J-2_ARSV_DRLs_-_Final_6-18-18.pdf

PDF 412 KB Posted

Attached to
Atlantic Undersea Test and Evaluation Center (AUTEC) Range Support Vessel, "ARSV"
Solicitation number
N00024-19-R-2205
Issued by

About this file

J-2 DRLS

View the file

Other files

File Type Posted
ARSV-Specification_4.0.PDF PDF
19R2205-0007.pdf PDF
19R2205-0006.pdf PDF
19R2205-0005.pdf PDF
J-1_ARSV_Specification_2.0_FINAL.pdf PDF
19R2205-0004.pdf PDF
19R2205-0003.pdf PDF
19R2205-0002.pdf PDF
19R2205-0001.pdf PDF
ACN4570.pdf PDF
J-3_ConsolidatedGovernmentFurnishedProperty_1.2_ARSV13Jun18.xlsx XLSX spreadsheet
ACN4420.pdf PDF
J-12_Technical_Data_Package_Status_List.xlsx XLSX spreadsheet
J-13_Past_Performance_Questionnaire.doc DOC document
ACN4416.pdf PDF
ACN4974.pdf PDF
ACN4563.pdf PDF
ACN6352.pdf PDF
ACN4578.pdf PDF
J-7_List_of_Prohibited_Materials_N0002419R2205.pdf PDF
J-14_Financial_Data_Requirements.pdf PDF
ACN6353.pdf PDF
J-1_ARSV_Specification_1.0_FINAL_6-14-18_signed.pdf PDF
J-5_Commercial_Warranty.pdf PDF
J-15_Price_Breakdown_Worksheet.xlsx XLSX spreadsheet
J-11_Offeror_Question_Submittal_Form.pdf PDF
ACN6346.pdf PDF
ACN6347.pdf PDF
J-10_Preservation_Instructions_Ver_7.0_FINAL_6-14-18.pdf PDF
ACN4577.pdf PDF
ACN6350.pdf PDF
ACN4571.pdf PDF
ACN6351.pdf PDF
ACN4583.pdf PDF
ACN6345.pdf PDF
ACN6088.pdf PDF
ACN6348.pdf PDF
Solicitation_N00024-19-R-2205_01NOV18.pdf PDF
ACN6349.pdf PDF
ACN4565.pdf PDF
ACN4572.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Data Requirements List, Attachment J-2 Solicitation: N00024-19-R-2205

AUTEC RANGE SUPPORT VESSEL (ARSV)

Data Requirements List Attachment J-2

18 June 2018

Prepared by Naval Sea Systems Command

1333 Isaac Hull Ave. SE Washington Navy Yard, DC 20376-2101

DESTRUCTION NOTICE - . Controlled Unclassified Information (CUI), (e.g., FOUO, Distribution Statement controlled) shall be destroyed by any methods that will prevent disclosure of contents or reconstruction of the document.

DISTRIBUTION STATEMENT A: Approved for public release: distribution unlimited.

AUTEC RANGE SUPPORT VESSEL

DATA REQUIREMENTS

CONTRACT NO.: N00024-19-R-2205 CONTRACTOR: TBD

ii

FOREWORD

The Data Requirements List (DRL) identifies Contractor Data Item requirements in support of the acquisition and conversion of the AUTEC Range Support Vessel (ARSV). This foreword provides direction to clarify administrative and procedural questions. Emergent issues that are not addressed herein or otherwise provided for in source documents should be referred to Program Executive Office Ships PMS325G.

I. CONTENT AND FORMAT OF SUBMITTALS

All submittals shall be prepared in the Contractor's format unless otherwise specified in the specific data item. Data item submittals shall be clear, legible, and prepared in the English language. Engineering drawings and associated lists shall be as identified in Engineering Drawing and Related Documentation Practices, American Society of Mechanical Engineers (ASME) Y14.100; Types and Applications of Engineering Drawings, ASME Y14.24 Associated Lists, ASME Y14.34 and Revision of Engineering Drawings and Associated Documents, Y14.35M. Calculations and design data shall be provided in metric standard units or in the inch-pound system; the convention for units of measure shall be consistent throughout the documentation.

Data Items shall be assigned a sequential one-character alphabet designation in the Revision Block to signify a change from the previous submittal. Revision letter designations shall be in alphabetical order. The first submittal of any data item shall be identified as Revision "-".

Revisions of submittals shall include a change log or be prepared in a "red line" format to allow for identification of changes from the previous submittal.

Electronic media and digital files shall be compatible with computers using Windows 10™ operating system, unless otherwise specified. The following electronic format products shall be used: Microsoft Office 2013™ , Microsoft Project 2013™, or Adobe 2018 products, unless otherwise specified. Schedules shall be Microsoft Project compatible. Alternative software or versions of software may be used if mutually agreed between the Contractor and the Government.

Electronic files shall not be password protected. All textual PDF files shall be searchable.

Documents shall not be submitted in PDF format unless specified in the specific data item. For documents with no electronic original available, the original document shall be prepared electronically in PDF format. Drawings shall be submitted in an AutoCAD 2018™ compatible format and PDF format, unless otherwise specified, and shall not be in "read only" format.

The first three characters of each digital filename shall be the Contractor's name or acronym. The filename shall include the applicable Data Item number and a Contractor determined designation, followed by a one-character revision letter, as applicable. The first submittal of each data item shall be assigned the revision"-“. Each file extension shall be the three-character default extension automatically assigned by the applicable software when a document is saved. Electronic files shall not be password protected.

iii

All data deliveries shall include a Department of Defense (DoD) Distribution Statement in accordance with DoD Instruction 5230.24. The Contractor shall determine which statement is applicable for the data being delivered.

Each data item submittal shall include the following export restriction:

"WARNING- This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C. Sec 2751 et seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App 2401, et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate per provisions of OPNAVINST 551 0.161, Withholding of Unclassified Technical Data from Public Disclosure, 29 July 1985."

All submittals shall be provided with a cover sheet. Each data item shall be submitted with a separate letter of transmittal. The cover sheet shall provide the following information:

• Contractor's name, correspondence serial number, and actual date of transmittal.

• The Contract Number, Data Item Number, and Data Item Title.

• Applicable revision letter and revision date.

• Electronic media or digital file name and respective file date.

• A brief explanation of the submittal, the reason for a document's change, or a more detailed discussion in the content of the submittal.

• Distribution and quantity of copies being sent (not applicable to data provided at a shared location).

II. SUBMISSION SCHEDULE

The Contractor shall deliver all data requirements in accordance with the DRL.

III. QUALITY CONTROL

The Contractor shall maintain internal quality control to ensure submittals are complete and adequate and should not rely on Government review comments to ensure the technical accuracy of data. The Contractor shall review submittals to ensure accuracy of language, flow, overall readability, as well as proofreading for grammar, spelling, and typographical errors.

IV. ACRONYMS

An alphabetical list of acronyms follows. The list includes those acronyms used most frequently in the Data Requirements List.

iv

ACRONYMS

ABS American Bureau of Shipping ASME American Society of Mechanical Engineers CLIN Contract Line Item Number DAC Days After Contract Award DARC Days After Receipt of Comments DI Data Item(s) DoD Department of Defense DPT Days Prior To DR Design Review DRL Data Requirements List ECP Engineering Change Proposal GP Guaranty Period HVAC Heating, Ventilation, and Air Conditioning IUID Item Unique Identification MCCS Machinery Centralized Control System MTHLY Monthly NECP Non-Engineering Change Proposal O&M Operation and Maintenance OEM Original Equipment Manufacturer OPNAVINST Office of the Chief of Naval Operations Instruction PAC Post Award Conference PLC Programmable Logic Controller PO Purchase Order PR Purchase Request R/ASR Revisions as Required RFV Request for Variance SD Ship Delivery SDS Safety Data Sheet SHML Ship Hazardous Materials List SWBS Ship Work Breakdown Structure T&S Trim and Stability TM Technical Manual TMI Technical Manual Index VRS Vendor Recommended Spares v

V. GLOSSARY

The items listed below are explanations of the headings and blocks on the Data Requirements List (DRL).

1. PROGRAM NAME: The name of the program.

2. CONTRACT NO.: The Procurement Instrument Identification Number (i.e., the contract number, Purchase Request (PR) number, the Request for Proposal number, or other appropriate designator).

3. CLIN: The Contract Line Item Number (CLIN) that is associated with the DRL.

4. CONTRACTOR: The Contractor's name.

5. PREPARED AND APPROVED BY: The name and organization responsible for preparation and approval of the Data Items.

6. DATE: The date the Data Item was approved.

7. BLOCK 1 -DATA ITEM NO.: An identification number to support data item identified in the Statement of Work or Contract.

8. BLOCK 2-DATA ITEM TITLE: The title of the Data Item.

9. BLOCK 3-REFERENCE: The specific location within the Statement of Work or Contract that contains the tasking that generates a requirement for the data.

10. BLOCK 4-DATA DESCRIPTION: Details regarding the Data Item’s content characteristics and format requirements, if applicable.

11. BLOCK 5- APPROVAL/REVIEW REQUIREMENTS: The Government will review the Contractor’s submittal as indicated. The time period required for Government review will be as specified. The Government will comment on Data Items that require Government comment within the timeframe noted. The Government reserves the right to comment on all deliverables. The time period for Government review, identified in the data requirements list, commences at receipt of the data by the Government.

12. BLOCK 6-SUBMITTAL SCHEDULE: The scheduled date for initial data submission, incremental submittals, and resubmittals, as specified. In addition, details regarding Data Item submittal requirements are included. Submittal dates are often based on Contract events. Days identified are calendar days unless otherwise identified. Where scheduled date for data submission falls on a Saturday, Sunday or Federal Government holiday, the submission due date shall be the following Government working day. Revisions and subsequent periodic submissions shall incorporate the resolution of Government comments.

vi

13. BLOCK 7-DISTRIBUTION: Unless otherwise stated, all deliveries shall be in digital format and posted to a shared electronic location or submitted to PMS325G and SEA 05D4 via E-Mail distribution. If deliverables are distributed by posting at a shared location, an E-Mail notification shall be submitted to PMS325G and SEA 05D4. Data provided at a shared location shall meet the requirements for digital copies identified herein. Specific formats and unique delivery requirements are identified in the individual data items.

ADDRESSEE COMPLETE ADDRESS

PMS325G

Assistant Program Manager

Naval Sea Systems Command ATTN: Peter Herrman 1333 Isaac Hull Ave, S.E. MS 2501 Washington Navy Yard, DC 20376-2501 Email: peter.herrman@navy.mil

SEA 05D4

Ship Design Manager

Naval Sea Systems Command ATTN: Jitesh Kerai 1333 Isaac Hull Ave, S.E. MS 5064 Washington Navy Yard, DC 20376-5064 Email: jitesh.kerai@navy,mil CC: jeffrey.e.fink@navy.mil mailto:jitesh.kerai@navy,mil vii

Table of Contents and List of Effective Pages Data Item No. Contract

Reference Data Item

Titles And Subtitles Change Status

DI-001 SOW C-3.042a AGENDAS BASIC DI-002 SOW C-3.042a MEETING MINUTES BASIC DI-003 SOW C-3.042b MASTER SCHEDULE BASIC DI-004 SOW C-3.042c DRY-DOCKING FACILITIES CERTIFICATION REPORT BASIC DI-005 SOW C-3.042d DOCKING INFORMATION BASIC DI-006 SOW C-3.042e SHIP DAMAGE REPORT BASIC DI-007 SOW C-3.045d FIRE AND FLOODING PROTECTION PLAN BASIC DI-008 SOW C-3.070b CLASSIFICATION SOCIETY OR REGULATORY BODY

COMMUNICATIONS

BASIC

DI-009 SOW C-3.070b CLASSIFICATION SOCIETY AND REGULATORY

BODY CERTIFICATES

BASIC

DI-010 SOW C-3.070c INTACT AND DAMAGE STABILITY REPORT BASIC

DI-011 NOT USED

DI-012 SOW C-3.077 NAVSEA HAZARDOUS MATERIAL WAIVER

REQUEST

BASIC

DI-013 SOW C-3.077 SHIP HAZARDOUS MATERIAL LIST BASIC

DI-014 SOW C-3.077 SAFETY DATA SHEETS BASIC

DI-015 SOW C-3.077 LITHIUM BATTERY REPORT BASIC

DI-016 SOW C-3.080 NOT USED BASIC

DI-017 SOW C-3.083 VENDOR AND ABS RECOMMENDED SPARES

LISTINGS

BASIC

DI-018 SOW C-3.085a CONVERSION DRAWINGS AND DOCUMENTATION BASIC DI-019 SOW C-3.085b TECHNICAL DATA PACKAGE BASIC

DI-019-01 SOW C-3.085b HULL LINES AND BODY PLAN BASIC DI-019-02 SOW C-3.085b MIDSHIP AND TYPICAL SECTIONS DRAWING BASIC DI-019-03 SOW C-3.085b SCANTLING PLANS, DECKS, AND PROFILES BASIC DI-019-04 SOW C-3.085b SHELL EXPANSION DRAWING BASIC DI-019-05 SOW C-3.085b MAIN ENGINES, GENERATORS, AND

MISCELLANEOUS FOUNDATIONS

BASIC

DI-019-06 SOW C-3.085b PROPELLER, SHAFT, AND RUDDER OR Z-DRIVE

ARRANGEMENT AND REMOVAL DRAWING

BASIC

DI-019-07 SOW C-3.085b PROPELLER DRAWING BASIC DI-019-08 SOW C-3.085b MAIN CONTROL CONSOLE AND SHIP CONTROL

CONSOLE ARRANGEMENTS

BASIC

DI-019-09 SOW C-3.085b INPUT/OUTPUT SIGNAL LIST BASIC DI-019-10 SOW C-3.085b TOPSIDE ARRANGEMENT DRAWING BASIC DI-019-11 SOW C-3.085b RUNNING, ANCHOR, AND SEARCHLIGHTS PLAN BASIC DI-019-12 SOW C-3.085b ANCHOR HANDLING AND STOWAGE BASIC DI-019-13 SOW C-3.085b ANCHOR AND MOORING DRAWING BASIC DI-019-14 SOW C-3.085b STEERING GEAR ARRANGEMENT AND DETAILS BASIC DI-019-15 SOW C-3.085b RUDDER AND RUDDER STOCK ARRANGEMENT

AND DETAILS

BASIC

DI-019-16 SOW C-3.085b BOW THRUSTER ARRANGEMENT AND DETAILS BASIC DI-019-17 SOW C-3.085b COMPARTMENT ARRANGEMENT AND OUTFITTING

DRAWINGS

BASIC

DI-019-18 SOW C-3.085b DOOR, WINDOW, AND HATCH SCHEDULE BASIC DI-019-19 SOW C-3.085b FLOOR GRATING ARRANGEMENT AND DETAILS BASIC DI-019-20 SOW C-3.085b RAILINGS, STAIRS, AND LADDERS ARRANGEMENT

AND DETAILS

BASIC

DI-019-21 SOW C-3.085b MACHINERY CENTRALIZED CONTROL SYSTEM

DESCRIPTION OF OPERATIONS

BASIC

viii

Reference Data Item

Titles And Subtitles Change Status

DI-019-22 SOW C-3.085b TELEPHONE DIRECTORY BASIC DI-019-23 SOW C-3.085b LIST OF LUBRICANTS BASIC DI-019-24 SOW C-3.085b KEY TAG INDEX BASIC DI-019-25 SOW C-3.085b INSULATION SCHEDULE BASIC DI-019-26 SOW C-3.085b FIRE CONTROL AND SAFETY PLANS BASIC DI-019-27 SOW C-3.085b PERIODIC SAFETY TEST PROCEDURES BASIC DI-019-28 SOW C-3.085b TRIM AND STABILITY BOOKLET BASIC DI-019-29 SOW C-3.085b BOOKLET OF TANK CAPACITY AND SOUNDING

TABLES

BASIC

DI-019-30 NOT USED

DI-019-31 SOW C-3.085b SHIP DRAWING INDEX BASIC DI-019-32 SOW C-3.085b GENERAL ARRANGEMENT OF DECKS BASIC DI-019-33 SOW C-3.085b INBOARD AND OUTBOARD PROFILES BASIC DI-019-34 SOW C-3.085b MACHINERY ARRANGEMENT PLANS BASIC DI-019-35 SOW C-3.085b ELECTRICAL DISTRIBUTION SYSTEM ONE-LINE

DIAGRAM

BASIC

DI-019-36 SOW C-3.085b MAIN AND EMERGENCY SWITCHBOARD ONE-LINE

DIAGRAM

BASIC

DI-019-37 SOW C-3.085b INTERIOR COMMUNICATION SYSTEM BLOCK

WIRING DIAGRAMS SRD

BASIC

DI-019-38 SOW C-3.085b RADIO COMMUNICATIONS BLOCK DIAGRAM SRD BASIC DI-019-39 SOW C-3.085b ELECTRICAL CABLEWAYS AND PENETRATIONS BASIC DI-019-40 SOW C-3.085b NAVIGATION AND COMMUNICATIONS SYSTEM

BLOCK DIAGRAM

BASIC

DI-019-41 SOW C-3.085b MACHINERY ALARM AND MONITORING BLOCK

DIAGRAM

BASIC

DI-019-42 SOW C-3.085b MACHINERY VENTILATION DIAGRAM AND

DETAILS

BASIC

DI-019-43 SOW C-3.085b HVAC DIAGRAMMATIC PLAN AND EQUIPMENT

LIST

BASIC

DI-019-44 SOW C-3.085b HVAC CALCULATIONS BASIC DI-019-45 SOW C-3.085b PIPING SYSTEMS DIAGRAMS BASIC DI-019-46 SOW C-3.085b TECHNICAL MANUAL INDEX BASIC DI-019-47 SOW C-3.085b OEM TECHNICAL MANUALS BASIC DI-019-48 SOW C-3.085b APPLICABLE MARPOL 73/75 PROCEDURES, ARRANGEMENTS AND MANAGEMENT MANUALS

BASIC

DI-020 SOW C-3.085c CRANE FABRICATION DRAWINGS BASIC DI-021 SOW C-3.085d AS-BUILT REVISIONS OF GFI DRAWINGS BASIC

DI-022 SOW C-3.092 TEST PROCEDURES BASIC

DI-023 SOW C-3.092 TEST REPORTS BASIC

DI-024 SOW C-3.094 PRE-DELIVERY INSPECTION AND TRIALS (PDIT)

AGENDAS

BASIC

DI-025 SOW C-3.094 PRE-DELIVERY INSPECTION AND TRIALS (PDIT)

REPORTS

BASIC

DI-026 SOW C-3.095 INFRARED ELECTRICAL SYSTEM SURVEY REPORT BASIC

DI-027 SOW C-3.096 WEIGHTS BASIC

DI-027-01 SOW C-3.096 INITIAL WEIGHT ESTIMATE BASIC

DI-027-02 SOW C-3.096 INTERIM WEIGHT ESTIMATE BASIC

DI-027-03 SOW C-3.096 INTERIM WEIGHT REPORT BASIC

DI-027-04 SOW C-3.096 FINAL WEIGHT REPORT BASIC

ix

Reference Data Item

Titles And Subtitles Change Status

DI-028 SOW C-3.402 CYBERSECURITY INFORMATION FOR CONTROL

SYSTEMS

BASIC

DI-029 SOW C-3.102 ACCESS CONTROL PLAN BASIC

DI-030 SOW C-3.105 ENGINEERING CHANGE PROPOSALS BASIC

DI-031 SOW C-3.105 NON-ENGINEERING CHANGE PROPOSALS BASIC

DI-032 SOW C-3.105 REQUEST FOR VARIANCE BASIC

DI-033 SOW C-3.106 CONTRACT PROBLEM IDENTIFICATION REPORT BASIC

DI-034 SOW C-3.112 ADVERSE ENVIRONMENTAL CONDITION PLAN BASIC

DI-035 SOW C-3.111 PLANT PROTECTION PLAN BASIC

Prepared and Approved by, Diego King Jr., Data Manager, PMS325L 18 June 2018

BLOCK 1-DATA ITEM NO.: DI-001

BLOCK 2-DATA ITEM TITLE: AGENDAS

BLOCK 3-REFERENCE: SOW C-3.042a

BLOCK 4-DATA DESCRIPTION:

1. The Agendas for conferences, reviews, working groups, and other meetings with the Government shall include the following general requirements:

a. Meeting name, date, time, and location

b. Sequential listing of each topic discussed

c. Discussion topics shall include, as applicable:

1) Schedule

2) Progress data

3) Design status

4) Staffing status

5) Regulatory Body approval status

6) Material status

7) Logistics status

8) Engineering change status

9) Test status

10) DRL delivery status

11) Problems/recommendations

12) Action Item status

2. The Post Award Conference (PAC) agenda shall include the same general agenda content listed above with the exception of unique topics shall also be included:

a. Personnel Introductions

b. Organization Overview

1) Contractor Organization Discussion

2) Roles and Responsibilities and Points of Contact

3) Communication – Authorized Contractor Representatives

c. Facilities Overview

1) Site Layout

2) Security and Access Control

d. Planned Detail Design and Conversion Approach

e. Regulatory Bodies Involvement

f. Near Term Schedule

1) Key Events

2) Conferences and Reviews

3) Deliverables

g. Deliverable Requirements List Review

h. Questions

i. Government topics:

1) Personnel Introductions

2) Organization Overview

i. Major Organizations involved in the contract

ii. Roles and Responsibilities and Points of Contact

BLOCK 1-DATA ITEM NO.: DI-001 (Continued)

BLOCK 2-DATA ITEM TITLE: AGENDAS

BLOCK 4-DATA DESCRIPTION: (Continued)

3) Program Overview i.Program Specifics, Contract and Technical Highlights

ii. Government Furnished Property

iii. Government expectations including the demonstration of production readiness iv.Proprietary information/data

4) Communications

i. Authorized Government Representatives

ii. Web Based Project Management System

iii. Email and letter correspondence iv.Regulatory Body correspondence v.Submission of data

j. Questions

3. A copy of each presentation shall be included.

BLOCK 5-APPROVAL/REVIEW REQ.:

Allow 3 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

7 DPT each conference, review, or meeting with the Government; R/ASR 2 DARC.

BLOCK 7-DISTRIBUTION: Addressee QTY

PMS325G 1*

SEA 05D4 1

*Hard copies of presentation materials shall also be provided for each attendee at the meeting.

BLOCK 1-DATA ITEM NO.: DI-002

BLOCK 2-DATA ITEM TITLE: MEETING MINUTES

BLOCK 3-REFERENCE: SOW C-3.042a

BLOCK 4-DATA DESCRIPTION:

1. The Meeting Minutes for conferences, reviews, working groups, and other meetings with the Government shall include:

a. Meeting name, date, time, and location

b. Attendees with contact information

c. Chronological listing of each topic discussed

d. Applicable discussions and concerns

e. Action Items with due date and assignee

f. Listing of documents discussed by document name, document revision, document date, and the digital file name and date.

2. Copies of each presentation and document reviewed shall also be included

Allow 7 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

7 days after each meeting, review, or conference; R/ASR 7 DARC.

BLOCK 7-DISTRIBUTION: Addressee QTY

PMS325G 1

BLOCK 1-DATA ITEM NO.: DI-003

BLOCK 2-DATA ITEM TITLE: MASTER SCHEDULE

BLOCK 3-REFERENCE: SOW C-3.042b

1. The Master Schedule (MS) shall present the overall plan for the design- of the conversion, the conversion, testing, trials, and delivery of the ship. The information will be used to verify attainability of program objectives and evaluate progress. The MS shall depict all activities required for the performance of this Contract. The MS schedule shall present key events, milestones, and the critical path.

2. The MS shall include all efforts required to complete milestones. The MS shall portray in chronological sequence, the actions, events, and requirements with corresponding planned start and completion dates and the actual start and completion dates, which shall be retained on each issue of MS. The MS shall be kept current with schedule modifications and completed tasks. As appropriate, a column, line or space shall be provided for comments, explanation of problems encountered, and any remarks providing clarification shall also be identified.

3. The MS shall be highlighted to show changes from the previous submittal.

BLOCK 5-APPROVAL/REVIEW REQ

Allow 14 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

30 DAC; Updates shall be provided every two weeks.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-004

BLOCK 2-DATA ITEM TITLE: DRY DOCKING FACILITIES CERTIFICATION

REPORT

BLOCK 3-REFERENCE: SOW C-3.042c

The Dry Docking Facilities Certification Report shall include certification of dry docking facilities and methods in accordance with the requirements of the Contract.

BLOCK 5-APPROVAL/REVIEW REQ.:

Allow 14 days for Government review, comment, and approval.

BLOCK 6-SUBMITTAL SCHEDULE:

30 DAC; R/ASR 14 DARC.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-005

BLOCK 2-DATA ITEM TITLE: DOCKING INFORMATION

BLOCK 3-REFERENCE: SOW C-3.042d

BLOCK 4-DATA DESCRIPTION:

1. The Docking Information shall include a description of the dry dock, Dockmaster qualifications, the docking and undocking procedures, docking plan, and supporting calculations.

2. The Docking Plan shall include the locations of all the hull zinc anodes.

Allow 14 days for Government review, comment, and approval.

BLOCK 6-SUBMITTAL SCHEDULE:

30 DPT ship drydocking; R/ASR 14 DARC.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-006

BLOCK 2-DATA ITEM TITLE: SHIP DAMAGE REPORT

BLOCK 3-REFERENCE: SOW C-3.042e

BLOCK 4-DATA DESCRIPTION:

A Ship Damage Report shall document the occurrence, assessment of the cause, damage sustained, personnel injuries, proposed corrective action, and effects on the ship's delivery schedule. Preliminary assessment of possible ship damage below the waterline shall be supported by underwater inspection and documented in the Ship Damage Report.

Allow 3 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

Notification 24 hours after each incident; submit detailed report 7 days after each incident.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-007

BLOCK 2-DATA ITEM TITLE: FIRE AND FLOODING PROTECTION PLAN

BLOCK 3-REFERENCE: SOW C-3.045d

BLOCK 4-DATA DESCRIPTION:

1. The Fire and Flooding Protection Plan shall include, but not be limited to, a damage control organization chart; an outline of protection and detection systems and associated detectors, alarms, and telephones; fire, flooding, evacuation, and watch bills; pertinent instructions outlining the required precautions and actions regarding the following:

a. Flooding, both gross and local, detection, including flooding repair and dewatering procedures during construction.

b. Heavy snow and ice loading, excess firefighting water and flood water, which could cause static instability of the hull when afloat.

c. Welding, cutting, smoking, and electric arcing, and handling of combustible material, such as fuel oil, paint, wood staging and trash that could result in fire ignition.

d. Reduced accessibility on an incomplete ship.

2. The plan shall also contain requirements for inspection by roving patrols, and for controlling fires or flooding in security areas.

3. The plan shall include copies of the fire and flooding protection organization charts and instructions and identify how the fire and flooding protection organization chart and instructions will be kept up to date.

4. The plan shall identify locations of audio/visual alarms and charts in work areas that alert work force of emergency conditions requiring personnel to abandon ship.

5. The Shipbuilder shall maintain a plan of flooding prevention, flooding detection, flooding repair and dewatering capability to protect the ship while it is waterborne and prior to delivery. Fire and flooding protection organization charts and instructions shall be prepared and shall be kept up to date. The schedule for training drill intervals shall be identified in the plan.

Allow 21 days for Government review, comment, and approval.

BLOCK 6-SUBMITTAL SCHEDULE:

30 DAC; R/ASR 10 DARC or change identified in the Contractor’s facilities, organization, instructions, procedures, or construction applications that impact the fire/flooding protection requirements.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-008

BLOCK 2-DATA ITEM TITLE: CLASSIFICATION SOCIETY OR REGULATORY

BODY COMMUNICATIONS

BLOCK 3-REFERENCE: SOW C-3.070b

1. Provide copies of all incoming and outgoing communications on technical matters, including attachments/enclosures, between the Classification Society or Regulatory Bodies and the Contractor or their Subcontractors. Communications shall include letters, emails, and conversation notes.

2. Communications shall be assigned serial numbers and shall be indexed by the serial numbers and applicable dates.

A cross-reference shall be made from Contractor assigned serial numbers to actual incoming communication’s serial numbers, where applicable.

Allow 14 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

3 days after incoming or outgoing communications have occurred.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-009

BLOCK 2-DATA ITEM TITLE: CLASSIFICATION SOCIETY AND REGULATORY

BODY CERTIFICATES

BLOCK 3-REFERENCE: SOW C-3.070b

1. Classification Society and Regulatory Body Certificates, Statements of Fact, and certificates of compliance shall contain the Contract number, a statement that identifies the purpose, applicability of this certification, and verification that the Contractor has complied with the Contract requirements.

2. Where Classification Society and Regulatory Body Certificates of compliance are presented as evidence of quality, such certificates shall indicate that the material or equipment was previously tested and met all performance requirements and shall contain verification data, refer to witnessing inspectors or present other verifiable quality data.

BLOCK 6-SUBMITTAL SCHEDULE:

Copies of certificates shall be submitted 7 days after receipt; original certificates shall be provided 10 DPT SD.

Certification verification data shall be submitted 10 days after request from the Government for copy of the verification of equipment/ test certification.

BLOCK 7-DISTRIBUTION: Addressee QTY

PMS325G 1

SEA 05D4 1

SHIP (via NAVSEA Authorized Representative) 1*

* Originals shall be mounted onboard the ship

BLOCK 1-DATA ITEM NO.: DI-010

BLOCK 2-DATA ITEM TITLE: INTACT AND DAMAGE STABILITY REPORT

BLOCK 3-REFERENCE: SOW C-3.070c

BLOCK 4-DATA DESCRIPTION:

The Intact and Damage Stability Report shall include all calculations required to support the derivation of the intact and damaged allowable KG curves. At a minimum the report shall include the following:

1. Definition of applicable stability criteria in accordance with the Contract.

2. Descriptions and data for the following:

a. Hull form

b. Hydrostatic properties

c. Watertight boundaries and compartmentation

d. Compartment permeabilities

e. Margin line and down flooding point locations

f. Compartments included in each flooding case

g. Cross-flooding arrangements for any cross-connected spaces

3. Operating restrictions and allowable draft and trim range.

4. The maximum allowable KG (or minimum required GM) vs. draft curves to meet intact and damaged stability criteria.

5. Supporting calculations in appendices.

Allow 7 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

30 DPT DR; R/ASR 30 DARC and when the need for change is identified.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-011

BLOCK 2-DATA ITEM TITLE: NOT USED

BLOCK 1-DATA ITEM NO.: DI-012

BLOCK 2-DATA ITEM TITLE: NAVSEA HAZARDOUS MATERIAL WAIVER

REQUEST

BLOCK 3-REFERENCE: SOW C-3.077

1. A NAVSEA Hazardous Material Waiver Request shall be provided for each prohibited substance the Contractor finds necessary to incorporate in the design, conversion, operation, or maintenance of the ship. The request shall contain the following information:

a. Material to be used (identified by the name and Chemical Abstract Service (CAS) Number)

b. A copy of the Safety Data Sheet (SDS) and vendor technical (specification) data sheet showing 100% of the material/product constituents/ingredients. Note: When a supplier will not release to the Contractor an SDS that identifies 100% of the ingredients, the Contractor shall request the supplier enter into a non-disclosure agreement with the Government to release information directly to the Government.

c. Description of each specific shipboard location where the material will be used, including the quantity of material at each location.

d. The material’s intended use and justification for use in the requested application.

e. Measures taken to minimize or eliminate the prohibited substance. Include measures taken to identify substitute materials.

f. Personnel or environmental exposure potential during handling, installation, maintenance, and repair.

1) Identify the frequency that the system will require maintenance or replacement that will result in exposure to the material.

2) Include a description of personnel and/or environmental hazards associated with potential exposure.

g. Control and management measures that will be taken to minimize occupational and environmental exposure to the material prior to delivery of the vessels.

h. Recommend control and management measures to be taken to minimize occupational and environmental exposure to the material after delivery of the vessels while they are in service.

i. Description of ultimate disposal requirements and recommendations for both the material and any associated wastes.

j. Identification of regulations governing the material and associated waste’s distribution in commerce, transportation (including air, sea, and land), use and ultimate disposal.

k. Identification of the hazardous decomposition of off-gas products expected or anticipated during normal use in the material’s intended usage environment and from exposure to heat and fire, as identified by the SDS.

l. Identification of the specific training required by personnel handling, using, installing, packaging, transporting and disposing of the material.

BLOCK 5-APPROVAL/REVIEW REQ.:

Allow 21 days for Government review, comment, and approval.

BLOCK 6-SUBMITTAL SCHEDULE:

30 DPT release for manufacture of related purchase specification material, or when the need to use a Government Prohibited Substance is identified for use during conversion, operation, or maintenance; whichever is earlier. R/ASR 21

DARC.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-013

BLOCK 2-DATA ITEM TITLE: SHIP HAZARDOUS MATERIAL LIST

BLOCK 3-REFERENCE: SOW C-3.077

BLOCK 4-DATA DESCRIPTION:

A Ship Hazardous Materials List (SHML) shall be developed including materials used for conversion and Operation and Maintenance (O&M). The construction materials shall include a detailed summary of all materials (hazardous or otherwise regulated) selected for ship conversion. The O&M materials shall include a detailed summary of all materials (hazardous or otherwise regulated) required to be used during ship operation and maintenance. All consumables to be carried on board ship shall be documented in the ARSV SHML and include types and quantities of each material. The SHML shall identify where all selected materials are used, why the materials were selected, the potential hazards/impacts associated with the materials, the regulations governing the distribution in commerce, transportation, use, and ultimate disposal of the materials and associated wastes, and the quantity and distribution of the materials on board ship. The final SHML shall identify the finalized list of all hazardous or otherwise regulated materials used in the conversion, operation, and maintenance of the ship.

BLOCK 5-APPROVAL/REVIEW REQ.:

Allow 14 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

Initial 30 DPT DR; R/ASR 14 DARC and when the need for change is identified. Final submittal shall be at SD.

BLOCK 7-DISTRIBUTION: Addressee QTY

PMS325G 1

SHIP (via NAVSEA Authorized Representative) 1

BLOCK 1-DATA ITEM NO.: DI-014

BLOCK 2-DATA ITEM TITLE: SAFETY DATA SHEETS

BLOCK 3-REFERENCE: SOW C-3.077

BLOCK 4-DATA DESCRIPTION:

1. All Safety Data Sheets for hazardous materials utilized in the conversion and for operation and maintenance shall be provided.

2. The Safety Data Sheets shall be included in a booklet at sea trials.

Allow 14 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

Individual Safety Data Sheets due 3 days after receipt from vendor. Deliver booklet to the ship NLT 3 DPT Trials.

BLOCK 7-DISTRIBUTION: Addressee QTY

PMS325G

SEA

05D4 1

* Booklet only

BLOCK 1-DATA ITEM NO.: DI-015

BLOCK 2-DATA ITEM TITLE: LITHIUM BATTERY REPORT

BLOCK 3-REFERENCE: SOW C-3.077

The Lithium Battery Report shall include the following applicable information for all lithium batteries.

1. For Category A and Category B lithium batteries, which are defined below, the Lithium Battery Procurement Report shall identify:

a. Battery manufacturer/brand name

b. Model identification (name and number)

c. Electrical description (voltage, ampere-hours capacity, and nominal load profile)

d. Use scenario/environment (e.g., office computer or test set, surface ship)

Category A lithium batteries are batteries that meet the following criteria:

1) Non-rechargeable lithium coin cells;

2) Unmodified, commercial item;

3) Used in a single-cell configuration;

4) Maximum nominal output of 3 Volts; and

5) Maximum rated capacity of 1 ampere-hours (Ah).

Category B lithium batteries are batteries that meet the following criteria:

1) Rechargeable (i.e. secondary) lithium ion batteries;

2) Unmodified, commercial battery for use in electronics and equipment;

3) Used in the device as recommended by the manufacturer;

4) Recharged only by devices expressly designed for recharge of the specific battery in use;

5) No more than four cells in series (less than or equal to 18-Volt output); and

6) Rated for no more than 100 Watt-hours, as listed in the manufacturer’s specification or as calculated by multiplying the capacity in Ah by the maximum working (nominal performance) voltage.

2. For all other lithium batteries that do not meet the criteria of Category A or Category B, the Lithium Battery

Procurement Report shall identify the following items:

a. The Proposed Cell/Battery Design Data :

1) Manufacturer (name, address, phone number)

2) Model number and/or part number

3) Electrical description (voltage, ampere-hour (Ah) capacity, and nominal load profile)

4) Electrical safety devices integral to the cell/battery

5) Cell/battery configuration (cells/batteries in parallel or series)

6) Operating life (shelf life and functional life)

7) Physical dimensions and description (weight, size, geometry, number of cells, battery housing description)

8) Marking indicating battery chemistry

9) Cell and/or battery yield pressure (if unvented, battery/housing room ambient yield pressure)

10) All applicable Safety Data Sheets, Product Information Sheets or equivalent document

11) Cell failure mode (indicating whether a single cell failure can cascade into multiple cell failures

12) Discharge rate

13) Rated cycle-life (versus depth of discharge) and the mean-time-between failures for the cell/battery. This data is only required for batteries that designed to be recharged after use.

14) Discharge and recharge rates including the limiting discharge/charge rates. This data is only required for batteries that designed to be recharged after use.

BLOCK 1-DATA ITEM NO.: DI-015 (Continued)

BLOCK 2-DATA ITEM TITLE: LITHIUM BATTERY REPORT

b. Lithium Battery-Powered System Description:

1) Description of system purpose or function

2) Manufacturer (name, address, phone number)

3) Model number and/or part number and device name

4) Diagram of the system’s overall mechanical interfaces showing battery proximity to other equipment and energetic devices

5) Battery installation (mounting, seals, electrical connectors)

6) Battery housing/container, strength, and free volume

7) Safety features of venting mechanisms (description and estimate of operational venting pressure

8) Current drain (load profile of the system)

9) Block diagram of system interfaces to the battery (electrical and physical)

10) Electrical schematic (showing fuses, blocking diodes, and external power interface)

11) Description of the charger and charge control mechanism, if applicable. (Are cells individually equilibrated, or is the battery charged as a series/parallel string?) Provide information for large form lithium batteries sufficient to support evaluation that features of the charging system related to charging safety have been included in the design, validated, and tested.

12) Description of other controls or mechanisms to enhance battery safety, such as a Battery Management System, software shutdown mechanism, etc.

c. Logistical and Operational Use Data:

1) Packaging. How will system/battery be packaged?

2) Storage facilities. How will system/battery be stored from delivery to disposal?

3) Transportation methods

4) Disposal information

5) Operational use scenario, including:

i. A complete description of how the system/batteries will be handled and used

ii. Location of recharging operations, if applicable

iii. Recovery operations, ashore and afloat, if applicable

iv. Number of units anticipated to be used

v. The sequence of events before the system use/activation/deployment, if applicable

6) Description of the battery change out/replacement plan including the number of batteries needed to support system during deployment and in what storage configuration.

d. Address all safety hazards to co-located systems, platforms, and personnel from operations and carriage identifying and mitigating the risks involved.

BLOCK 6-SUBMITTAL SCHEDULE:

Preliminary list 30 DPT DR; R/ASR 14 DARC and when the need for change is identified.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-017

BLOCK 2-DATA ITEM TITLE: VENDOR AND ABS RECOMMENDED SPARES

LISTINGS

(See Attachment 1 to Data Item No. DI-017)

BLOCK 3-REFERENCE: SOW C-3.083

BLOCK 4-DESCRIPTION:

1. Each Vendor Recommended Spares (VRS) Listings shall contain the OEM recommended spares quantities, including all consumable and expendable items. VRS Listings shall be submitted for each repairable piece of equipment that is required to sustain ship operation and maintenance for a minimum of 720 operating hours. VRS listings shall include any special tools, portable tools, test equipment, any hardware required to support the end item, Programmable Logic Controllers (PLCs), and any associated software and hardware.

2. An ABS Recommended Spares Listing shall be provided in accordance with ABS guidelines.

3. Each listing shall consist of the information for the data fields provided in Attachment 1 to this DI. The listings shall be provided in spreadsheet format.

4. The contents of updated listings shall be cumulative. Any revision to the Listings shall be annotated to identify all changes that have occurred including subsequent submissions up to and including the final submission, including such changes as new items, duplications, quantity changes or part number changes.

BLOCK 6-SUBMITTAL SCHEDULE:

Submit VRS Listings 60 DPT SD; R/ASR 14 DARC or as the need for change is identified.

BLOCK 7-DISTRIBUTION: Addressee QTY

ATTACHMENT 1 TO DI-017 VENDER RECOMMENDED SPARES LISTINGS

FIELD

LENGTH DATA DESCRIPTION

56 MANUFACTURER

32 POINT OF CONTACT (POC)

32 POC EMAIL

10 POC PHONE NUMBER

12 SWBS

48 EQUIPMENT NOMENCLATURE

32 PART NUMBER

48 PART DESCRIPTION

15 SERIAL NUMBER

2 UNIT OF ISSUE

3 MINIMUM REPLACEABLE UNIT (MRU)

6 QTY PER APPLICATION/QTY PER COMPONENT

11.(2) UNIT PRICE

BLOCK 1-DATA ITEM NO.: DI-018

BLOCK 2-DATA ITEM TITLE: CONVERSION DRAWINGS AND DOCUMENTATION

BLOCK 3-REFERENCE: SOW C-3.085a

1. The Conversion Drawings and Documentation shall include all drawings and calculations for the reactivation (if applicable) and conversion of the ship.

2. Drawings shall provide the design information necessary for construction, installations, removals, assembly, disassembly, repair, and maintenance. The drawings shall reflect the end product and provide engineering data sufficient to support conversion of the vessel, logistics support, repair, and maintenance.

3. Drawings shall document directly or reference the following details, as applicable, when essential for conversion of the vessel, logistics support, repair, and maintenance

a. Performance Ratings

b. Dimensional Data

c. Critical Manufacturing Processes and Assembly Sequences

d. Input and Output Characteristics

e. Diagram of Mechanical and Electrical Connections

f. Physical Characteristics

g. Details of Material Identification, including Heat Treatment and Protective Coatings

h. Inspection

i. Verification, Test and Evaluation Criteria

j. Quality Assurance Requirements

k. Hardware Marking Requirements

l. Requirements for Reliability, Maintainability, Environmental Conditioning, and Other Operational or

Functional Tests; and Vendor Substantiation Data when required

4. Drawing title block shall include the following:

a. Drawing Title

b. Drawing Number

c. Drawing Revision Letter

d. Applicable by 3-digit SWBS

e. Drawing Sheet Number and number of sheets

f. Ship's Hull Number

g. Approval Signatures

h. Date

i. Drawing Scale

j. Drawing Size

5. The following shall be included for each set calculations:

a. A cover that identifies the Contract Number, Data Item No., Data Item Title, Applicable Revision, Document Date, and preparing activity information, such as Contractor Name, and Address. Subcontractor reports shall give the name of the prime Contractor. Signature of the responsible company official shall also be included.

b. If approval is required, a statement that the document is being submitted for approval shall also be included in the transmittal.

c. Final submittals shall include a statement on the cover that the document is the final submittal.

d. Report data shall be sufficient to allow assessment of the methodology and verify the results.

BLOCK 1-DATA ITEM NO.: DI-018 (Continued)

BLOCK 2-DATA ITEM TITLE: CONVERSION DRAWINGS AND DOCUMENTATION

6. Calculations and their revisions shall include examples, computer printouts, and worksheets, if used.

7. Engineering Design Calculations and diagrams shall be numbered. Each calculation shall reference applicable drawings by drawing number, drawing revision, and title.

8. Calculations shall allow an independent reviewer to follow each step without difficulty.

9. Calculations including stress diagrams shall prove that the subject has been designed in accordance with the requirements of the Contract. These calculations shall reflect design configuration. All symbols and abbreviations shall be identified and any diagrams, with their associated components, clearly labeled. Calculations shall include the following, where applicable:

a. Assumptions used shall be stated and all references identified.

b. A listing of system and equipment requirements.

c. Applicable sections of ABS and Regulatory Body requirements.

d. Calculation methodology or calculation methodology identification.

e. A summary of calculation results, conclusions, recommendations and actual system, equipment or component sizes incorporated.

f. Design load, working load, test load, assumptions as to manner of loading, such as live, dead, and alternating;

assumed friction, materials (including specification section number), maximum stresses in each part such as compressive, tensile, shearing, and torsional developed by the load, and the factor of safety in each part.

g. Information regarding characteristics under dynamic loading, where applicable, including natural frequencies of vibration, impact, ship motions, and other pertinent data.

h. Summary loads shall include utilization factors and connected loads.

i. Environmental considerations including temperature and motions.

10. Where calculations are performed using a computer program, include a description of the program, input variables, and program assumptions. An explanation of how the computer printout results are used in the design shall be provided which identifies a clear and traceable path of the analysis.

Allow 21 days for Government review and comment.

NLT 30 DPT DR; R/ASR 30 DARC and when the need for change is identified.

BLOCK 7-DISTRIBUTION: Addressee QTY

BLOCK 1-DATA ITEM NO.: DI-019

BLOCK 2-DATA ITEM TITLE: TECHNICAL DATA PACKAGE

(See Attachment 1 to Data Item No. DI-019)

BLOCK 3-REFERENCE: SOW C-3.085b

1. All Technical Data Package items shall reflect the as-built condition of the converted vessel.

2. The Technical Data Package items shall include the same level of content as the current ship’s drawings and data unless otherwise specified in Attachment 1.

Unless otherwise noted in Block 5 of Attachment 1 to this Data Item, allow 7 days for Government review and comment of the initial submittal. Allow 21 days for Government review and comment of the validated “As-Built” version.

BLOCK 6-SUBMITTAL SCHEDULE:

Unless otherwise noted in Block 6 of Attachment 1 to this Data Item, 30 DPT DR; R/ASR 30 DARC and when the need for change is identified. Validated "As-Built" version shall be provided 30 DPT Trials. Revisions shall incorporate resolution of Government comments.

BLOCK 7-DISTRIBUTION: Addressee Preliminary Final

PMS325G 1 1

SEA 05D4 1 1

*Upon completion of incorporating the Government comments to the final delivery, the Technical Data Package shall be delivered as a set in both hard-copy and on a portable hard drive to the ship (via NAVSEA Authorized Representative).

ATTACHMENT 1 TO DATA ITEM NO DI-019 TECHNICAL DATA PACKAGE

ATTACH 1

TO DATA

ITEM NO

(BLOCK 1)

DATA ITEM TITLE AND

REFERENCE (BLOCKS 2

AND 3)

DATA DESCRIPTION

(BLOCK 4)

REVIEW/APPROVAL

REQUIREMENTS

(BLOCK 5)

SUBMITTAL SCHEDULE

(BLOCK 6)

DI-019-01 HULL LINES AND BODY

PLAN

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-02 MIDSHIP AND TYPICAL

SECTIONS DRAWING

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-03 SCANTLING PLANS,

DECKS, AND PROFILES

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-04 SHELL EXPANSION

DRAWING

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-05 MAIN ENGINES,

GENERATORS, AND

MISCELLANEOUS

FOUNDATIONS

Main Engines, Generators, and Miscellaneous Foundations shall show the details of the foundations for the main engines, generators, and miscellaneous equipment. The drawing shall identify materials and dimensions of the foundations.

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-06 PROPELLER, SHAFT, AND

RUDDER OR Z-DRIVE

ARRANGEMENT AND

REMOVAL DRAWING

The Propeller, Shaft, and Rudder or Z-drive Arrangement and Removal drawing shall show the arrangement and clearances and sequences for removal of propellers, shafting, and rudders (or Z-drives).

The drawing shall show lifting points and the associated loads.

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-07 PROPELLER DRAWING The Propeller Drawing shall include all necessary information used for manufacturing and shall completely define the geometry of the propeller including blade section offsets, pitch distribution, expanded area ratio, blade outlines, rake and skew angles, edge and blade thicknesses, anti-singing edge treatments (if required), hub shape and parameters, and shaft interface details.

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-08 MAIN CONTROL

CONSOLE AND SHIP

CONTROL CONSOLE

ARRANGEMENTS

The Main Control Console and Ship Control Console Arrangements shall show a scale drawing of each control console including monitors, keyboards, dedicated devices and controls, and third party equipment that is installed on the consoles. Each item shall be identified, including manufacturer make and model.

Construction details shall include plan elevation views, installation details, and wiring data. Wiring data shall include specification, construction standard, insulation type, temperature rating, and type of shielding, if provided.

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-09 INPUT/OUTPUT SIGNAL

LIST

The MCCS Input/Output Signal List (hardwired, discrete, analog and serial) shall be provided in Excel format. Each point in the database shall be defined in detail including as a minimum connection details(terminations, cable numbers, etc.), signal types and levels, alarm parameters, scaling parameters, units, tag names, descriptions, and protocol (for serial interfaces only).

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-10 TOPSIDE ARRANGEMENT

DRAWING

The Topside Arrangement Drawing shall include top, port and starboard sides, bow, and stern views.

Each view shall depict all topside equipment including masts, stacks, radars, antennas, navigational lights, lifesaving equipment, rails, stanchions, lifelines, boats, winches, vans and deck equipment, tie-down instruments and locations.

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-11 RUNNING, ANCHOR, AND

SEARCHLIGHTS PLAN

A Running, Anchor, and Searchlights Plan shall be provided to identify:

1. Navigation lights, distance fore/aft, and height above the uppermost continuous deck.

2. Searchlight and signal light locations, type, and size.

3. Any sectors, which have blockages.

See Block 5 of DI-019 See Block 6 of DI-019

ATTACHMENT 1 TO DATA ITEM NO DI-019 TECHNICAL DATA PACKAGE

ATTACH 1

TO DATA

ITEM NO

(BLOCK 1)

DATA ITEM TITLE AND

REFERENCE (BLOCKS 2

AND 3)

DATA DESCRIPTION

(BLOCK 4)

REVIEW/APPROVAL

REQUIREMENTS

(BLOCK 5)

SUBMITTAL SCHEDULE

(BLOCK 6)

DI-019-12 ANCHOR HANDLING AND

STOWAGE

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-13 ANCHOR AND MOORING

DRAWING

The Anchor and Mooring Drawing shall demonstrate the orientation of the anchor and mooring systems with storm, breast, and spring lines shown. The drawing shall also illustrate the rigging of lines, bridles, and fittings for mooring to a pier, including the operation of the accommodation ladder, in all expected tidal ranges. The location of hawse pipes, bolsters, chain stoppers, and anchor pockets shall also be shown. The drawing shall list fittings and hawsers, and shall include lengths, sizes, and description of each item used for the anchor and mooring systems.

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-14 STEERING GEAR

ARRANGEMENT AND

DETAILS

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-15 RUDDER AND RUDDER

STOCK ARRANGEMENT

AND DETAILS

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-16 BOW THRUSTER

ARRANGEMENT AND

DETAILS

See Block 5 of DI-019 See Block 6 of DI-019

DI-019-17 COMPARTMENT

ARRANGEMENT AND

OUTFITTING DRAWINGS

The Compartment Arrangement and Outfitting Drawing shall show the interior arrangements of each space except tanks and voids to include compartment arrangements, equipment, joiner work, furnishings, and outfitting. Each compartment shall be labeled with the compartment name and number.