This Request for Proposal from the U.S. Agency for International Development Malawi seeks proposals to construct 51 community day secondary schools across 18 districts in Malawi. Offerors may bid on constructing schools in one or both of the two large lots containing 19-20 schools each, with these lots reserved for Malawian firms. Offerors may also bid on one or both of the two smaller lots of 6 schools each, which are open to international competition. Proposals are due by the closing date and time specified in Section L, with contracts to be awarded for a 25 month period comprising 13 months for construction and a 12 month warranty period. The solicitation also outlines requirements for offeror capacity and pricing terms.
View the file
Other files for this federal contract opportunity
Show all 50
Secondary Education Expansion for Development (SEED) Rural Group 2 Activity has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EMMP TEMPLATE INSTRUCTIONS
(These are template instructions; please delete this page as you finalize this document).
Background:
This standardized template is part of a broader initiative to harmonize application of 22 CFR 216 across USAID. It also serves as an important step towards moving to an online Environmental Compliance System (ECS) which will be integrated with the Development Information System (DIS).
This template is used for:
1. This template is to be used to document the Environmental Mitigation and Monitoring Plan for any project/activity for which the Initial Environmental Examination or Environmental Assessment specified development of an EMMP as a requirement of implementation.
How to use this template:
1. The first page is standard metadata utilized in the ECD and planned DIS system, please do not alter the fields. Enter as much of the information as is known at the time of drafting.
2. On subsequent pages, there are embedded (screen tips) instructions to assist the writer. To see the instructions, hover over the red underlined text. The embedded instructions are intended to streamline the paper template and to simulate the online system. Please ignore reference to “Control+Click to follow link” within the screen tips.
3. All headings and existing text are standard. Please refrain for editing.
4. Yellow highlighted text may be updated and/or deleted as appropriate. Please remove all yellow highlighting as you finalize the document.
5. Be sure no PII information is contained within the document prior to submitting for BEO approval.
6. Delete this page as you finalize this document.
Reminder: Mission Environmental Officers, Regional Environmental Officers, and Bureau Environmental Officers are resources for USAID staff developing projects and compliance documents. Please engage them early and often. Additional guidance and help is also available at https://www.usaid.gov/environmental-procedures.
USAID’s Environmental Compliance Database of approved 22 CFR 216 documentation provides examples of approved RCEs and other environmental compliance documents, which may assist with language for similar projects.
Revision Date: March 2019 Version: 3.1 Responsible Office: E3/AA File Name: Template_EMMP BUREAU/MISSION/Project USAID 216 ACRO Template Version 2, March 2018
ENVIRONMENTAL MITIGATION AND MONITORING PLAN (EMMP)
Project/Activity Data
| Project/Activity Name: |
| Malawi Secondary Education Expansion for Development (SEED) Rural Group 2 Construction Project |
Lot X
| Geographic Location(s) (Country/Region): |
| Name of Site |
Name of District Malawi
| Implementation Start/End Dates: |
| FY 2021 – FY 2023 |
| Contract/Award Number: |
| TBD |
| Implementing Partner(s): |
| Contractor Name - TBD |
Tracking ID:
| Tracking ID/link of Related IEE: |
| Malawi Secondary Education Expansion for Development (SEED) IEE, approved 12/18/2017: |
http://gemini.info.usaid.gov/document.php?doc_id=50453
Malawi Development Objective 2 IEE, approved 07/28/2021:
| Tracking ID/link of Other, Related Analyses: |
| This EMMP is complemented by the SEED CMC EMMP, |
submitted by Tetra Tech under a separate cover. The SEED CMC EMMP contains pre-construction environmental activities such as site selection process, land tenure documents, social considerations, climate and environmental considerations, design standards, pre-construction risk assessment, and other requirements conducted in accordance with the SEED IEE. This EMMP and the SEED CMC EMMP are to be reviewed together when evaluating environmental compliance for this Activity.
Organizational/Administrative Data Implementing Operating Unit(s):
(e.g. Mission or Bureau or Office) USAID/Malawi
| Lead BEO Bureau: |
| USAID/Africa (AFR) Bureau Environmental Officer (BEO): Brian Hirsch |
| Prepared by: |
| Contractor Name - TBD |
| Date Prepared: |
| Date |
| Submitted by: |
| Contractor Name - TBD |
| Date Submitted: |
| Date |
Environmental Compliance Review Data
| Analysis Type: |
| EMMP for SEED Rural Group 2 Construction Services |
| Additional Analyses/Reporting Required: |
| EMMR |
Purpose Environmental Mitigation and Monitoring Plans (EMMPs) are required for USAID-funded projects, as specified in ADS 204, when the 22 CFR 216 documentation governing the project (e.g. the Initial Environmental Examination (IEE)) specifies mitigation measures are needed. EMMPs are in important tool for translating applicable IEE conditions and mitigation measures into specific, implementable, and verifiable actions.
An EMMP is an action plan that clearly defines:
1. Mitigation measures. Actions that reduce or eliminate potential negative environmental impacts resulting directly or indirectly from a particular project or activity, including environmental limiting factors that constrain development.
2. Monitoring indicators.[footnoteRef:1] Criteria that demonstrate whether mitigation measures are suitable and implemented effectively. [1: Note: Monitoring indicators differ from performance indicators, which are the measures that USAID uses to detect progress towards the results included in a Results Framework.]
3. Monitoring/reporting frequency. Timeframes for appropriately monitoring the effectiveness of each specific action.
4. Responsible parties. Appropriate, knowledgeable positions assigned to each specific action.
5. Field Monitoring/Issues. Field monitoring needs to be adequately addressed i.e. monitoring dates, observations, issues identified and resolution. This field is primarily for documentation during implementation.
Generally, EMMPs are developed by the IP (and updated at least annually) in conjunction with the Annual Work Plan. Some IEEs include a general EMMP, in such instances it is incumbent on the IP to tailor the general EMMP once activities are fully defined. Responsibility for ensuring IPs develop appropriate EMMPs and budget for their implementation rest with USAID CORs/AORs.
An EMMP is a living document. It should be reviewed against the IEE and updated/tailored as needed over the life of implementation, e.g. when new sites are identified or changes in scope are made through award modifications and IEE Amendments.
1.0 Project/Activity Summary
The SEED Rural Group 2 Construction Services Project is a school infrastructure construction project to build 51 new community day secondary schools (CDSS) in 18 Districts in Malawi. The first year of the the project includes procurement, construction, installation, and handover of the new school infrastruture and the second year includes a one year warranty period during which time the contractor will correct any defects from construction.
The construction scope of work at each new school includes two classroom blocks with administration space; one science classroom with administration space; staff, boy and girl pit latrines; two teacher houses with latrines, and a borehole with handpump. [Name of construction contractor] is responsible to provide the labor, eqipment, materials, tools, and machinery appropriate for the scope of work and to complete quality work and build using quality materials. [Name of construction contractor] is responsible to provide management, supervision, and quality assurance for the during of the project to ensure the work is done according to contract and compliant with environemntal, health & safety, and other project requirements. [Name of construction contractor] is responsible to conduct quality control testing, install environmental control measures, and other complimentary tasks to the consturction work.
General activities included at each site are:
1. Mobilization – includes assembling and moving the project site team, eqiupment, tools, and initial materials to the site; establishing project signage, and completing early deliverables.
2. Site Work – the first major activity once the contractor is on site and includes site clearing, grading and leveling of the land, preparing the site for the new buildings, preparing the site for the stormwater drainage infrastructure when required.
3. Construction Work– includes building the new school buildings and pit latrines. Work includes subsurface foundation work, floor slabs, and building walls, truss and roof installation, window/doors, electrical conduit, final finishing work for each building, interior and exterior.
4. Borehole – includes drilling and developing a borehole and installing a manual hand pump
5. Project Management – the administrative tasks, procurement of long lead and ongoing materials, construction site management and supervision, and quality control and assurance.
2.0 Site Specific Information
Site specific environmental mitigation measures will be developed durign mobilization and prior to the start of site clearing. Each site will follow the typical environmental mitigation measures highlighted in Section 1.0. One example is, each site must be establish a sediment control silt fence and other measures identified in the construction drawings to protect against erosion and sediment control. These measures must be in place prior to the start of site clearing.
Environmental mitigation measures proposed for the SEED Rural Group 2 Construction Services Project are typical to low risk, rural, construction sites. Typical construction environmental measures are outlined in the project EMMP. Typical construction environmental measures are summarized, but are not limited to, the following:
1. Erosion and sediment control of the site during construction phase
2. Use of best practices when clearing the site, excavating and stock piling spoils, and other mass earth work activities
3. Proper maintenance, operation, and repair of construction tools, equipment, and machinery
4. Minimizing impact of the construction site to the community through dust control, maintaining agreed working hours, keeping loud work to a minimum
5. Implement correct health and safety measures including PPE, emergency response plans, and site safety protocol and communication
6. Traffic control and site access control of local community and visitor Site specific or special conditions assessed on a site by site basis are included in Section 2.0. Special conditions may include a school site that is near a protected water way, swamp, protected habituate, forested area, etc.
[Contractor to enter site specific environmental measures]
3.0 Annual Reporting
Annually, the Implementing Partner will prepare an Environmental Mitigation and Monitoring Report (EMMR) to be submitted to the Activity Manager/AOR/COR and the USAID Environmental Compliance Database. This report will summarize the effectiveness of mitigation measures, issues encountered, resolutions, and lessons learned. As appropriate, attachments such as site photos, verification of local inspections, product warranties, etc. should also be included.
BUREAU/MISSION/PROJECT
EMMP Template Version 3.1
4.0 EMMP Table for SEED RUral group 2 - Provide name of site
| Project/Activity/Sub-Activity |
| Identified Environmental Aspects or Impacts |
| Mitigation Measure(s) |
| Monitoring Indicator(s) |
| Monitoring and Reporting Frequency |
| Responsible Parties |
| Field Monitoring/Issues/Resolution |
Field monitoring needs to be adequately addressed i.e. monitoring dates, observations, issues identified and resolution
Activity 1:
| Mobilization |
| Risk of negative social impact when construction workers move to a community |
| Provide training on child safeguarding |
| Excessive disturbance at the construction site |
| Construction perimeter fence to be installed per the drawings to minimize disturbance to property not part of the construction work |
Activity 2:
| Site Work |
| Sedimentation of downstream water bodies during site clearing and grading. |
Protecting downstream water bodies from sediment transfer during rain event; measures may include a silt fence or diversions to reduce sediment from work site entering a water body.
Install and maintain the erosion and sediment control plan per the site-specific drawings.
| Erosion of steeper slope cleared during site clearing |
| Erosion control, especially on steeper slopes, through minimizing excavation and clearing and replanting disturbed areas with local vegetation to stabilize steep slopes. |
| Heavy machinery emitted excessive exhaust |
| Reducing the idle time of heavy machine to reduce air pollution from exhaust. |
| Dust causing a nuisance with the local community |
| Dust control resulting in open trench, stockpile and excavation activities through reducing the amount of vegetation cleared, watering dusty conditions, etc. |
| Oil or fluid spill contaminate environment |
| Maintenance of construction equipment to prevent spills of oil and fuels and establish a spill contingency plan to address accidental spills. |
Activity 3:
| Construction work |
| Foundation excavation |
| Protecting excavation stockpile in order to control sediment transfer during rain event; measures may include reducing the amount of time the stockpile is present, covering stockpile, reducing time trench is open, etc. |
Using care while excavating not to collide with underground sanitary infrastructure such as septic tank or sewage line.
| Waste generated during construction and site clearing |
| Minimize construction waste and dispose waste in an approved manner. |
| Injury and accidents of construction workers |
| Implement personal protection measures for each employee and monitor health and safety requirements. Establish and maintain emergency response protocol and contact personnel. |
| Site safety for both construction works, community members and passing vehicles |
| Traffic control as necessary. |
| Loud construction site a nuisance to the community |
| Noise control, limiting work to business hours and workdays. |
Activity 4:
| Borehole |
| Contaminated borehole during installation |
| Following drilling specifications and best practices. |
Develop the well correctly and complete the well cap per the plan to prevent contamination from surface
| Poor water quality supplied from ground water |
| Water quality tests will be conducted by a Third party, funded through the SEED CMC Project |
| Hand pump breaks in the first year due to misuse |
| Provide hand pump O&M training to the School Management Committee. |
Provide spare parts at project handover.
Activity 5:
| Project Management |
| Poor quality work and materials. |
| Provide pro-active and engagement management |
| Poor health and safety conditions on site |
| Establish a project culture that values health and safety and provide training and refresher training and tool talks frequently during construction |
Add rows as needed
USAID Approval of EMMP
Approval:
[NAME], Activity Manager/A/COR [required]
Date
Clearance:
[NAME], Mission Environmental Officer [as appropriate]
Date
DISTRIBUTION: