ITB-216999219_Infusion Center MIscellaneous Renovations_ Addendum 001.pdf

PDF 1 MB Posted

Attached to
J. E Smith Library – Chiller Replacement
Solicitation number
ECSU 2027-200
Issued by
Tolland County, Connecticut

About this file

This is an Invitation to Bid (ITB) addendum for the University of Connecticut Health Center's Infusion Center Miscellaneous Renovations project (ITB-216999219, Project 26-013), issued July 29, 2026. The addendum addresses supplier questions and provides clarifications and revisions to the original bid documents for renovation work at the UConn Health CT Tower Level 6 Ambulatory Care Infusion Unit located at 263 Farmington Avenue, Farmington, Connecticut. The scope of work includes miscellaneous renovations to infusion center areas, including demolition, new wall construction, equipment storage modifications, plumbing and fixture installations, electrical and lighting control systems, and finishing work across multiple patient care areas and support spaces. The original bid due date is August 7, 2026 at 2:00 p.m. Bidders were required to sign and return the addendum with their proposals. The addendum clarifies structural drawing attachments, confirms no alternates are included in the bid (revised bid form provided), provides additional information on light fixtures and pillow speaker locations, establishes Infection Control Risk Assessment (ICRA) protocols for work scheduling and containment, sets a 120-day timeframe for substantial completion, corrects the contract documents date to July 6, 2026, and specifies construction area environmental control as Type B/Class III. Detailed revisions include specifications for lighting control devices based on a Lutron system compatible with nurse call tie-ins, architectural drawings showing new light fixture and pillow speaker locations, structural details for steel lintels at new wall openings, and mechanical/electrical/plumbing coordination drawings.

The bid documents specify prevailing wage requirements under Connecticut General Statutes Section 31-53, with annual adjustments effective July 1st posted on the Connecticut Department of Labor website. Bidders estimated at $500,000 or greater must obtain pre-qualified status prior to bid submission; smaller projects require submission of a Contractor Qualification Statement. A 10% bid bond with response is required. Work scheduling is restricted in certain areas with weekend-only demolition for the Nurse Station Vitals area and Reception/Waiting area, while infusion room work may occur on weekends when areas are vacant or during normal hours if rooms are taken offline individually. All work requires isolation, HEPA filtration, and personnel protective measures including bunny suits or HEPA vac clothing. The bid form includes a Schedule of Values subdivided by construction trade divisions, with subcontractors pricing exceeding $25,000 requiring identification. The University of Connecticut Health Center Procurement Operations & Contracts office, directed by Buyer King Hei Leung (860-679-8174, kleung@uchc.edu), manages the procurement process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID

ADDENDUM

UCHC ITB-10 Form Rev. 2/15

UNIVERSITY OF CONNECTICUT HEALTH CENTER

Procurement Operations & Contracts

263 Farmington Avenue, MC4036 Farmington, CT 06032-4036

Buyer

Telephone Number

E-mail Address

Fax Number

ITB NUMBER: BID DUE DATE: BID DUE TIME: ITB SURETY:

EST

ITB TITLE:

ADDENDUM NUMBER:

DATE ADDENDUM ISSUED:

FOR: The University of Connecticut Health Center

NOTE:

This Addendum must be Signed & Returned with your bid.

Authorized Signature of Bidder Company Name

Approved By: ______________________________________

Buyer (Original Signature on Document in Procurement Files)

UConn Health ITB Section Supplier Question UConn Health Response the structural prints referenced on the drawings are missing. Please provide. Referenced structral drawings attached

The Alternates spec section states to see the bid form to see if there are any alternates. The bid form states “Schedule of Alternates: NOT USED” but then has an alternate #1 listed below. Please advise if there are any alternates on this project. See attached revised Bid Form

UCH Clarification - Additional information provided related to light fixtures Information attached

UCH Clarification - Correction on architectural drawings on new light fixture locations and pillow speakers Drawings attached

UCH Claificationregarding ICRA and working hours.

•Nurse Station Vitals area oAll work occurs over the weekend when infusion area is vacant oArea is isolated during demo and cleaned up prior to re-occupancy oNo ventilation to outside – use hepa machine vented to inside during active work.

•Reception /Waiting area o Demolition work occurs over the weekend when infusion area is vacant oArea is isolated during demo and cleaned up prior to re-occupancy oHard barrier required in waiting area after demolition is complete oRemainder of construction can occur during normal working hours if accessed from Office area.

oNo ventilation to outside – use hepa machine vented to inside during active work.

•Infusion rooms Agreed o work occurs on weekend when infusion area is vacant or during normal working hours if one room is taken off-line at a time odoor to room is kept shut during all work oInduction units should be shut off -otherwise rooms will osealed containers and walk-off mat at each side of door oworkers wear bunny suits or Hepa vac clothing when leaving room

UCH Clarification - Substantiantial Completion: The contractor shall achieve Substantial Completion within 120 days

UCH Calrification - 1.02 Contract Documents date correction July 6, 2026

UCH Clarification - Section 01020 Construction Area Environmental Control to be TypeB/Class III.

UCH Clarification - 01030, 1.02, E - Alternates - Not Used/None

UConn Health ITB-216999219 26-013 CT6 H6003-05 Infusion Center Miscellaneous Renovations

BID FORM Revised 9/1/22

BID FORM Page 1

PROJECT NAME: UConn Health CT Tower Level 6 Ambulatory Care Infusion Unit Renovations

PROJECT NUMBER: 26-0134

PROPOSAL OF:

BIDDER’S NAME

BIDDER’S ADDRESS

DATE: ____________________________________________________

1. In accordance with Connecticut General Statutes Sections 10a-109a through 10a-109y and pursuant to, and in compliance with your Invitation to Bid, the Notice and Instructions to Bidders, the Form of Contract, including the conditions thereto, the form of required bond, I (we) propose to furnish the labor and/or materials installed as required for the project named and numbered on the BID FORM of this proposal to the extent of the Proposal submitted herein, furnishing all necessary equipment, machinery, tools, labor and other means of construction, and all materials specified in the manner and at the time prescribed strictly in accordance with the provisions of the Contract including specifications and/or drawings together with all addenda issued and received prior to the scheduled closing time for the receipt of the bids, and in conformity with requirements of the University of Connecticut and any laws or departmental regulations of the State of Connecticut or of the United States which may affect the same, for and in consideration of the price(s) stated on the said BID FORM, hereof.

2. The Lump Sum Base Bid by me (us) on the BID FORM includes all work indicated on the drawings and/or described in the specifications, except:

A. Work covered by Alternates as may be listed on the BID FORM.

B. Contingent work covered by Unit Prices as may be listed on the BID FORM.

C. Work covered by Options as may be listed on the BID FORM.

3. This proposal is submitted subject to and in compliance with the foregoing and following conditions and/or information.

A. AWARD: All proposals shall be subject to the provisions and requirements of the

Bid Documents and for purpose of award, consideration shall be given only to proposals submitted by qualified and responsible bidders.

BID FORM Page 2

B. COMMENCEMENT AND COMPLETION OF WORK: Contractor shall commence and complete the work in accordance with the requirements of the Contract Documents.

C. If the Contractor fails to complete the work within the time required by the Contract

Documents, the University shall have the right to assess liquidated damages as provided in Paragraph 9.11 of the General Conditions.

D. AVAILABILITY OF FUNDS:

The funding for this project is contingent upon the continued availability of funds.

Funds will be released based on project phases.

E. CONTRACTORS INSURANCE REQUIRED:

1. The limits of liability and coverages shall be those set forth in Article 11 of the General Conditions.

F. STATEMENT OF BIDDERS’ QUALIFICATIONS AND INTENTION OF

OBJECTIVE CRITERIA:

1. Each Project estimated to be $500,000 and greater, Bidders shall be required to complete and submit qualification forms to obtain “Pre-qualified Status” prior to submission of Bids. Contractors not obtaining “Pre-qualified Status” shall not be allowed to submit a Bid on said projects.

2. For Projects estimated to be less than $500,000 the Bidder shall complete and submit with this BID FORM the Contractor’s Qualification Statement in support of its Qualifications to perform the Work of this project, and to demonstrate its compliance with the University’s Objective Criteria regarding Qualifications.

G. FEDERAL & STATE WAGE DETERMINATIONS AND PRICING

CONSIDERATION:

1 Each contractor who is awarded a contract on or after October 1, 2002 shall be subject to provisions of the Connecticut General Statutes, Section 31-53 as amended by Public Act 02-69, “An Act Concerning Annual Adjustments to Prevailing Wages”.

2 In determining bid price, consideration should be given to Section 31-53 of the

General Statutes of Connecticut as amended by Public Act 02-69, “An Act Concerning Annual Adjustments to Prevailing Wages”. Such prevailing wage adjustment will not be considered a basis for an annual contract adjustment.

3 The State of Connecticut Labor Department Wage Schedule where required, shall be provided with these documents, typically as part of the University of Connecticut Health Center Purchasing Department issued documents, or will be incorporated in the Contract Documents as an Addendum. At the time of bidding, the bidder agrees to accept the current prevailing wage scale, as well as

BID FORM Page 3 any annual adjustment to the prevailing wage scale, as provided by the Connecticut Department of Labor. Wage Rages will be posted each July 1st on the Department of Labor website: www.ctdol.state.ct.us. Such prevailing wage adjustment will not be considered a basis for an annual contract amendment.

4. I (We), the undersigned, hereby declare that I am (we are) the only person(s) interested in the proposal and that it is without any connection with any other person making any bid for the same work. No person acting for, or employed by, the State of Connecticut is directly interested in this proposal, or in any contract which may be made under it, or in expected profits to arise there from.

This proposal is made without directly or indirectly influencing or attempting to influence any other person or corporation to bid or refrain from bidding or to influence the amount of the bid of any other person or corporation. This proposal is made in good faith without collusion or connection with any other person bidding for the same work and this proposal is made with distinct reference and relation to the plans and specifications prepared for this Contract.

I (We) further declare that in regard to the conditions affecting the work to be done and the labor and materials needed, this proposal is based solely on my (our) investigation and research and not in reliance upon any representations of any employee, officer or agent of the State.

5. Each class of work set forth in a separate Section of the Specifications and designated as a subtrade in Item 2A of the proposal pages shall be the matter of a subcontract made in accordance with the procedures set forth in the Bid and Contract Documents.

6. The undersigned agrees that, if selected as General Contractor, he shall, within five (5) days, Saturdays, Sundays and legal holidays excluded, after presentation thereof by the University of Connecticut, execute a contract in accordance with the terms of this general bid.

7. The undersigned agrees and warrants that he has made good faith efforts to employ minority business enterprises as subcontractors and suppliers of materials under such contract and shall provide the Commission on Human Rights and Opportunities with such information as is requested by the Commission concerning his employment practices and procedures as they relate to the provisions of the Connecticut General Statutes governing contract requirements.

8. The undersigned agrees that if notice of acceptance of Bid is delivered to him within 90 calendar days from the date of bid opening, he will promptly execute a contract for the above stated compensation.

BID FORM CONTINUED ON NEXT PAGE

http://www.ctdol.state.ct.us/

BID FORM Page 4

The undersigned proposes to furnish all labor and material required for:

UConn Health CT Tower Level 6 Ambulatory Care Infusion Unit Renovations Project Number: 26-013 in accordance with the accompanying Drawings and Specifications prepared by

Kenneth Boroson Architects, LLC for the Contract Price specified below subject to additions and deductions according to the terms of the Contract Documents dated July 6, 2026.

A. ADDENDA:

This bid includes Addenda numbered: ______________ Dated _______________

______________ Dated _______________

______________ Dated _______________

______________ Dated _______________

B. ALLOWANCES: Not used

C. PROPOSED BASE CONTRACT PRICE:

Written Figures

D. SCHEDULE OF ALTERNATES: Not used

E. SCHEDULE OF UNIT PRICES: Not used

F. SCHEDULE OF OPTIONS: Not used

G. SUBDIVISION OF CONTRACT PRICE:

The subdivision of the proposed Contract Price is as follows:

ITEM 1A Subcontractors and prices for the following trades must be listed (if such prices exceed $25,000.00). However, the general bidder may list himself together with his price if he customarily performs any of the trades specified.

If the general contractor requires a performance and/or labor & material payment bond then the general contractor must indicate below which of the subcontractors are subject to this requirement. The amount (%) shall not exceed the subcontractor’s price listed below.

BID FORM Page 5

DESCRIPTION NAME OF

SUBCONTACTOR

DOLLAR

AMOUNT

LABOR &

MATERIAL BOND

PERFORMANCE

BOND

MASONRY

ELECTRICAL

MECHANICAL

WITHOUT HVAC

HVAC

The undersigned agrees that each of the subcontractors listed on this BID FORM will be used for the work indicated at the amount stated, unless a substitution is permitted by the University of Connecticut Health Center. Such permission shall only be granted for “good cause” as defined by Connecticut General Statute Section 4B-95(C).

BID FORM Page 6

ITEM 1B SCHEDULE OF VALUES:

The undersigned agrees that the Schedule of Values submitted with this Bid is a true representation of the distribution of the costs of this project and equals the Proposed Base Contract Price shown above. The Schedule of Values is an integral part of this proposal.

Please indicate N/A for those divisions of work not applicable.

*Refer to ITEM 1A above for stipulations pertaining to those Divisions of Work requiring listing of subcontractors and pricing.

SCHEDULE OF VALUES

Division 1, General Requirements __________

Division 2, Site Construction __________

Division 3, Concrete __________

*Division 4, Masonry __________

Division 5, Metals __________

Division 6, Wood & Plastic __________

Division 7, Thermal and Moisture Protection __________

Division 8, Doors & Windows __________

Division 9, Finishes __________

Division 10, Specialties __________

Division 11, Equipment __________

Division 12, Furnishings __________

Division 13, Special Construction __________

Division 14, Conveying Systems __________

*Division 15, Mechanical, without HVAC __________

*Division 15, Mechanical, HVAC __________

*Division 16, Electrical __________

TOTAL OF PROPOSED BASE CONTRACT PRICE __________

BID FORM Page 7

H. CONTRACTORS CERTIFICATION

We certify that we are familiar with the contents of the Contract Documents for this project and that we have examined the site and accept the conditions under which the work will be done.

NOTE: All proposals must be signed by a duly authorized representative of the firm.

NO FACSIMILE SIGNATURE PERMITTED.

If this proposal is being submitted by a Joint Venture, each Joint Venture shall sign the Proposal, and each Joint Venture agrees to be bound by the terms and conditions thereof.

Signed the __________ day of ____________________ 20____.

Project Number: ___________________________________________________ _

(TO BE FILLED IN AND SIGNED BY THE BIDDER)

Firm Name: _______________________________________________________ _ Street: _____________________________________________________________ City/State/Zip Code: ________________________________________________ Telephone: __________________________________________________ Fax Number: _______________________________________________________ Duly Authorized Signature:______________________________________ Name / Title _______________________________________________________

(TO BE FILLED IN AND SIGNED BY JOINT VENTURE IF APPLICABLE)

Firm Name: _______________________________________________________ _ Street: _____________________________________________________________ City/State/Zip Code: ________________________________________________ Telephone: __________________________________________________ Fax Number: _______________________________________________________ Duly Authorized Signature:______________________________________ Name / Title _______________________________________________________ Duly Authorized Signature:______________________________________ Name / Title _______________________________________________________

END OF SECTION

GENERAL NOTES

1. PROVIDE SOLID WOOD BLOCKING FOR MOUNTING OF TOILET AND BATH ACCESSORIES.

2. INSULATE ALL EXPOSED PIPING AT SINKS FOR PERSONS WITH DISABILITIES.

3. REFER TO FINISH KEY FOR ADDITIONAL INFORMATION.

4. REFER TO PLUMBING DRAWINGS FOR FLOOR DRAIN LOCATIONS AND ADDITIONAL INFORMATION.

5. REFER TO MEP DRAWINGS FOR ADDITIONAL INFORMATION REGARDING POWER.

6. REFER TO STRUCTURAL DRAWINGS FOR ADDITIONAL INFORMATION REGARDING NEW STEEL LINTEL AT NEW

FRAMED WALL OPENING.

7. WALLS LOCATED ADJACENT TO URINALS AND WATER CLOSETS SHALL BE FINISHED WITH A WATER BASED

EPOXY PAINT. REFER TO FINISH KEY AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.

8. ALL CEILINGS WITHIN THIS SCOPE OF WORK ARE E.T.R.

9. ALL HEAD BOARDS WITHIN PATIENT ROOMS ARE E.T.R.

10. ALL EXISTING OVERHEAD CUBICLE CURTAIN TRACKS ARE E.T.R.

11. NEW AND EXISTING LIGHT FIXTURES WITHIN PATIENT ROOMS TO BE CONTROLLABLE BY EACH PATIENT. SEE

MEP DRAWINGS FOR ADDITIONAL INFORMATION.

12. EXISTING NURSE CALL SYSTEMS WITHIN PATIENT ROOMS TO BE CONTROLLABLE BY EACH PATIENT. SEE MEP

DRAWINGS FOR ADDITIONAL INFORMATION.

13. PATCH AND PAINT FOR ALL MEP WORK WHERE REQUIRED.

14. ALL NEW DOOR HARDWARE WITHIN SCOPE OF WORK EXTENTS - TO BE FINALIZED BY OWNER.

CONSTRUCTION KEY

NEW CMU WALL CONSTRUCTION

NEW STUD & GWB WALL CONSTRUCTION

NEW BRICK WALL CONSTRUCTION

DIMENSIONAL NOTE #1: ALL INTERIOR DIMENSIONS SHOWN IN THESE PLANS ARE TO THE

FACE OF THE STUD / RESILIENT CHANNEL OR TO THE ROUGH MASONRY. ALL EXTERIOR

DIMENSIONS ARE TO THE FINISH FACE - REFER TO WALL SECTIONS & STRUCTURAL DWGS

FOR ALL ADDITIONAL INFORMATION REGARDING SPECIFIC SIZES OF NEW WALL

CONSTRUCTION SYSTEMS & ASSEMBLIES

DIMENSIONAL NOTE #2: ALL ANGLES (IN PLAN @ WALLS) SHOULD BE ASSUMED TO BE

90 DEGREES UNLESS OTHERWISE NOTED

EXTENTS OF PROJECT SCOPE

NOT IN PROJECT SCOPE, EXISTING TO REMAIN

ZZ

ZZ

93.21sf

136.19sf

42.97sf 62.61sf

15.73sf

159.98sf 233.23sf

26.37sf

228.72sf

26.37sf

23.69sf

288.43sf

24.18sf

226.40sf

67.99sf

275.68sf

274.96sf

23.44sf

23.34sf

274.53sf

23.55sf

325.34sf

23.32sf

239.66sf

23.42sf

238.32sf

23.32sf

234.50sf

25.95sf 79.40sf

153.15sf 46.44sf

300.89sf

109.36sf109.33sf 81.61sf

164.94sf 83.24sf

29.48sf 143.56sf

54.78sf

78.89sf

6.22sf

234.31sf

111.04sf

189.10sf

65.94sf73.83sf73.83sf73.83sf

278.35sf

210.67sf

73.71sf159.14sf

359.23sf

105.36sf

89.30sf50.80sf

50.16sf18.93sf

185.19sf

136.02sf

18.44sf

33.04sf

202.11sf

197.20sf

25.89sf

25.78sf

198.78sf 26.09sf

199.77sf

25.98sf

205.75sf

19.88sf

229.89sf

15.93sf

242.97sf

1,734.34sf

1,063.40sf

129.14sf

9.58sf

100.00sf

73.12sf

894sf

H6M30

H6034A

H6034

H6042A H6042B

H6E2

H6S2 H6033

H6033A

H6032

H6032A

H6042C

H6031

H6031A

H6030

H6030A

H6029

H6028

H6029A

H6028A

H6027

H6027A

H6026

H6026A

H6025

H6025A

H6024

H6024A

H6023

H6023A H6M15

H6S1 H6M16 H6010

H6011H6012

H6009 H6008B

H6008H6005

H6007 H6008A

H6M19

H6001

H6003

H6002

H6M13H616EH617EH618E

H6015

H6017

H6019H6020

H6014

H6022

H6M14H6E1

H6CSCH6M14A

H6016

H6044

H6M17

H6041A

H6041

H6040

H6040A

H6039A

H6039 H6038A

H6038

H6037A

H6037

H6M36

H6036

H6M35

H6035

H6042

H6043

H6021

H6M18

H6018

H6045

H6046

ACU INFUSION ACU INFUSION ACU INFUSION

ACU INFUSION

ADA TOILET

ACU INFUSION

ACU INFUSION

ACU INFUSION

ACU INFUSION

ACU INFUSION

ACU INFUSION

ACU INFUSION

STAFF AREA

EXIST.

STAFF SINK

EQUIPMENT STORAGE

EXISTING SLEEP LAB

EXIST.

STAFF SINK

ACU NURSE

MGR. OFFICE

IT CLOSET

ACU RECEPTION

ACU WAITING RM

ACU LOCKER RM

EXIST.

ELEC. CL.

EXIST. SLEEP

LAB TECH RM

EXIST. SLEEP

LAB STORAGE

EXIST. SLEEP LAB

PATIENT RM

EXIST. SLEEP LAB

PATIENT RM

EXIST. SLEEP LAB

PATIENT RM

EXIST. SLEEP LAB

PATIENT RM

ACU MED. RM

EXIST.

ELEC. CL.

EXIST. ADMIN

OFFICE SUITE

EXIST. NURSE

STATION

EXIST. NURSE

STATION

SPIU

RECEPTION

EXIST. NURSE

STATION

EXIST.

NUTRITION

EXIST.

STORAGE

EXIST. STAFF

TOILET

A3.00

A3.00

A3.00

A3.00

D-05

D-05

D-05

D-05

D-05

D-05

D-04

D-04

D-04

H6013

6 74

6 74

1 1 1

D-03

D-03

D-03D-03D-03

NEW DATA TO GO IN I.T. CLOSET. SEE MEP

DWGS FOR ADDITIONAL INFORMATION

D-01

D-06

D-02

A3.022 A3.022 A3.022

A3.02

A3.01

1 1

D-03

1 1

D-03

NEW WORK KEY

- NEW WALL MOUNTED LIGHT FIXTURES ABOVE. MOUNT ON FACE OF

WALL BEHIND BED/CHAIR. SEE MEP DWGS FOR MOUNTING HEIGHT AND

ADDITIONAL INFORMATION.

NEW ADA SINKS, COUNTERS, BACKSPLASHES, AND BASE CABINET.

CORIAN COUNTERS WITH 810 INTEGRAL CORIAN SINK.

PLAM CABINET DOORS, FAKE FRONT AND FILLERS.

ALL PLAM AND CORIAN TO MATCH UNITS ON H-7038.

HARDWARE: CONCEALED HINGES - HEAVY DUTY & WIRE PULLS

NEW TIE-IN TO EXISTING TO REMAIN NURSE CALL SYSTEM WITH WALL-

MOUNTED LIGHT CONTROLS INCLUDED FOR (2) PATIENTS.

SEE MEP DRAWINGS FOR ADDITIONAL INFORMATION.

NEW CEILING LIGHT FIXTURES WITHIN SPACE. ALL CEILINGS ARE E.T.R.

REF. REFLECTED CEILING PLANS, MEP DWGS, AND SPECIFICATIONS FOR

ADDITIONAL INFORMATION.

NEW WALL OPENING AND COUNTERS. SEE STRUCTURAL DRAWINGS FOR

STEEL LINTEL INFORMATION.

NEW FINISHES WITHIN SPACE. SEE FINISH TAGS AND FINISH KEY.

NEW FURNITURE WITHIN SPACE BY OWNER. SEE SPECIFICATIONS FOR

ADDITIONAL INFORMATION.

EQUIPMENT STORAGE AREA SCOPE OF WORK: (2) NEW 3 5/8" MTL STUD

PARTITIONS, NON INSULATED. ONE PARTITION TO HAVE 5/8" GWB BOTH

SIDES, ONE PARTITION TO HAVE 5/8" GWB ON ONE SIDE ONLY. 0.06" FULL

HEIGHT uPVC RIGID SHEET WALL PROTECTION APPLIED TO GWB ON NEW

PARTITIONS WHERE INDICATED. WALL PROTECTION TO TERMINATE AT

THE FINISHED FLOOR. 4" BASE TO BE INSTALLED OVER TOP OF WALL

PROTECTION. SEAL ALL EDGES AND JOINTS OF WALL PROTECTION PER

MANUFACTURER'S RECOMMENDATIONS. 1/2" PLYWOOD SUBSTRATE END

PANEL TO BE INSTALLED WITH WALL PROTECTION AND 4" BASE ON TOP.

1/2" SOLID SURFACE WALL CAP WITH SQUARE EDGE ON BOTH SIDES.

WALL CAP TO TERMINATE AT E.T.R. ADJACENT COUNTERTOP WITH 1 1/2"

OVERHANG. SEE FINISH KEY FOR ADDITIONAL INFO. REF. 5/A3.00 & 8/A9.00

DEMO OPENING IN EXISTING CMU PARTITION FOR NEW FRAMED

WALL OPENING AND COUNTER, WITH A STEEL LINTEL ABOVE.

REF. 5/AD2.00.

SEE STRUCTURAL DRAWINGS FOR ADDITIONAL INFO REGARDING

STEEL LINTEL.

DEMO BUILT IN CASEWORK. PATCH AND PAINT GWB AS NEEDED

TO MATCH ADJACENT. INFILL WOOD CHAIR RAIL WITH SALVAGED

CHAIR RAIL FROM WALL OPENING AREA.

DEMO EXISTING LIGHTING FIXTURE(S). EXISTING ELECTRICAL TO

REMAIN. NEW LIGHTING FIXTURES TO BE INSTALLED IN NEW

WORK SCOPE.

REF. REFLECTED CEILING PLANS ON A3.00.

DEMO EXISTING FLOORING AND BASE.

DEMO EXISTING SINK, COUNTERTOP, BACKSPLASHES, AND

CASEWORK. EXISTING PLUMBING AND ELECTRICAL TO REMAIN TO

BE UTILIZED IN THE NEW WORK SCOPE.

DEMO COUNTERTOP, PARTITIONS, CABINET DOORS, AND

SURROUNDING WOOD FINISH WITHIN THE AREA DEFINED IN

DRAWING 4/AD2.00.

REF. 5/A3.00 AND 8/A9.00 FOR ADDITIONAL INFORMATION

REGARDING NEW CONSTRUCTION WITHIN THE NEW EQUIPMENT

STORAGE AREA.

D-01

D-02

D-03

D-04

D-05

D-06

DEMOLITION KEY

Kenneth Boroson

ARCHITECTS

315 Peck Street

New Haven, CT 06513 p: 203.624.0662 f: 203.562.1732 www.kbarch .com

THIS PRINT IS THE PROPERTY

OF KENNETH BOROSON

ARCHITECTS. IT IS LOANED

WITH THE EXPRESS AGREEMENT

THAT THE DRAWING AND THE

INFORMATION CONTAINED

THEREIN ARE THE PROPERTY OF

KENNETH BOROSON

ARCHITECTS AND WILL NOT BE

REPRODUCED, COPIED OR

OTHERWISE DISPOSED OF,

DIRECTLY OR INDIRECTLY, AND

WILL NOT BE USED IN WHOLE

OR IN PART TO ASSIST IN

MAKING OR TO REFURNISH ANY

INFORMATION FOR MAKING

DRAWINGS, PRINTS OR OTHER

REPRODUCTIONS THEREOF OR

FOR THE MAKING OF

APPARATUS OR PARTS THEREOF

EXCEPT UPON WRITTEN

PERMISSION OF KENNETH

BOROSON ARCHITECTS. THE

ACCEPTANCE OF THE PRINTS

WILL BE CONSTRUED AS AN

ACCEPTANCE OF THE

FOREGOING AGREEMENT.

CERTIFICATION:

STATUS:

U N

IV

E

R S

IT

Y

O F

C

N

N E

C T

IC

U

T

U N

IV

E

R S

IT

Y

P L

A N

N

IN

G D

E S

IG

N

O

N S

T R

U C

T

IO

N

D

IS

C

O V

E R

Y D

R

IV

E

U N

IT

S

T O

R R

S

C T

-3

T

E L E

P H

O N

E

(8

-2

F

A C

S

IM

IL

E

(8

-3

PROJECT:

PROJECT #:

WORK ORDER #:

FILE NAME:

AUTHOR:

DRAFTER:

SCALE:

PRINT DATE:

SHEET TITLE:

SHEET:

SHEET OF

AS NOTED

26-013

/2

/2

:2

:2

A

M N

P ro d u c ti o n \A c ti v e P ro je c t F o ld e rs

\2 .0

U C

H

-0

H

J

D H

A U

IC

\D ra w in g s \R e v it \0

.0

.2

U C

H

-0

H

J

D H

A U

IC

A

W .r v t

N:\Production\Active Project Folders\2026.003 - UCH #25-020 H6 JDH AUIC\Drawings\Revit\03.04.2026 - UCH #25-020 H6 JDH AUIC_AW.rvt

100% BID DOCUMENTS -

ADDENDUM 01

U C

H C

T T

O W

E R

L E

V E

L

A M

B U

L A

T O

R Y

C A

R E

IN

F

U S

IO

N

U N

IT

R

E N

O V

A T

IO

N

S

F

A R

M

IN

G T

O N

A V

E F

A R

M

IN

G T

O N

C

T

JBG/AW

JBG/AW

PROPOSED SIXTH FLOOR PLAN

A2.00

SCALE: 1/8" = 1'-0"A2.00

1 PROPOSED SIXTH FLOOR PLAN

REVISIONS

MARK DATE DESCRIPTION

1 ADDENDUM 01 07/29/2026

NOT FOR CONSTRUCTION

JULY 29, 2026

NON-LOAD BEARING

EXISTING 8" CMU (V.I.F.)

(2)L6x3-1/2x5/16 STEEL ANGLES (A36).

PROVIDE A MINIMUM OF 6" BEARING

EA END OF OPENING. GROUT THE

FIRST BEARING CELL SOLID WITH NON-

SHRINK GROUT (TYP EA END).

T/ OPENING

REFER TO ARCHT'L

DETAIL NOTE:

1. EXISTING STRUCTURAL DRAWINGS PREPARED BY SEVERUD-PERRONE-

FISCHER-STURM-CONLIN-BANDEL, DATED 4/26/68 WERE UTILIZED IN THE

REVIEWED OF THIS CONDITION.

2. SHORING AND BRACING OF EXISTING CMU WALL FOR INSTALLATION OF STEEL

ANGLES IS THE RESPONSIBILITY OF THE INSTALLER AS PART OF MEANS AND

METHODS. CONTACT A PROFESSIONAL ENGINEER LICENSED IN THE STATE OF

CONNECTICUT FAMILIAR WITH SHORING FOR ADDITIONAL INFORMATION IF

REQUIRED.

Project Title:

Drawing Title:

Date:

Scale:

Drawn By:

Job Number:

Drawing Number:Revisions:

3/4" = 1'-0" S1.00

NEW OPENING IN EXISTING CMU WALL

U. OF CONNECTICUT UCONN HEALTH

LVP

26-98

06/03/26

UCH CT TOWER LEVEL 6, AMBULATORY CARE INFUSION UNIT RENOVATION

263 FARMINGTON AVE, FARMINGTON, CT 06030

3/4" = 1'-0"

LINTEL DETAIL

JULY 29, 2026

DOCUMENT CHANGES:

SPECIFICATIONS

*changes listed below each drawing are for bidder’s convenience and do not represent a comprehensive list of all modifications. It is the bidders responsibility to inspect all attached documents for changes and modifications to the original Contract Documents.

REPLACE:

Replace: 260923 Lighting Controls Devices with attached revised specification:

• Modified spec: Basis of design lighting controls to be a wired Lutron system compatible with the nurse call tie in required in patient rooms.

DRAWINGS

*changes listed below each drawing are for bidder’s convenience and do not represent a comprehensive list of all modifications. It is the bidders responsibility to inspect all attached documents for changes and modifications to the original Contract Documents.

DRAWINGS

Replace: MEP3.00 – ENLARGED SIXTH FLOOR PLANS with attached revised drawing:

• Revise Lighting in patient rooms.

jgould Text Box CES addendum Q&A 7.28.26

NLC

PL

OS

NLC

LVC LVC

LVC

23.32sf

239.66sf

23.42sf

H6025

H6025A

ACU INFUSION

ACU INFUSION

D-05

3 P1

S-1

ETR

ETR ETR ETR

ETR

E T

R

E T

RETRE

T

R

E T

RETR

NO ELECTRICAL SCOPE IN ROOM.

SHOWN FOR REFERENCE ONLY

153.15sf

81.61sf

ACU NURSE

MGR.

D-04

H6013

6 74

EL3

EL3

LVD

EL2

ETR

ETR

ETR

ETR

EQUIPMENT STORAGE

D-06

EP1

164.94sf 83.24sf

29.48sf

143.56sf

54.78sf

78.89sf

6.22sf

234.31sf

H6008 H6005

H6007

H6M19

H6001

ACU RECEPTION

ACU WAITING RM

D-04

D-04

6 74

D-01

D-02

EL5 EL5

EL5EL5

EL2

EP1

LVD

RE-ROUTE CONDUIT AROUND

LENTIL. COORDINATE EXACT SIZE

AND LOCATION IN FIELD.

143.56sf

111.04sf

H6005

H6003

IT CLOSET

ACU RECEPTION

D-04

6 74

D-01

TELECOMMUNICATIONS

GROUNDING BUSBAR.

REFER TO TELECOM

PATHWAYS AND

GROUNDING RISER

DIAGRAM FOR ADDTIONAL

INFORMATION.

EXISTING RACKS

TO REMAIN

EXISTING LADDER

RACK TO REMAIN

L14-60R, USE 3#6, #10G,

USE EXISTING CONDUIT

MOUNT 36" AFF.

L6-30R, USE 2#10, #

10G, USE EXISTING

CONDUIT. MOUNT

TO OVERHEAD

LADDER RACK.

QUAD RECEPTACLE,

USE 2#12, #12G, USE

EXISTING CONDUIT.

MOUNT TO OVERHEAD

LADDER RACK.

EXISTING TO

REMAIN ACCESS

CONTROLS

EXISTING TO

REMAIN NURSE

CALL CONTROLS

EXISTING (3)-3/4"C. TO

ELEC CLOSET H6E1 TO

BE USED FOR NEW

CIRCUITS

EL4

EL4

EP2

EP3

EP4

EP5

EXISTING 4"C. SLEEVE

DOWN

EXISTING (2)4"C. SLEEVE

UP. (1) SPARE.

M5

23.32sf

234.50sf

25.95sf

H6023

H6023A

H6M15

ACU INFUSION

ETR ETR ETR

ETR

E T

R

E T

RE

T

R E

T

REL1 EL1

EL2

,u1,d,1 ,u2,d2

L V

D P

,u ,d

L V

D P

,u ,d

MOUNTED TO

MULLION

,u2,d2,u1,d1

1 1

67.99sf

275.68sf

23.44sf

H6M30

H6030A

H6029

H6028

H6029AACU INFUSION

ACU INFUSION

D-05

D-05

D-03

D-03

ETR

ETR

ETR

ETR

ETR

ETR

ETR

ETR

ETR

ETR

HILLROM

FLATWALL(ETR)

HILLROM

FLATWALL(ETR)

P1

P1

,u1,d1

,u2,d2

EL1

EL1

LVDP,u1,d1 LVDP,u2,d2

24.18sf

226.40sf

67.99sf

275.68sf

H6M30

H6031A

H6030

H6030A

H6029

ACU INFUSION

ADA TOILET

ACU INFUSION

D-03

D-03

ETR

ETR

ETR

ETR

ETR

HILLROM

FLATWALL(ETR)

HILLROM

FLATWALL(ETR)

,u,d

EL2

EL1

LVDP,u,d

,u,d

MOUNTED TO

MULLION

Kenneth Boroson

ARCHITECTS

315 Peck Street

New Haven, CT 06513 p: 203.624.0662 f: 203.562.1732 www.kbarch.com

THIS PRINT IS THE PROPERTY

OF KENNETH BOROSON

ARCHITECTS. IT IS LOANED

WITH THE EXPRESS AGREEMENT

THAT THE DRAWING AND THE

INFORMATION CONTAINED

THEREIN ARE THE PROPERTY OF

KENNETH BOROSON

ARCHITECTS AND WILL NOT BE

REPRODUCED, COPIED OR

OTHERWISE DISPOSED OF,

DIRECTLY OR INDIRECTLY, AND

WILL NOT BE USED IN WHOLE

OR IN PART TO ASSIST IN

MAKING OR TO REFURNISH ANY

INFORMATION FOR MAKING

DRAWINGS, PRINTS OR OTHER

REPRODUCTIONS THEREOF OR

FOR THE MAKING OF

APPARATUS OR PARTS THEREOF

EXCEPT UPON WRITTEN

PERMISSION OF KENNETH

BOROSON ARCHITECTS. THE

ACCEPTANCE OF THE PRINTS

WILL BE CONSTRUED AS AN

ACCEPTANCE OF THE

FOREGOING AGREEMENT.

CERTIFICATION:

STATUS:

U N

IV

E

R S

IT

Y

F

N

N E

C T

IC

U

T

U N

IV

E

R S

IT

Y

P L A

N N

IN

G

D E

S

IG

N

O N

S T

R U

C T

IO

N

D

IS

C

O V

E R

Y D

R

IV

E

U N

IT

S T

O R

R S

C

T

-3

T E

L E

P H

O N

E

(8

-2

F A

C S

IM

IL

E

(8

-3

PROJECT:

PROJECT #:

WORK ORDER #:

FILE NAME:

AUTHOR:

DRAFTER:

SCALE:

PRINT DATE:

SHEET TITLE:

SHEET:

SHEET OF

AS NOTED

26-013

CES #250859.00

/2

/2

:3

:3

P

M C

U s e rs

\q h e in ri c h \D o cu m e n ts

\R -2

-M

E P

C e n tr a l-

U C

O N

N H e a lt h C

T q h e in ri c h .r v t

C:\Users\qheinrich\Documents\R24-250859-MEP Central-UCONN Health CT6_qheinrich.rvt

100% BID DOCUMENTS

U C

H C

T T

O W

E R

L E

V E

L

A M

B U

L A

T O

R Y

C A

R E

IN

F

U S

IO

N

U N

IT

R

E N

O V

A T

IO

N

S

F A

R M

IN

G

T O

N A

V E

F A

R M

IN

G

T O

N C

T

QEH

QEH

07/06/26

ENLARGED SIXTH FLOOR PLANS

MEP3.00

1/4" = 1'-0"

MEP ACU INFUSION ROOM H6025-H6028 - ENLARGED PLAN

1/4" = 1'-0"

MEP ACU NURSE MGR. OFFICE - ENLARGED PLAN

1/4" = 1'-0"

MEP VITALS AREA - ENLARGED PLAN

1/4" = 1'-0"

MEP ACU RECEPTION & WAITING ROOM - ENLARGED PLAN

REVISIONS

MARK DATE DESCRIPTION

1 ADDENDUM 01 07/29/2026

KEYNOTES - NEW WORK

Key Value Keynote Text

EL1 PROVIDE ARM MOUNT LINEAR FIXTURE EQUAL TO: TETRUM "T3-ARM-B-CL30-4-NL36"-8-40K-H-L-HL-ID-FINISH TO BE SELECTED BY ARCHITECT", ARM MOUNTED, BI DIRECTIONAL ORIENTATION, 30" ARM LENGTH, FLAT 4" DIAMETER COVER PLATE, 3 FEET LENGTH, 80 CRI, 4000K, DIRECT OUPTUT HIGH 12020 LM/FT, LAMBERTIAN OPTIONS, INDIRECT OUTPUT HIGH 1190 LM/FT LAMBERTIAN OPTICS, 0-10V DIMMING, FINISH TO BE SELECTED BY ARCHITECT. PROVIDE LOW VOLTAGE CONNECTION FOR PATIENT CONTROL VIA PILLOW SPEAKER. REFER TO

TYPICAL INFUSION ROOM LIGHTING DETAIL

EL2 POWER VIA LINE SIDE OF LOCAL NORMAL LIGHTING CIRCUIT, USE 2#12, #12G, IN 3/4"C.

EL3 PROVIDE 2X2 RECESSED LIGHT FIXTURE EQUAL TO: COLUMBIA "LCATT22-35-VW-G-ED1-U", 80 CRI, 3500K, 1554 LUMENS, GRID LAY-IN, CURBED SHIELDING, 0-10V DIMMING 1%, UNIVERSAL VOLTAGE, COLD ROLLED STEEL, 60,000HR LED L80, 5 YEAR WARRANTY

EL4 PROVIDE CHAIN HUNG LINEAR STRIP FIXTURE EQUAL TO: COLUMBIA "MPS4-35K-MW-C-W-DALIP-U-NXCS" 4'L, 80 CRI, 3500K COLOR TEMP, 3600 LUMENS, CURVE FROSTED ACRYLIC LENS, WIDE DISTRIBUTION, DALI DRIVER TO INTEGRATE WITH INTEGRAL OCCUPANCY SENSOR, 120-277V, PROVIDED WITH NXCS WIRELESS INDOOR OCC SENSOR. LIGHT SHALL AUTOMATICALLY TURN OFF AFTER 20 MINS OF NON-OCCUPANCY. LIGHTS SHALL AUTOMATICALLY TURN ON UPON OCCUPANT SENSING, CODE-GAUGE STEEL HOUSING, L80 60,000HRS, 5 YEAR

WARRANTY.

EL5 PROVIDE 4" RECESSED ROUND DOWNLIGHT FIXTURE EQUAL TO: PRESCOLITE

"LTR-4RD-H-SL10L-DM1-CP/LTR-4RD-T-SL35K8MD-FINISH-FINISH-FINISH" 1000 LUMEN, 0-10V DIMMING TO 1%, PLENUM RATED, 3500K CCT, 80 CRI, MEDIUM DISTRIBUTION, FINISHES TO BE SELECTED BY ARCHITECT, UNIVERSAL VOLTAGE, DAMP LOCATION RATED, 5 YEAR WARRANTY.

EP1 POWER VIA LINE SIDE OF LOCAL NORMAL RECEPTACLE CIRCUIT, USE 2#12, #12G, IN 3/4"C.

EP2 POWER VIA EXISTING 60A BREAKER, POLES 19,21 IN "EL6S" LOCATED IN ROOM "H6E1"

EP3 POWER VIA EXISTING 20A BREAKER, POLE 23 IN "EL6S" LOCATED IN ROOM "H6E1"

EP4 POWER VIA NEW 30A -2P BREAKER, "R6S-L" LOCATED IN ROOM "H6E1"

EP5 POWER VIA EXISTING 20A BREAKER, POLE 25 IN "EL6S" LOCATED IN ROOM "H6E1". USE 2#12, #12G IN 3/4"C.

M5 PROVIDE TITUS DIFFUSER MODEL TMR WITH 6"Ø NECK. CONNECT TO EXISTING OPEN-ENDED 6"Ø SUPPLY DUCT IN ROOM. DIFFUSER NECK SIZE TO MATCH EXISTING DUCT SIZE, CONTRACTOR TO VERIFY DUCT SIZE BEFORE

ORDERING DIFFUSER.

P1 PROVIDE NEW SINK AND FAUCET. RECONNECT TO EXISTING H&CW, WASTE, AND VENT PIPING AND PROVIDE

MIXING VALVE TV-1. TYPICAL OF H6025, H6026, H6027, H6028, H6029, H6031

1/4" = 1'-0"

MEP IT H6003 CLOSET - ENLARGED PLAN

1/4" = 1'-0"

MEP ACU INFUSION ROOM H6023,H6024 - ENLARGED PLAN

1/4" = 1'-0"

MEP ACU INFUSION ROOM H6029, H6031-H6033 - ENLARGED PLAN

1/4" = 1'-0"

MEP ACU INFUSION ROOM H6030 - ENLARGED PLAN

LIGHTING CONTROL DEVICES 26 09 23 Page - 1

SECTION 26 09 23

LIGHTING CONTROL DEVICES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Section Includes:

1. General Requirements

2. Switch Plates.

3. Class 2 Conductors and Cables

4. Wired Lighting Controls

a. Low Voltage Keypads / Switches.

b. Low Voltage Occupancy/Vacancy Sensors

c. Normal Lighting Controllers

d. Emergency Lighting Controllers

B. System Description: IECC compliant lighting controls to control all interior and exterior lighting:

1. Lighting controls in individual spaces consisting of some combination of occupancy sensors, vacancy sensors, switches with dimming capability.

2. Microprocessor-based controllers with distributed switching control using self-contained individually mounted lighting controllers. Provides multiple modes of operation incorporating vacancy sensors, photocells, and low voltage control stations with dimming capability.

C. Refer to lighting control details and riser diagrams on the drawings for additional information.

1.2 RELATED REQUIREMENTS

A. Related Sections:

1. Division 01 – General Requirements.

2. Section 260400 – General Conditions for Electrical Trades.

3. Section 260500 - Common Work Results for Electrical Trades

4. Section 262726 - Wiring Devices: Product requirements for wiring devices for placement by this section.

1.3 REFERENCE STANDARDS (Follow the most recently adopted standard)

A. National Electrical Manufacturers Association:

1. NEMA 410 - Performance Testing for Lighting Controls and Switching Devices with

Electronic Drivers and Discharge Ballasts

B. 47 CFR 15 - Radio Frequency Devices; current edition.

C. NECA 1 - Standard for Good Workmanship in Electrical Construction.

D. NECA 130 - Standard for Installing and Maintaining Wiring Devices.

E. NFPA 70 - National Electrical Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

LIGHTING CONTROL DEVICES 26 09 23 Page - 2

F. UL 773A - Nonindustrial Photoelectric Switches for Lighting Control; Current Edition, Including

All Revisions.

G. UL 916 - Energy Management Equipment; Current Edition, Including All Revisions.

H. UL 917 - Clock-Operated Switches; Current Edition, Including All Revisions.

I. UL 1472 - Solid-State Dimming Controls; Current Edition, Including All Revisions.

J. IECC – International Energy Conservation Code; Most Recent Edition Adopted by Authority

Having Jurisdiction, Including All Applicable Amendments and Supplements.

1.4 ADMINISTRATIVE REQUIREMENTS

A. Coordination:

1. Coordinate the placement of lighting control devices with millwork, furniture, equipment, etc. installed under other sections or by others.

2. Coordinate the placement of wall switches with actual installed door swings and sidelights.

3. Coordinate the placement of wall switch occupancy/vacancy sensors with actual installed door swings and sidelights.

4. Coordinate the placement of occupancy/vacancy sensors with millwork, furniture, equipment or other potential obstructions to motion detection coverage installed under other sections or by others.

5. Coordinate the placement of photo sensors for daylighting controls with windows, skylights, and luminaires to achieve optimum operation. Coordinate placement with ductwork, piping, equipment, or other potential obstructions to light level measurement installed under other sections or by others.

6. Notify Architect of any conflicts or deviations from the contract documents to obtain direction prior to proceeding with work.

B. Sequencing:

1. Protect lighting control devices during construction.

2. Clean lighting control devices once final surface finishes and painting are complete.

C. Pre-Installation Meeting:

1. Convene minimum one week prior to commencing work of this section.

1.5 SUBMITTALS

A. See Division 01 - General Requirements.

B. Shop Drawings: Indicate dimensioned drawings of lighting control system components and accessories.

1. One Line Diagram: Indicating system configuration, panels, number and type of switches or devices.

2. Include typical wiring diagrams for each component.

3. Floor Plan Layout Drawings: Manufacturers symbols are acceptable, provided that symbology between engineer’s device legend and manufacturers symbols are cross-referenced.

LIGHTING CONTROL DEVICES 26 09 23 Page - 3

C. Product Data: Submit manufacturer’s standard product data for each system component. This shall include, but not be limited to: ratings, configurations, dimensions, sensor coverage ranges, colors, service condition requirements, and installation features.

D. Manufacturer's Installation Instructions: Submit for each system component.

E. Manufacturer's Certificate: Certify products meet or exceed specified requirements.

F. Coordination Drawings: Submit evidence that lighting controls are compatible with connected monitoring and control devices and systems specified in other Sections and evidence that the control schemes identified herein and shown on the typical lighting control details are configured and operational as specified.

1. Show interconnecting signal and control wiring and interfacing devices that prove compatibility of inputs and outputs.

2. Provide documentation addressing each room/area control scheme specified with a description of how the submitted system complies.

1.6 CLOSEOUT SUBMITTALS

A. Division 01 - Execution and Closeout Requirements: Closeout procedures.

B. Project Record Documents: Record the following information:

1. Actual installed locations of components and settings for lighting control devices. Record circuiting and switching arrangements.

2. Wiring diagrams reflecting field-installed conditions with identified and numbered system components and devices.

C. Operation and Maintenance Data:

1. Submit replacement parts numbers.

2. Submit manufacturer’s published installation instructions and operating instructions.

3. Recommended renewal parts list.

4. Detailed information on device programming and setup.

1.7 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in manufacturing the products specified in this section with minimum five years documented experience. Company shall provide 24/7 telephone support by qualified technicians.

1. A complete offering of full service for the lighting control system shall be available. All work shall be performed by factory trained service personnel in the same state as the project.

2. The manufacturer shall, upon request, provide replacement parts for the lighting control system in a timely manner as well as provide access to qualified and trained service personnel to provide preventative maintenance and service on the lighting control system.

B. Product Listing Organization Qualifications: An organization recognized by OSHA as a

Nationally Recognized Testing Laboratory (NRTL) and acceptable to authorities having jurisdiction.

C. Installer Qualifications: Installer shall be one who is experienced in performing the work of this section, and who has specialized in installation of work similar to that required for this project.

LIGHTING CONTROL DEVICES 26 09 23 Page - 4

D. Contractor shall ensure that lighting system control devices and assemblies are fully compatible and can be integrated into a system that operates as described in the lighting control notes on drawings and as described within this specification. Any incompatibilities between devices, assemblies, and system controllers shall be resolved between the contractor and the system provider, as required to ensure proper system operation and maintainability.

E. Performance Requirements: Shall provide all system components that have been manufactured, assembled, and installed to maintain performance criteria stated by manufacturer without defects, damage, or failure.

F. Performance Testing Requirements

1. Manufacturer shall 100% test all equipment prior to shipment. Sample testing is not acceptable.

G. Code Requirements

1. System Control Unit and System Field Devices shall be UL listed and certified.

2. All system components shall be FCC / IC compliant.

3. All system components shall be installed in compliance with National Electrical Codes.

4. Building Codes: All units shall be installed in compliance with applicable, local building codes.

1.8 DELIVERY, STORAGE AND HANDLING

A. See Division 01 - General Requirements.

B. Accept components on site in manufacturer’s packaging. Inspect for damage.

C. Protect components by storing in manufacturer’s containers indoor protected from weather.

1.9 WARRANTY

A. See Division 01 - General Requirements.

B. Furnish five year manufacturer warranty for all components.

PART 2 PRODUCTS

2.1 GENERAL REQUIREMENTS

A. Provide products listed, classified, and labeled as suitable for the purpose intended.

B. Unless specifically indicated to be excluded, provide all required conduit, wiring, connectors, hardware, components, accessories, etc. as required for a complete operating system.

C. Products for Switching of Electronic Ballasts/Drivers: Tested and rated to be suitable for peak inrush currents specified in NEMA 410.

D. Source Limitations: Furnish products produced by a single manufacturer and obtained from a single supplier.

LIGHTING CONTROL DEVICES 26 09 23 Page - 5

E. Refer to lighting control details on drawings for additional requirements and product specifications.

2.2 SWITCH PLATES

A. Manufacturers:

1. Hubbell Incorporated

2. Leviton Manufacturing Co., Inc.

3. Pass & Seymour, a brand of Legrand North America, Inc.

4. Substitutions: Division 01 - General Requirements.

a. Where low voltage keypads / switches or line voltage sensor switches are shown, provide switch plate by same manufacturer.

B. Product Description: Specification Grade.

1. Stainless steel

2. Color: By Architect.

2.3 CLASS 2 CONDUCTORS AND CABLES

A. General Requirements:

1. Line Voltage Wiring: Comply with requirements of Section 260500.

2. Class 2 Low-Voltage Cable:

a. Provide plenum-rated cable.

b. UTP Cable: CAT 5, CAT 6, or as required by manufacturer:

1) Listed and labeled by an NRTL acceptable to authorities having jurisdiction as complying with UL 444 and NFPA 70 for the following types:

2) All cabling shall meet or exceed Commercial Building

Telecommunications Cabling Standard ANSI/TIA/EIA 568-C.2

3) Cabling shall use 23AWG minimum conductors.

4) Pulling tension: The cable pulling tension shall not exceed 25 ft/lbs as indicated in TIA/EIA-568-A.

c. Control Cable:

1) Stranded copper cable, Type CMP.

a) Multiple-Conductor.

b) Twisted Pair.

c) Shielded Twisted Pair

d) Minimum AWG: Per manufacturer requirements, as shown on drawings and details.

2.4 WIRED LIGHTING CONTROL SYSTEM

A. Manufacturers:

1. Lutron Electronics Company, in. – Athena Series (Basis of Design)

2. Current NX Wired

3. Acuity nLight Wired

4. Crestron Zum Wired

5. Cristal Lighting Controls

6. Legrand Wattstopper Plus Wired

7. Signify Dynalite

8. Substitutions: See Division 01 – General Requirements.

LIGHTING CONTROL DEVICES 26 09 23 Page - 6

B. GENERAL REQUIREMENTS

1. Sensor Layout and Tuning: Include additional costs for Lighting Control Manufacturer's

Sensor Layout and Tuning service; Equal to Lutron LSC-SENS-LT:

a. Lighting Control Manufacturer to take full responsibility for wired or wireless sensor layout and performance for sensors provided by Lighting Control

Manufacturer.

b. Lighting Control Manufacturer to analyze reflected ceiling plans, via supplied electronic AutoCAD format, and design detailed sensor layout that provides adequate occupancy sensor coverage and ensures occupancy and daylight sensor performance per agreed upon sequence of operations. Contractor to utilize layouts for sensor placement.

c. During startup, Lighting Control Manufacturer to direct Contractor regarding sensor relocation, as required, should conditions require deviation from locations specified in drawings.

d. Lighting Control Manufacturer to provide up to two additional post-startup on-site service visits within one calendar year from Date of Substantial Completion to fine-tune sensor calibration per agreed upon sequence of operations.

2. Provide products listed, classified, and labeled by Underwriter's Laboratories Inc. as suitable for purpose indicated.

3. Unless specifically indicated to be excluded, provide required equipment, conduit, boxes, wiring, connectors, hardware, supports, accessories, software, system programming, etc.

as necessary for complete operating system that provides control intent indicated.

4. Shade Control Requirements:

a. Capable of operating shades and recalling shade presets via keypad, contact closure input, lighting management system software, or other lighting control system interface.

b. Capable of operating any individual, group, or subgroup of shade electronic drive units within system without requiring separate group controllers.

5. Design lighting control equipment for 10-year operational life while operating continually at any temperature in ambient temperature range of 32 degrees F (0 degrees C) to 104 degrees F (40 degrees C) and 90 percent non-condensing relative humidity.

6. Electrostatic Discharge Tolerance: Design and test equipment to withstand electrostatic discharges without impairment when tested according to IEC 61000-4-2.

7. Dimming and Switching/Relay Equipment:

a. Designed so that electrolytic capacitors operate at least 36 degrees F (20 degrees C) below capacitor's maximum temperature rating when device is under fully loaded conditions at maximum rated temperature.

b. Inrush Tolerance:

1) Utilize load-handling thyristors (SCRs and triacs), field effect transistors

(FETs) and isolated gate bipolar transistors (IGBTs) with maximum current rating at least two times rated operating current of dimmer/relay.

2) Capable of withstanding repetitive inrush current of 50 times operating current without impacting lifetime of dimmer/relay.

c. Surge Tolerance: Designed and tested to withstand surges of 6,000 V, 200 amps according to IEEE C62.41.2 without impairment to performance.

d. Power Failure Recovery: When power is interrupted and subsequently restored, within 3 seconds lights to automatically return to same levels, e.g. dimmed setting, full on, or full off, as prior to power interruption.

e. Dimming Requirements:

1) Line Noise Tolerance: Provide real-time cycle-by-cycle compensation for incoming line voltage variations including changes in RMS voltage

(plus or minus 2 percent change in RMS voltage per cycle), frequency shifts (plus or minus 2 Hz change in frequency per second), dynamic harmonics, and line noise.

a) Systems not providing integral cycle-by-cycle compensation to include external power conditioning equipment as part of dimming system.

LIGHTING CONTROL DEVICES 26 09 23 Page - 7

2) Incorporate electronic "soft-start" default at initial turn-on that smoothly ramps lights up to appropriate levels within 0.5 seconds.

3) Utilize air gap off to disconnect load from line supply.

4) Control light sources in smooth and continuous manner. Dimmers with visible steps are not acceptable.

5) Load Types:

a) Assign load type to each dimmer that will provide proper dimming curve for specific light source to be controlled.

b) Provide capability of being field-configured to have load types assigned per circuit.

6) Minimum and Maximum Light Levels: User adjustable on circuit-by-circuit basis.

f. Switching Requirements:

1) Rated Life of Relays: Typical of 1,000,000 cycles at fully rated 16 A for all lighting loads.

2) Switch load in manner that prevents arcing at mechanical contacts when power is applied to and removed from load circuits.

3) Provide output fully rated for continuous duty for inductive, capacitive, and resistive loads.

8. RS485 Communication Between Low-Voltage Devices:

a. Communicate at minimum speed of 10,000 bits per second; systems with slower communication speeds are not acceptable.

b. Support low-voltage communication links up to 2,000 feet (610 m) with 12 AWG wiring with available low-voltage power supplies to extend links farther; systems without this capability are not acceptable.

c. Support both wired and wireless wall controls and sensors; systems without this capability not acceptable.

C. ROOM CONTROLLER / LIGHTING CONTROL MODULE

1. Provide lighting control modules as indicated or as required to control loads as indicated.

2. General Requirements:

a. Listed to UL 508 as industrial control equipment.

b. Comply with NFPA 70 requirements for use in other spaces used for environmental air (plenum).

c. Delivered and installed as listed factory-assembled panel.

d. Passively cooled via free-convection, unaided by fans or other means; modules that require fan cooling not acceptable.

e. Mounting: Surface.

f. Connects to lighting management hub via RS485.

g. LED status indicators confirm communication with occupancy sensors and daylight sensors.

h. Contact Closure Input (select models):

1) Directly accept contact closure input from dry contact closure or solid-state output without interface to:

a) Activate scenes.

(1) Scene activation from momentary or maintained closure.

b) Enable or disable after hours.

(1) Automatic sweep to user-specified level after user-specified time has elapsed.

(2) System provides occupants visual warning prior to sweeping lights to user-specified level.

(3) Occupant can reset timeout by interacting with lighting system.

c) Activate or deactivate demand response (load shed).

(1) Load shed event reduces lighting load by user-specified amount.

i. Emergency Contact Closure Input:

LIGHTING CONTROL DEVICES 26 09 23 Page - 8

1) Turn all zones to full output during emergency state via direct contact closure input from UL 924 listed emergency lighting interface, security system or fire alarm system.

2) Allow configurable zone response during emergency state.

3) Disable control operation until emergency signal is cleared.

j. Supplies power for control link for keypads and control interfaces (select models).

k. Distributes sensor data among multiple lighting control modules.

l. Capable of being controlled via wireless sensors and controls.

m. No minimum load requirement.

3. Normal Lighting Controllers (as defined by “NLC” symbol on plans):

a. Basis of Design: Lutron 0-10V Energi Savr Node; Model QSN-4T20-S: 20 A

(16 A ballast) continuous-use per channel; capable of switching 20A receptacles.

b. Coordination Between Low Voltage Dimming Module and Line Voltage Relay:

Capable of being electronically linked to single zone.

c. Single low voltage dimming module; capable of controlling the following light sources:

1) 0-10V analog voltage signal.

a) Provide Class 2 isolated 0-10V output signal conforming to IEC

60929.

b) Sink current per IEC 60929.

2) 10V-0V analog voltage signal.

a) Provide Class 2 isolated 0-10V output signal conforming to IEC

60929.

b) Sink current per IEC 60929.

d. Switching:

1) Rated Life of Relay: Typical of 1,000,000 cycles at fully rated 16 A for all lighting loads.

2) Load switched in manner that prevents arcing at mechanical contacts when power is applied to and removed from load circuits.

3) Fully rated output continuous duty for inductive, capacitive, and resistive loads.

4) Module to integrate up to four individually controlled zones.

5) Utilize air gap off, activated when user selects "off" at any control to disconnect load from line supply.

4. “Emergency Lighting Controllers” (as defined by “ELC” symbol on plans):

a. Basis of Design Lutron Athena system does not support integrated UL924 bypass capability within the room controllers.

b. Provide a separate UL924 bypass relay wired to outputs of room controller to support emergency fixtures shown…