc DOC document
J_-_13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
J_-_3_Category_B_Items.xls XLS spreadsheet
J_-_2_Category_A_Items.xls XLS spreadsheet
J-4_USNS_SUPPLY_ROH18.pdf PDF
J_-_8_Request_for_Spec_Clarification.doc DOC document
J_-_11_Dry_Dock_Evaluation_Form.docx DOCX document
J-15_Non-Mariner_Maintenance_Contractor_Vetting_Sheet_(Rev_8_(v4)_20_Sep_2017).xlsx XLSX spreadsheet
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220518R4251

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0002

The CLIN extended description has changed from:

Additional Growth Requirements (AGR)(29,592) man-hours @ $________ per man-hour = $_____________

Other Direct Costs (ODC)Base $_1,752,849.40_ Proposed G&A Rate _______________%

Subtotal:$_____________
Proposed Profit Rate _______________%Subtotal:$_____________

To:

Additional Growth Requirements (AGR)(20,000) man-hours @ $________ per man-hour = $_____________ Other Direct Costs (ODC)Base $_1,750,000.00_ Proposed G&A Rate _______________%

Subtotal:$____________
Proposed Profit Rate _______________%Subtotal:$_____________

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

C – 2 List of Standard WIs included for this solicitation:

000 GENERAL REQUIREMENTS

001
NSP
Intent, Scope, general, and Definitions
002
NSP
Technical and Manufacture's Representatives
003
NSP
Approach, Berth, and Mooring Requirements
004
NSP
Testing & Quality Assurance
005
NSP
Electrical Safety Procedures and Requirements
006
NSP
Heavy Weather Plan
007
NSP
Cold Weather Plan
10
A
Furnish Office for OMT
11
A
General Services for the Ship T-AOE
12
A
Telephone Services
13
A
Project Planning and Monitoring
14
A
Weight and Moment report
15
A
ILS, GFM
16
A
Fire Protection and Ship's Safety Program
17
A
Handling Ship's Stores
18
A
Delivery and Redelivery
19
A
Shipboard Access
20
A
Gas Free Certificates
21
A
Clean and Gas Free Tanks, Voids, and Cofferdams
22
A
Dock Trials and Sea Trials
23
A
Hazardous Waste Disposal
24
A
Physical Security at Private Contractor's Facility
25
B
Physical Security at Private Contractor's Facility
30
B
Continuation of Services

100 STRUCTURAL

A A

ABS TANK CLOSE-UP INSPECTION SUPPORT

TANK VENT CLEAN AND INSPECT

103
A
ABS TANK INSPECTION AND TESTING
104
A
FLIGHT DECK NON-SKID RENEWEL
105
A
FLIGHT DECK SAFETY NETS
107
A
WEATHERDECK DRAIN PPG REPAIR
108
A
REMOVE UNUSED ANTENNA FDN
111
A
CHT TANKS MAINTENANCE COAT REV-
112
A
MSD TANK MAINTANACE COAT
124
A
03 LVL CIC CONVERSION TO STATEROOMS
125
A
CARGO TK LVL SENSOR INSTL
126
A
HAWESPIPE, RESTORE CLAD WELD (VR16-071)
127
A
PALLET CONVEYOR DOOR REPAIR (VR16-079)
129
A
AMR ESCAPE TRUNK PRESERVATION (VR15-022)
131
A
STACK STRUCTURAL STEEL REPAIRS
132
A
FAN TAIL STRUCTURAL REPAIRS

A A

POTABLE WATER TANK PRESERVATION

CLAD WELD REPAIR TO 03 OVERHEAD

200 MAIN PROPULSION MACHINERY

201
A
RCC RELIEF VALVE INSPECT SET AND TEST.

A A

RRG RELIEF VALVE INSPECT SET AND TEST.

PORT AND STBD PROPULSION SHAFT REACTIONS

210
A
HOSE REPLACEMENT, GAS TURBINE MODULE

A A

GAS TURBINE INTAKE INSPECTION AND REPAIR

LUBE OIL SYSTEM, INSTALL UNLOADER BYPASS (TA)

300 ELECTRICAL

304
B
STUFFING TUBE REPLACEMENT
305
B
MULTIPLE CABLE TRANSIT REPAIRS
306
A
SSDG WINDING CLEANING AND BEARING REFURB
310
A
SSDG TOP END OVHL (20,000 Hr) SSDG 3
326
A
SSDG 5 RESILIENT MOUNT CHANGE
328
A
SSDG, HEAT EXCHANGER REPAIRs (Two SSDG)

400 ELECTRONICS

407
A
OE-82 ANTENNA PM
410
A
FATHOMETER PM
415
A
GYROCOMPASS AND REPEATERS
424
A
SRD-500 DOPPLER SPEED LOG REPLACEMENT
425
A
ADNS NAVMACS SUPPORT Items

500 AUX EQUIPMENT

A A A

ASSIST SHIPS FORCE

RELIEF VALVE OVERHAUL

PORT AND STBD RHIB DAVIT INSPECTION

505
A
PORT AND STBD SAFETY BOAT INSPECTION

A A

AUXILIARY BOILER INSPECTION

REPLACE STERN TUBE COOLING SYSTEM

511
A
DIST PLT FDWTR REG VLV OVERHAUL

B A

LAGGING AND INSULATION REPAIR

CHT PIPING REPAIR

517
A
FIRE PMP 1 AND 2 RECIRC PPG RPR
518
A
FIRE PMP 3 AND 4 RECIRC PPG RPR

A A

UPTAKES FLUE CLEANING, INSPECTION AND REPAIR

SCBA CYLINDER HYDROSTATIC TESTING

527
A
6&8-INCH MAGAZINE SPRINKLING VALVE OVERHAUL (10 yr)
530
A
PUMPS AND MOTORS
534
A
WEATHERDECK VENT DUCT REPAIRS
535
A
FIREMAIN REPAIR, VARIOUS
540
A
VENT PLENUM RPR, EXH 1-447-2 (16-076)
541
A
SOIL DRN SYSTEM, REPLACE VALVE (16-072)
542
A
CMWD ISOLATION BUTTERFLY VALVE RENEWALS
544
A
VENT PLENUM RPR, EXH E01-250-2 (16-053)
545
A
VENT PLENUM RPR, SUP S1-332-2 (16-043)
548
A
UNREP RECEIVING STATION REPAIR, DFM (17-089, 91, 92)
549
A
UNREP RECEIVING STATION REPAIR, JP5 (17-089, 91, 92)
551
A
LAUNDRY HOSES (VR17-067)
552
A
STEERING AND RUDDER INDICATING CHECKS
553
A
SSDG No 2, 3, 4, and 5 EXHAUST, INSULATION
554
B
STEAM TO ELEC WTR HTR CONVERSION TA314
555
B
INSTALL OILY WATER SEPARATOR (OWS) UNIT TA301

600 HABITABILITY

601
A
GALLEY EQUIPMENT SERVICE

A A

ACCOMODATION LADDER MAINTENANCE AND TESTING (VR17-009, 17-010)

LIFE RAFT CERTIFICATION

A A A

INTERIOR CPC DECK REPLACEMENT

PAINT LOCKER MIXING ROOM, ADD EXHAUST VENTIALTION

DECK REPAIR-MAIN SCULLERY

800 HVAC

801
A
GALLEY AND VENTILLATION DUCT CLEANING

900 DRYDOCKING AND UNDERWATER HULL

901
A
DRY DOCKING AND UNDOCKING
902
B
DRY DOCKING AND UNDOCKING B ITEM
904
A
RUDDER AND STERN FRAME EXAMINATION
905
A
BILGE KEEL EXAMINATION
906
A
CATHODIC HULL PROTECTION SYSTEM MAINTENANCE
907
A
CATHELCO PROTECTION SYSTEM PM
908
A
RENEW ZINCS
909
A
ULTRA SONIC TESTING (12,000)
910
A
UNDERWATER HULL CLEANING AND PAINTING
911
A
FREEBOARD CLEANING AND PAINTING
913
A
CHAIN AND LOCKER PAINTING
915
A
PROPELLER CLEAN AND REPAIR
917
A
PROPELLER SHAFT WEAR DOWN READINGS
918
A
REPLACE RUDDER STOCK SEAL
919
A
FOREPEAK TANK PRESERVATION (VR14-045)
928
B
SHELL PLATE AND WELDING REPAIR
929
B
STEEL RENEWAL
932
B
ULTRASONIC TESTING

1000 UNREP/VERTREP

1001
A
QUADRENNIAL BOOM SURVEY
1002
A
TOPPING WINCH FDN AND WINCH REFURB
1003
A
LEAD ANGLE COMPENSATORS REPAIR
1004
A
GYPSY WINCH FDN AN WINCH REPAIRS
1005
A
SLIDING BLOCK CHAIN REPLACEMENT WITH PRESERVATION
1006
A
SLIDING BLOCK NO.1 ELEC MTR AND BRAKE ASSEMBLY REFURB

*BOLDED WORK ITEMS HAVE EITHER BEEN REVISED, ADDED OR CONVERTED TO CAT “B” WORK ITEMS.

image1.wmf

File details come from the government source that posted it.