Attachment 14 Deliverable Check Sheet
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specification Reference
| Item |
| Timeframe |
| 085 |
| Construction Drawings |
| Prior to 1st boat construction |
| 085 |
| Technical Data Package |
1. Construction Drawings
2. BOM
3. COTS Manuals
4. OEM Certifications
5. OEM Warranty Duration
6. Test and Trial Reports
7. Master Data Index Preliminary: 30 days prior to PDIT for 1st boat Draft: at PDIT for 1st boat Final: with each boat delivery
| 085 |
| Revised Offsets |
| If applicable, prior to 1st boat construction |
| 092 |
| Test Certifications |
1. OCC Boat Scale Weight
2. LPD-17/EVBSS Boat Scale Weight
3. Trailer Scale Weight
4. Inclining Experiment (1st boat only)
5. Boat and Trailer Tiedown Provisions
6. Fuel Tank Pressure Test
7. Fuel System Pressure Test
8. Forward and Aft Tow Provisions
9. Bow Eye
10. Hoisting Fittings
11. Hoisting Slings
12. LPD-17 Single Point Lift Frame
13. Weapons Foundations
14. Torsional Vibration Analysis 30 days prior to PDIT for 1st boat of each Delivery Order, 5 days prior to shipment for all other boats
| 094 |
| Builders Trials Results |
| Prior to PDIT for 1st boat of each Delivery Order, |
5 days prior to shipment for all other boats
| 094 |
| Notice of PDIT date and agenda/test plan |
| 30 days prior to each PDIT |
| 096 |
| Accepted Weight Estimate (AWE) |
| 45 days after Contract award |
| 096 |
| Periodic Weight Reports (PWR) |
| Midway through the detail design effort, |
At completion of detail design, Midway through construction of the 1st boat, Any point necessary to convey changes significant enough to affect compliance with weight and LCG requirements.
| 096 |
| Scale Weighing Reports |
| 30 days prior to PDIT for 1st boat of each Delivery Order, |
5 days prior to shipment for all other boats
| 096 |
| Final Weight Report (FWR) |
| PDIT for 1st boat |
| 096 |
| QC Weighing Report |
| 10 days after weighing |
| 097 |
| Inclining Experiment Notification |
| 10 days prior to inclining |
| 099 |
| Photographs |
| As completed |
| 100 |
| Lamination Process Procedures Description (LPPD) |
| 14 calendar days prior to start of lamination |
| 100 |
| Inspection System Plan (ISP) |
| 14 calendar days prior to start of lamination |
| 100 |
| Hull Lamination Inspection Notification |
| 30 days prior to removal from mold |
Confirm 10 days prior
| 100 |
| Preconstruction Test Panels |
| Prior to start of 1st boat construction |
| 100 |
| Hull Cutout Test Samples |
| Each boat after cut |
| 166 |
| Inflatable Collar Leak and Overpressure tests |
| With test reports for each boat |