Attachment_9_AIR-6_6_Surveillance_Activity_Checklist.docx

DOCX document 39 KB Posted

Attached to
AIR 6. 6 Logistics Support Federal contract opportunity
Solicitation number
N00421-15-R-0092
Issued by
Department of the Navy Naval Air Systems Command

About this file

Attachment 9

View the file

Other files for this federal contract opportunity

Other files attached to AIR 6. 6 Logistics Support, newest first.
File Type Posted
Answer_to_Industry_VII.docx DOCX document
Attachment_2_Corporate_Experience_TablesREV4.xlsx XLSX spreadsheet
Answers_to_Industry_-_Amd_07.pdf PDF
N00421-15-R-0092-0007.pdf PDF
15-R-0092-0006.docx DOCX document
Attachment_2_Corporate_Experience_TablesREV3.xlsx XLSX spreadsheet
15-R-0092_Answers_to_Industry_Questions_V.docx DOCX document
15-R-0092_INDUSTRY'S_QUESTIONS_PART_IV.docx DOCX document
15-R-0092-0005.docx DOCX document
Attachment_2_Corporate_Experience_TablesREV2.xlsx XLSX spreadsheet
15-R-0092_ANSWERS_TO_INDUSTRY_QUESTIONS_III.docx DOCX document
N00421-15-R-0092-0004.docx DOCX document
Attachment_6_P6_CLIN_Breakout_spreadsheet_Cost_Summary_Spreadsheet_for_Sample_task_1REV1.xlsx XLSX spreadsheet
N00421-15-R-0092-0003.docx DOCX document
Attachment_2_Corporate_Experience_TablesREV1.xlsx XLSX spreadsheet
N00421-15-R-0092_Amend_0002.docx DOCX document
15-R-0092_INDUSTRY'S_QUESTIONS_PART_II_10_May.docx DOCX document
15-R-0092_ANSWERS_TO_INDUSTRY_QUESTIONS_PART_I.docx DOCX document
N00421-15-D-0092-0001.docx DOCX document
Attachment_4_P5_Past_Performance_Questionnaire_Package_for_Services.doc DOC document
Attachment_10-_SGFP_Data_Input_Spreadsheet_template_(NAVAIR_Version_16Sept2015).xlsx XLSX spreadsheet
Attachment_5_CPARS_UPDATE_QUESTIONNAIRE.doc DOC document
Attachment_6_P6_CLIN_Breakout_spreadsheet_Cost_Summary_Spreadsheet_for_Sample_task_1.xlsx XLSX spreadsheet
Attachment_2_Corporate_Experience_Tables.xlsx XLSX spreadsheet
Attachment_8_AIR-6_6_Quality_Assurance_Surveillance_Plan_N00024-15-R-0092.docx DOCX document
Attachment_3_P4_Past_Performance_Matrix_(3).doc DOC document
Attachment_7_N00421-15-R-0092_BID_DD254_signed.pdf PDF
Attachment_1_Workforce_Qualification_Spreadsheet_for_Key_Personnel.xls XLS spreadsheet
AIR_6.6_14_APR_2016_RFP1.docx DOCX document
AIR-6_6_MAC_FBO_Pre-Solicitation_Notice_QuestionsAnswers.docx DOCX document
Advanced_Planning_Notice_Milestones.docx DOCX document
6_6_MAC_DRAFT_SOW.docx DOCX document
ADVANCED_PLANNING_NOTICE_LOE_BREAKDOWN.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Surveillance Activity Checklist Integrated Logistics Support (ILS) for Program Management and Logistic Support Services for AIR 6.6, Logistics Management Integration Department (LMID), Patuxent River, MD

1. Purpose This Surveillance Activity Checklist is a Government developed and applied document used to make sure the systematic quality assurance assessment methods are used in the administration of the Statement of Work (SOW). The intent is to ensure that the Government receives the quality of services and products for tasks identified in the SOW.

This requirement will provide for Integrated Logistics Support (ILS) program management and logistics support services in acquisition and sustainment for the Life Cycle of the designated weapons system/system of systems, its sub-systems and support equipment for AIR-6.6 and the associated Program Offices. There are multiple logistics functional leads, including AIR 6.6 Logistics Integration Department, Program Office Product Support managers, Assistant Program Manager for Logistics (APML)/Military Lead, respective Platform Principal APMLs, respective IPT Deputy APMLs, Logistics Element Managers (LEMS), and Fleet staffs (Resident Independent Logistics Support Detachment - RILSD). The types of services that are to be provided under this contract consist the resources necessary to plan, manage, and integrate the design, development, acquisition, delivery and sustainment of naval aviation weapons systems and products.

The resultant contract will be an Indefinite Quantity Indefinite Delivery (IDIQ), Multiple Award Contract (MAC) in accordance with FAR 16.505, and will consist of both performance based and non-performance based task orders. The level of effort (LOE) task order(s) awarded off this MAC will contain a cost-plus-fixed-fee (CPFF) labor CLIN, and cost-reimbursable CLINs for travel, material, and NMCI. The resultant contract will contain a five year ordering period and three year award term period. A properly executed Checklist will assist the Government in achieving the objectives of this procurement.

2. Authority Authority for the issuance of this Surveillance Activity Checklist is provided under the basic NAWCAD MAC, Section E – Inspection and Acceptance, which provides for inspections and acceptance of the services and documentation called for in task orders, to be executed by the Contracting Officer or a duly authorized representative.

3. Scope To fully understand the roles and responsibilities of the parties, it is important to first define the distinction in terminology between Quality Control Plan and the Surveillance Activity Checklist. The contractor, and not the Government, is responsible for management and quality control actions necessary to meet the quality standards set forth by the contract.

The Checklist is put in place to provide Government surveillance oversight of the contractor’s efforts to assure that they are timely, effective and are delivering the results specified in the contract.

4. Government Resources Outlined below are the following definitions of the roles and responsibilities for Government resources as applicable to this Surveillance Activity Checklist:

Contracting Officer – A person duly appointed with the authority to enter into (Procuring Contracting Officer (PCO)) or administer (Administrative Contracting Officer (ACO)) task orders and make related determination and findings on behalf of the Government. The PCO and ACO will be designated in the resulting order. Contracting Officers are designated via a written warrant, which sets forth limitations of authority.

Contracting Officer’s Representative (COR) – (formerly Task Order Manager (TOM)). An individual appointed in writing by the PCO to act as their authorized representative to assist in administering the task order. The COR will be appointed in the resulting task order. The limitations of authority are contained in a written letter of appointment.

5. Responsibilities The following Government resources shall have responsibility for the implementation of this Surveillance Activity Checklist.

Contracting Officer – The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the task order and safeguards the interests of the United States in the contractual relationship. It is the Contracting Officer that assures the contractor receives impartial, fair and equitable treatment under the task order. The Contracting Officer is ultimately responsible for the final determination of the adequacy of the contractor’s performance.

Contracting Officer’s Representative (COR) – The COR is responsible for technical administration of the task order and assures proper Government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the contractor deems may affect task order price, terms, or conditions shall be referred to the Contracting Officer for action.

6. Methods of QA Surveillance

1. Methods of Surveillance

a. Contractor Performance Assessment Reporting System (CPARS) – The marketplace for logistic and technical service is very competitive. As such, the successful offeror has a vested interest in the Government-generated CPARS ratings for all task orders under this MAC. Additionally, the CPARS ratings will be the determinant in exercising an option or award term. For this procurement the Government will address the quality of product or service, schedule, cost control, business relations, management, and other important areas. As this information may affect future source selections throughout DoD, and the continuation of the task order, the annual Government assessment will be used appropriately as an additional performance oversight and communication tool with the SURVEILLANCE ACTIVITY CHECKLIST.

b. Surveillance Activity Checklist – The below listed methods of surveillance will be used by the COR in the technical administration of this checklist. In addition to the below instructions, the form to be used for documentation of quality assurance surveillance is the Semi-Annual Surveillance Activity Checklist.

c. Observation, Feedback, and Review – Unscheduled observation of products and services provided by the contractor on site and recurring review of contractor submitted reports and documentation identified in CDRLs will be performed by the COR and ACOR. Feedback from customers will be collected and used by the COR to document surveillance of technical performance.

7. Surveillance The Surveillance Activity Checklist, Enclosure (1), will be provided to the contractor on a monthly basis, as feedback on the performance of their management and quality control actions for meeting the quality standards set forth by the task order.

8. Documentation In addition to providing quarterly reports to the Contracting Officer, the COR will maintain a complete Quality Assurance file. The file will contain copies of all reports, evaluations, recommendations, and any actions related to the Government’s performance of the quality assurance function, including the originals of the Semi-annual Customer Survey Checklists. All such records will be maintained for the life of the task order. The TOM shall forward these records to the Contracting Officer at termination or completion of the order.

9. Enclosures

N00024-15-R-0092 Attachment 9 Enclosure (1) - Surveillance Activity Checklist Source Selection Information 2 For Official Use Only See FAR 3.104 and 2.101

Source Selection Information See FAR 3.104 and 2.101 SURVEILLANCE ACTIVITY CHECKLIST (Enclosure 1)

All SOW/CDRL tasks, including SOW/CDRL sub-tasks, will be assessed focusing on the following.

Quality of Product or Service – Assess the contractor’s effort to transform operational needs and requirements into an integrated solution. Areas of focus may include the planning and management of program tasks, the quality of support provided throughout all phases of contract execution, the integration of program management specialties, management of interfaces, and the management of a totally integrated effort of all program management concerns to meet cost, performance, and schedule objectives. Assess how successfully the contractor meets program quality.

Schedule – Assess the contractor’s adherence to the required delivery schedule by assessing the contractor’s efforts during the assessment period that contribute to or effect the schedule variance. Also address significance of scheduled events (i.e., design reviews), discuss causes, and assess the effectiveness of contractor corrective actions.

Cost Control – Assess the contractor’s effectiveness in forecasting, managing, and controlling contract cost. Is the contractor experiencing cost growth or underrun? If so, discuss the causes and contractor-proposed solutions for the cost overruns. For contracts where task or contract sizing is based upon contractor provided person-hour estimates, the relationship of these estimates to ultimate cost should be assessed. In addition, the extent to which the contractor demonstrates a sense of cost responsibility, through the efficient use of resources in each work effort should be assessed.

Business Relations – Assess the timelines, completeness and quality of problem identification, corrective action plans, proposal submittals, the contractor’s reasonable and cooperative behavior, effective business relations, and customer satisfaction.

Management – Assess the contractor’s success with timely award and management of subcontracts. Discuss the extent to which the contractor discharges its responsibility for integration and coordination of all activity needed to execute the contract; identifies and applies resources required to meet schedule requirements; assigns responsibility for tasks/actions required by contract; communicates appropriate information to affected program elements in a timely manner. Assess the contractor’s risk mitigation plans. If applicable, identify any other management areas that are unique to the contract.

Other areas – Assess additional evaluation areas unique to the contract or that cannot be captured elsewhere.

Monthly Surveillance:

The COR will perform a monthly assessment of Quality, Schedule, Cost Control, Business Relations, Management, and Other Areas as applicable utilizing the CPARS evaluation rating definitions listed below.

The evaluation ratings definitions are as follows:

Exceptional – Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the task and sub-task being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good - Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the task and sub-task being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Satisfactory - Performance meets contractual requirements. The contractual performance of the task and sub-task contain some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal - Performance does not meet contractual requirements. The contractual performance of the task and sub-task being assessed reflect a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the task or sub-task contains a serious problem(s) for which the contractor’s actions appear or were ineffective.

Enclosure (1) Surveillance Activity Checklist

Description
Surveillance Method/

Measure

Date Planned
Date Completed
Quality
Schedule
Cost Control
Business Relations
Mgmt Key Personnel

Other

Plan, Schedule, and Implement support to the AIR 6.6 Competency / requiring Program Office logistics organization in the gathering and correlation of information for the preparation and development of presentations to support team meetings, management reviews, logistics team reviews, audits and other requests for presentation/briefing information
COR and Customer feedback
NTL 10th of each month
Provide support in the development and updating of the primary individual system/component LRFS as well as the respective IPT-related LRFSs (end item/system) in support of production, engineering change orders, and budgetary adjustments
COR and Customer feedback
NTL 10th of each month
Conduct technical research, provide recommendations, and prepare draft inputs for the development of SOW / SPECs / CDRLs for new acquisitions and modification programs that include the elements of supportability, reliability, availability, and maintainability.
COR and Customer feedback
NTL 10th of each month
Provide recommendations for developing, modifying, and updating the LCSP / ULSS Support as defined in the Defense Acquisition Guidebook and IAW NAVAIR and supported organization requirements and guidance.
COR and Customer feedback
NTL 10th of each month
Conduct Business Case Analyses (BCA) to provide recommendations for developing and modifying alternative supportability solutions for weapon systems, subsystem and/or support systems to identify the most cost effective plan to ensure the accomplishment of program objectives.
COR and Customer feedback
NTL 10th of each month

Conduct a Best Value analysis making recommendations on the optimum level of support based on the 12 IPS elements to include the following areas:

Supply Chain Management Strategy Workload allocation strategy Technical Data Rights Strategy (TDS) Life cycle cost control and risk mitigation

COR and Customer feedback
NTL 10th of each month

Develop, prepare, review or update DMSMS Plans following the policy, standards and guidance provided by the Deputy Assistant Secretary of the Navy (Logistics), Program Executive Office, Commander, Naval Air Systems Command, or other authority

COR and Customer feedback

NTL 10th of each month

Provide insight and guidance for the development, preparation and/or update of the IUID Plans following the policy and guidance provided by the Under Secretary of Defense for Acquisition, Technology and Logistics, Deputy Assistant Secretary of the Navy (Logistics), Program Executive Office, Commander, Naval Air Systems Command, or other authority.
COR and Customer feedback
NTL 10th of each month

Provide recommendations for the development of a Demilitarization And Disposal Plan.

Review and analyze specified parts lists and BOMs and provide options for disposition IAW DOD INST 4160.21-M and DOD INST 4160.28

COR and Customer feedback
NTL 10th of each month

Monthly Summary of Ratings:

QualitySchedule
Number of Exceptional____Number of Exceptional____
Number of Very Good____Number of Very Good____
Number of Satisfactory____Number of Satisfactory____
Number of Marginal____Number of Marginal____
Number of Unsatisfactory____Number of Unsatisfactory____
Cost ControlBusiness Relations
Number of Exceptional____Number of Exceptional____
Number of Very Good____Number of Very Good____
Number of Satisfactory____Number of Satisfactory____
Number of Marginal____Number of Marginal____
Number of Unsatisfactory____Number of Unsatisfactory____
Management of Key PersonnelOther Areas
Number of Exceptional____Number of Exceptional____
Number of Very Good____Number of Very Good____
Number of Satisfactory____Number of Satisfactory____
Number of Marginal____Number of Marginal____
Number of Unsatisfactory____Number of Unsatisfactory____

Enclosure (2)

ANNUAL CPARS SURVEILLANCE

Surveillance will be completed annually with Contract Performance Assessment Report (CPAR) across all task orders.

Assessment Description
Method of Surveillance
Date Planned
Date Completed
Summary Rating
Results
Quality of Service
· 100% Inspection by COR

· Review of Monthly CDRLS

· Review of COR and Customer Feedback

Schedule
· 100% Inspection by COR

· Review of Monthly CDRLS

Cost Control
· 100% Inspection by COR

· Review of Monthly CDRLS

Business Relations
· 100% Inspection by COR

· Review of Monthly CDRLS

Management
· 100% Inspection by COR

· Review of Monthly CDRLS

Other
· 100% Inspection by COR

· Review of Monthly CDRLS