Attachment 14 - Implementation Plan for Item Unique Identification (IUID) of Tangible Items

View the file

Other files for this federal contract opportunity

Other files attached to Amphibious Combat Vehicle (ACV) 1. 1, newest first.
File Type Posted
Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data_-_150130.pdf PDF
Attachment_02_-_COVER_150227.docx DOCX document
Attachment_16_-_Cover.docx DOCX document
Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Attachment_20_-_CM_Plan_ACV-PLN-02001_v1.0_Signed.pdf PDF
Attachment_15__-_ACV_Fielding_Table_(150129).docx DOCX document
Attachment_05_-_COVER.docx DOCX document
Attachment_10.1.xlsx XLSX spreadsheet
Attachment_03_-_Meeting_List_150316.docx DOCX document
Attachment_16.3-TABLE_A-IV.__Combined_Maint_and_Maint_w_Parts_Rqmts.docx DOCX document
Attachment_24_-_Reserved_for_Contract_Data_Assertion_List.docx DOCX document
Attachment_22_-_2015_01_30_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
Section_L_Attachment_3_-_Proposal_Requirements_Cross_Reference_Matrix.xlsx XLSX spreadsheet
Second_Draft_Attachment_09_-_Failure_Definition_Scoring_Criteria_(FDSC).docx DOCX document
Second_Draft_Attachment_10.1_-GFP-GFI_-__12-9-14_V2.docx DOCX document
Second_Draft_Attachment_06.1_-_ACV_CSDR_PLAN_EMD_Contract_Plan_N-14-G-C1.pdf PDF
Second_Draft_Attachment_10_-_COVER_-_GFP_GFI_List.docx DOCX document
Second_Draft_Attachment_05.1_-_ACV_1._1_Integrated_Master_Plan.pdf PDF
Second_Draft_Attachment_04_-_CDRL_Submission_Instructions.docx DOCX document
ACV_CDRLs_Combined_01082015.pdf PDF
Second_Draft_Attachment_17_-_Technical_Data_Package.docx DOCX document
Second_Draft_Cover_Letter.pdf PDF
Second_Draft_Attachment_05_-_COVER.docx DOCX document
Second_Draft_Attachment_01.1_-_MASTER_SOW_-_150108.docx DOCX document
Second_Draft_Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data.docx DOCX document
Second_Draft_Attachment_23_-_COVER.docx DOCX document
Second_Draft_Attachment_16_-_Technical_Manual_Contract_Requirement_(TMCR).docx DOCX document
Second_Draft_Attachment_22.1_-_2014_12_10_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
SECTION_M_dated_6_Nov_2014_M.7_updated_-_Final.docx DOCX document
Attachment_23_-_COVER.docx DOCX document
Attachment_22_-_COVER.docx DOCX document
Attachment_06.2_ACV_CSDR_Contract_Plan_RDTEN_-_EMD_Phase.pdf PDF
Attachment_01_141105_-_MASTER_SOW_-_For_RFP_First_Draft_Release.docx DOCX document
Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data.docx DOCX document
Attachment_18_-_COVER_-_Ships_Loading_Characteristics_Pamphlet_(SLCP).docx DOCX document
Attachment_24_-_COVER_-_RWS_ICD.docx DOCX document
Attachment_15__-_ACV_Fielding_Table.docx DOCX document
Attachment_04.1_-_CDRL_Submission_Instructions_(CDRL_List).xlsx XLSX spreadsheet
Attachment_04_-_CDRL_Submission_Instructions_.docx DOCX document
Attachment_20_-_Configuration_Management_Plan_(CMP).docx DOCX document
Attachment_22_-_ACV__Integrated_Program_Plan.pptx PPTX presentation
Attachment_06.1_ACV_CSDR_Program_Plan.pdf PDF
Attachment_16_-_Technical_Manual_Contract_Requirement_(TMCR).docx DOCX document
Attachment_05_-_ACV_1._1_Integrated_Master_Plan.pdf PDF
Attachment_05_-_COVER_-_ACV_1.1_Integrated_Master_Plan.docx DOCX document
Attachment_12_-_COVER_-_Concept_of_Employment_(COE).docx DOCX document
SECTION_M_dated_5_Nov_2014_-_Final.docx DOCX document
Attachment_11_-_Test_Schedules_and_Test_Locations.docx DOCX document
Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Attachment_10_-_COVER_-_Government_Furnished_Equipment_(GFE)___Government_Furnished_Information_(GFI)_List.docx DOCX document
Show all 50

Amphibious Combat Vehicle (ACV) 1. 1 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 14 Implementation Plan for Item Unique Identification (IUID) of Tangible Items Document Identification Number ACV-PLN-04003 V1.0 18 Sep 2014

IMPLEMENTATION PLAN (IP)

FOR

ITEM UNIQUE IDENTIFICATION (IUID) OF TANGIBLE ITEMS

AMPHIBIOUS COMBAT VEHICLE (ACV)

PROGRAM MANAGER

ADVANCED AMPHIBIOUS ASSAULT (PM AAA)

PROGRAM EXECUTIVE OFFICER LAND SYSTEMS (PEO LS)

ACV-PLN-04003 V1.0

18 Sep 2014

Implementation Plan (IP) for Item Unique Identification (IUID) Of Tangible Items Program System Name:

Amphibious Combat Vehicle ACV Nomenclature:

Amphibious Combat Vehicle Acquisition Category (ACAT):

ACAT 1(TBD)

Table of Authorized Material Control Number:

TBD

NSN:

TBD

Legacy or New:

New Date of Plan:

9 Sep 2014 Principal End Items Covered in Plan:

ACV

Program Manager:

John Garner Program Office:

PM AAA

Email:

john.garner@usmc.mil Telephone Number:

703-784-1381

Product Director:

Lt Col Kirk Mullins Program Office:

PM AAA

Email:

kirk.mullins@usmc.mil Telephone Number:

703-784-2783

IUID Point of Contact:

Candido (Ken) Higareda Program Office:

PM AAA

Email:

candido.higareda@usmc.mil Telephone Number:

703-784-1274

SUBMITTED BY

______________________________________________________
Richard M. JensenDate

Product Support Manager (PSM) Amphibious Combat Vehicle ACV

CONCURRENCE

_______________________________________________________
Lt Col Kirk MullinsDate

Product Manager Amphibious Combat Vehicle ACV

APPROVAL

_______________________________________________________
John GarnerDate

Program Manager Advanced Amphibious Assault (PM AAA) Program Executive Office – Land Systems

_______________________________________________________
Judith SchutrumDate

IUID Champion Assistant Commander Acquisition Logistics and Product Support Marine Corps Systems Command

______________________________________________________
Mary E. LaceyDate

Deputy Assistant Secretary of the Navy Research, Development, Test and Evaluation

Date

Revision
Reason for Change
Entered by:
18 Sep 2014
1.0
Initial Version
Candido Higareda

Refer questions concerning this IUID Plan to Mr. Candido (Ken) Higareda, Supply Chain Manager, Program Manager Advanced Amphibious Assault, Program Executive Officer Land Systems, Quantico, VA. 703-784-1274, candido.higareda@usmc.mil.

TABLE OF CONTENTS

1.0System Description1
1.1Description.1
1.2Program Development Life Cycle.1
1.3Integrated Components.1
1.4Overarching Program.1
2.0References.1
3.0Exception and Approval Documentation.2
4.0Overall IUID Implementation Strategy.3
4.1Current and Future Contracts.3
4.2Legacy Systems.3
4.3Depot Manufactured Items and Plant Equipment.3
4.4Process for Entry of UII and Pedigree Data into the IUID Registry.3
4.5Technical Documentation Strategy.3
4.6Engineering Change Proposal (ECP).4
4.7Government Furnished Property (GFP).4
5.0IUID Related Actions to Improve or Enhance Business Processes.4
6.0Radio Frequency Identification (RFID) Application4
7.0Metrics. System is in T&D Phase and the contract is pending.4
7.1Measures of Success.4
8.0Element Dates.5
8.1Preparation Activities.5
8.2Implementation/Execution Activities.5
8.3Capability Achieved (physical marking & ability to transfer Pedigree data to Registry).6
9.0Key Program Trigger Events for Physical Marking of UIIs on Legacy and GFP Items.6
10.0Program Manager’s IUID Related Budget.6

LIST OF APPENDICES

APPENDIX A:ACV IUID Marked Components………………………………
7
APPENDIX B:Acronyms…………………………………………………………..
8
M67854-15-R-0001
Section J

ii System Description Description.

The Amphibious Combat Vehicle (ACV) is an armored, wheeled vehicle that maneuvers adjacent to the surface assault elements of the landing force from assault shipping during amphibious operations to inland objectives. It also conducts mechanized operations and related combat support in subsequent operations ashore. The ACV will augment the AAV7A1 Family of Vehicles currently in the fleet.

Program Development Life Cycle.

The ACV is a new acquisition program, Engineering and Manufacturing Development (EMD) Phase, focused on a non-developmental solution with integration of Government Furnished Equipment (GFE) to meet capability objectives. Life cycle management will conform to existing USMC expeditionary support doctrines, policies, and procedures to the maximum extent possible. ACV production is planned to start in Fiscal Year (FY) 2018 with an Approved Acquisition Objective (AAO) of 204 vehicles. Initial Operational Capability (IOC) is planned for FY 2020, followed by Full Operational Capability (FOC) projected in FY 2023. Throughout the ACV product life cycle, PM AAA intends to use Item Unique Identification (IUID) information to enhance management and tracking of marked assets. This information will be used to support supply chain accountability, financial accounting, property accountability, and to provide material history information.

Integrated Components.

Items meeting the IUID marking criteria will be identified in Appendix A of this plan.

Overarching Program.

There is no overarching program associated with the ACV.

References.

a) DODI 8320.04, “Item Unique Identification (IUID) Standards for Tangible Personal Property”, June 16, 2008

b) DoDI 4161.02, “Accountability and Management of Government Contract Property, April 27, 2012”

c) SECNAVINST 4440.34, “Implementation of Item Unique Identification within the Department of the Navy”, Dec. 22, 2009

d) MCO 4410.28, “Item Unique Identification (IUID) of Ground Equipment” Feb. 1, 2010

e) DFARS 211.274, “Item Identification and Valuation Requirements”

f) DFARS, Clause 252.211-7003, “Item Identification and Valuation,” June 2011, update

g) DFARS, Clause 252.211-7007, “Reporting of Government-Furnished Property,” August 2012, update

h) DFARS, Clause 252.245-7001, "Tagging, Labeling, and Marking of Government Furnished Property,” April 2012, update

i) DFARS, Clause 252.245-7002, "Reporting Loss of Government Property,” August 2011

j) DFARS, Clause 252.245-7003, "Contractor Property Management System Administration,” August 2011

k) DFARS, Clause 252.245-7004, "Reporting, Reutilization, and Disposal,” August 2011

l) DFARS, Clause 252.246-7005, "Notice of Warranty Tracking of Serialized Items,” June 2011

m) DFARS, Clause 252.246-7006, "Warranty Tracking of Serialized Items,” June 2011

n) OSD DPAP Memorandum, “Implementation of DFARS Provision and Clause for Warranty Tracking of Serialized Items,” April 12, 2012

o) MIL-STD-130N, “Department of Defense Standard Practice – Identification Marking of U.S. Government Military Property”, Nov. 16, 2012

p) Program Manager’s Planning Road Map For Implementing Item Unique Identification, 10 June 2005

q) OSD IUID Policies and Regulations

r) OSD IUID Guides Exception and Approval Documentation.

N/A

Overall IUID Implementation Strategy.

The ACV vehicles and Secondary Repairables (SECREPs) will be marked and registered by the vendor prior to delivery. The Defense Contract Management Agency will validate the Unique Item Identifier (UII) during acceptance. ACVs with missing or damaged UIIs will have the original UII reapplied by the Contractor Logistic Support (CLS) during maintenance and inspection per the contract.

ACV IUID marks will be placed on the system data plate in accordance with MIL-STD-130N and any applicable directives. The UII will be a construct 2. The UII will be encoded into a 2D machine readable data matrix on the data plate and will include associated human readable information. The location of data plates will be chosen to ensure readability during normal operational use. All IUID data plates will be permanently affixed and will withstand and perform within the same environmental conditions as the ACV.

Current and Future Contracts.

All new contracts for procurement and maintenance will include the DFARS Clause 252-211-7003.

Legacy Systems.

N/A Depot Manufactured Items and Plant Equipment.

N/A Process for Entry of UII and Pedigree Data into the IUID Registry.

The vendor will be responsible for registering the UIIs and associated information in the IUID Registry through Wide Area Workflow.

Technical Documentation Strategy.

The vendor will develop the engineering drawings with the marking information and the In-Service Engineering Agent will review to ensure marking specifications meet MIL-STD-130N requirements and do not affect the form, fit, or function of the system . The Program Manager will maintain the documentation and will use the documentation to assist with marking similar items.

Engineering Change Proposal (ECP).

An ECP may require changes to IUID marking methods and location. During the development of an ECP, the IUID Implementation Plan and marking information may be updated if new items are identified that meet marking criteria; there is a change to the location or mark construct; or items are identified that no longer require a UII.

Government Furnished Property (GFP).

If GFP is identified for this system, then GFP meeting IUID marking criteria will be properly marked and registered by the vendor prior to delivery to the Contractor. Any GFP delivered unmarked will be identified to PM AAA. PM AAA will coordinate marking with the CLS Contractor.

IUID Related Actions to Improve or Enhance Business Processes.

When the Marine Corps’ enterprise Automated Information System (AIS) solution becomes available, the program office will provide UII data into the system and exploit the capabilities of the UII in the areas of maintenance and supply support. There is no process reengineering required at this time. The Program Office will continue to monitor existing and future business processes to ensure compatibility is achieved with cross program/cross service AISs.

Radio Frequency Identification (RFID) Application Per reference DOD 4140.1-R, Navy Standard Operating Procedure -3692 (ILA Handbook), DFARS Clause 252.211-7006 252.211-7600, and MCO 4000.51B, it was determined that RFID requirements are currently not applicable to the ACV Program. The ACV Program will stay engaged in RFID policy and processes and will readdress the requirement as necessary.

Metrics. System is in Technology Maturation and Risk Reduction (TM&RR) Phase and the contract is pending.

Measures of Success.

What is the Systems Approved Acquisition Objective (AAO):
204
What quantity of the AAO is Funded/Fielded:
0/0
Number of items requiring IUID to include integrated components:
TBD
Percent of items assigned a UII reported to the IUID Registry (total items registered/number of items requiring IUID):
0%
Percent of total items marked with a IUID compliant Data Matrix (total items marked/total items requiring IUID):
0%
Percent of new contracts including the IUID clause:
N/A
Percent of existing contracts modified for IUID requirements:
N/A

Element Dates.

Preparation Activities.
Start Date
Completion Date
Priority of IUID/associated data transfer established
2014
2014
Listing of items requiring IUID completed for each application priority
TBD
TBD
IUID marking strategy and Rough Order of Magnitude (ROM) estimates completed
TBD
TBD
Cross Program/Service AIS integration strategy studies and ROM estimates completed
N/A
N/A
Budget for IUID implementation submitted
N/A
N/A
Implementation/Execution Activities.
Start Date
Completion Date
Legacy contracts (issued prior to 1 Jan 2004) modified
N/A
N/A
Key program trigger event (physical marking of items) identified (i.e., Milestone "C", Upon instruction for maintenance)
N/A
N/A
Progress Reviews
TBD
TBD
Capability Achieved (physical marking & ability to transfer Pedigree data to Registry).
Yes/No
Completion Date
All New Solicitations include IUID Requirements per DFARS Clause (Jan 04)
No
TBD
Legacy Contracts Modified
N/A
N/A
Property Assigned UIIs
No
TBD
GFP (Any equipment located at the Contractors facility requiring UII)
N/A
N/A
Items in operational use
N/A
N/A
Items in inventory (Inventory Control Points), Supply Depots, etc.)
N/A
N/A
Depot maintenance & manufactured items achieved
N/A
N/A
IUID capable AIS
No
TBD

Key Program Trigger Events for Physical Marking of UIIs on Legacy and GFP Items.

N/A Program Manager’s IUID Related Budget.

IUID funding will be incorporated in the ACV contracts and Statements of Work for this system.

APPENDIX A

ACV IUID Marked Components TBD

NSN/Part #
Nomenclature (include SECREPS)
Entity marking
Qty to Mark
Location of mark
Total Components to IUID Mark
xx,xxx

APPENDIX B

Acronyms

AAO
Approved Acquisition Objective
ACAT
Acquisition Category
ACV
Amphibious Combat Vehicle
AIS
Automated Information System
DFARS
Defense Federal Acquisition Regulation Supplement
DODI
Department of Defense Instruction
DPAP
Defense Procurement and Acquisition Policy
ECP
Engineering Change Proposal
EMD
Engineering and Manufacturing Development
FY
Fiscal Year
GFP
Government Furnished Property
HQMC
Headquarters Marine Corps
IAW
In Accordance With
IOC
Initial Operational Capability
IP
Implementation Plan
IUID
Item Unique Identification
MCO
Marine Corps Order
MIL
Military
N/A
Not Applicable
NSN
National Stock Number
OSD
Office of the Secretary of Defense
PEI
Principal End Item
PEO LS
Program Executive Office Land Systems
PM AAA
Program Manager Advanced Amphibious Assault
PSM
Product Support Manager
RFID
Radio Frequency Identification
ROM
Rough Order of Magnitude
SECNAVINST
Secretary of the Navy Instruction
SECREPs
Secondary Repairables
STD
Standard
TBD
To Be Determined
TM&RR
Technology Maturation and Risk Reduction
UII
Unique Item Identifier
USMC
United States Marine Corps

image1.jpeg

File details come from the government source that posted it. Updated .