J.7_06.Mesilla - 100 Specifications.2009_11_13.pdf
PDF 19 MB Posted
- Attached to
- RECOVERY- Mesilla Phase 1 Levee Improvements Federal contract opportunity
- Solicitation number
- IBM10B0002
About this file
IBM10B0002 Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| IBM10B0002-Abstract Spreadsheet.xls | XLS spreadsheet | |
| IBM10B0002 amendment A004.pdf | ||
| attmt4_IBM10B0002_amend A003_all3BidderQuestions_set2.pdf | ||
| IBM10B0002 amend A003.pdf | ||
| attmt2_IBM10B0002_amend A003_MesillaBidderQuestions.pdf | ||
| attmt3_IBM10B0002_amend A003 Hatch_Mesilla_Canutillo_Questions_set1.pdf | ||
| attmt5_IBM10B0002_amend_A003_MesillaQuestions_SET 16_12.pdf | ||
| attmt1_IBM10B0002 amend A003 Mesilla_Addendum_SummaryofPlan_Spec_Revisions_12_11.pdf | ||
| IBM10B0002_amend A002.pdf | ||
| IBM10B0002_Mesilla-quest ans.pdf | ||
| IBM10B0002 amend A001.doc.pdf | ||
| IBM10B0002_prebidattendees.pdf | ||
| J.3_IBWC 110.pdf | ||
| J.4_IBWC 116.pdf | ||
| J.6_sf28.pdf | ||
| IBM10B0002.pdf | ||
| J.5_sf24_f.pdf | ||
| J.2_IBWC 117.pdf | ||
| J.1_wage determination.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINAL
SPECIFICATIONS
FOR
Upper Rio Grande Flood Control Project Rehabilitation Improvements for the
Rio Grande Canalization Protective Levee System Mesilla Levee Segment – Phase I Doña Ana County, New Mexico
Prepared for:
United States Section, International Boundary & Water Commission
Submitted / Prepared by:
Project Manager: Daniel O. Rios Task Manager: James M. Sassin, PE Senior Project Managers: Nelson B. Nuckles Wade Zhao
This document is being submitted for interim review under the authority of James M. Sassin, PE, New Mexico No. 13960. It is not intended for use as bid document, permits, or construction.
Contract No. IBM05D0001 Task Order No. IBM09T0030
November 16, 2009
11/16/09
Rehabilitation Improvements for the Rio Grande Canalization Protective Levee System MESILLA LEVEE SEGMENT – Phase I Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
DIVISION 00-
USIBWC Contract No.: IBM05D0001 PROCUREMENT AND CONTRACTING REQUIREMENTS
US INTERNATIONAL BOUNDARY & WATER COMMISSION
GOVERNING TECHNICAL SPECIFICATIONS AND PROVISIONS
DIVISION 00 – PROCUREMENT AND CONTRACTING
REQUIREMENTS
(INTRODUCTORY / AVAILABLE INFORMATION)
MESILLA LEVEE SEGMENT – Phase I Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
DIVISION 00-
USIBWC Contract No.: IBM05D0001 PROCUREMENT AND CONTRACTING REQUIREMENTS
This Page Intentionally Blank
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
PROJECT TITLE
USIBWC Contract No.: IBM05D0001 Page 00.01.01 - 1
INTRODUCTORY INFORMATION 00.01.01
PROJECT TITLE
The title of this project is as follows:
International Boundary & Water Commission – United States Section Upper Rio Grande Flood Control Project
Rehabilitation Improvements for the Rio Grande Protective Levee System Mesilla Levee System – Phase I Doña Ana County, New Mexico
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
PROJECT TITLE
USIBWC Contract No.: IBM05D0001 Page 00.01.01 - 2
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
TABLE OF CONTENTS
USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 1
TABLE OF CONTENTS
Proposed Specification List
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SPECIFICATION 00 01 01 PROJECT TITLE
SPECIFICATION 00 01 10 TABLE OF CONTENTS
SPECIFICATION 00 01 15 LIST OF CONTRACT DRAWINGS
SPECIFICATION 00 01 20 LIST OF SCHEDULES
SPECIFICATION 00 31 19 EXISTING CONDITION INFORMATION
SPECIFICATION 00 31 21 SURVEY INFORMATION
SPECIFICATION 00 31 24 ENVIRONMENTAL ASSESSMENT INFORMATION
SPECIFICATION 00 31 26 EXISTING HAZARDOUS MATERIAL INFORMATION
SPECIFICATION 00 31 32 GEOTECHNICAL DATA
SPECIFICATION 00 31 43 PERMIT APPLICATION
SPECIFICATION 00 31 50 OTHER PROJECT INFORMATION
DIVISION 01 - GENERAL REQUIREMENTS
SPECIFICATION 01 01 00 IDENTIFICATION OF TECHNICAL SPECIFICATIONS
SPECIFICATION 01 19 00 SCOPE OF WORK
SPECIFICATION 01 27 00 MEASUREMENT AND PAYMENT
SPECIFICATION 01 31 00 PROJECT MANAGEMENT AND COORDINATION
SPECIFICATION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION
SPECIFICATION 01 33 00 SUBMITTALS
SPECIFICATION 01 39 00 SAFETY
SPECIFICATION 01 42 00 REFERENCES
SPECIFICATION 01 46 00 QUALITY CONTROL / QUALITY ASSURANCE
SPECIFICATION 01 51 00 TEMPORARY UTILITIES
SPECIFICATION 01 56 00 BARRICADES AND SIGNS
SPECIFICATION 01 57 00 TEMPORARY EROSION, SEDIMENTATION AND
ENVIRONMENTAL CONTROLS
SPECIFICATION 01 59 00 TEMPORARY CONTROLS FOR WORK AREAS /
PROJECT-SPECIFIC LOCATIONS
SPECIFICATION 01 69 00 CONTROL OF MATERIALS
SPECIFICATION 01 70 00 MOBILIZATION
SPECIFICATION 01 71 00 FIELD ENGINEERING
SPECIFICATION 01 77 00 CONTRACT CLOSE-OUT
DIVISION 02 - EXISTING CONDITIONS
SPECIFICATION 02 02 00 EXISITING CONDITIONS
STANDARD DIVISIONS
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
TABLE OF CONTENTS
USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 2
DIVISIONS 31 / 33 / 34 - SITE GRADING
SPECIFICATION 31 04 00 REMOVE CONCRETE
SPECIFICATION 31 05 00 REMOVING STABILIZED BASE
SPECIFICATION 31 11 00 PREPARING RIGHT OF WAY
SPECIFICATION 31 12 00 OBLITERATE ROADWAY
SPECIFICATION 31 14 00 REMOVE / STOCKPILE EXISTING MATERIALS
SPECIFICATION 31 81 00 PROOF ROLLING
SPECIFICATION 31 92 00 VEGETATION FOR EROSION CONTROL
SPECIFICATION 33 46 00 PIPE UNDERDRAIN
SPECIFICATION 34 01 00 CLEAN EXISTING CHANNELS
DIVISION 35 - WATERWAY / MARINE
SPECIFICATION 35 41 00 CONSTRUCTION OF LEVEE
SPECIFICATION 35 42 00 RIPRAP
SPECIFICATION 35 43 00 TOE DRAIN
DIVISION 50 - ROADWAY CONSTRUCTION
SPECIFICATION 50 11 00 ROADWAY EMBANKMENT
SPECIFICATION 50 12 00 ROADWAY EXCAVATION
SPECIFICATION 50 20 00 ROADWAY BASE
SPECIFICATION 50 91 00 PROVIDE AND INSTALL NEW TRAFFIC SIGNS
SPECIFICATION 50 94 00 DELINEATOR AND OBJECT MARKER ASSEMBLIES
DIVISION 60 - STRUCTURES
SPECIFICATION 60 01 00 FLOWABLE BACKFILL
SPECIFICATION 60 02 00 TRENCH EXCAVATION PROTECTION
SPECIFICATION 60 10 00 EXCAVATION AND BACKFILL FOR STRUCTURES
SPECIFICATION 60 20 00 CONCRETE STRUCTURES
SPECIFICATION 60 21 00 HYDRAULIC CEMENT
SPECIFICATION 60 40 00 REINFORCING STEEL
SPECIFICATION 60 41 00 STEEL STRUCTURES
SPECIFICATION 60 42 00 METAL FOR STRUCTURES
SPECIFICATION 60 45 00 GALVANIZING
SPECIFICATION 60 46 00 CLEANING AND PAINTING STEEL
SPECIFICATION 60 47 00 STRUCTURAL BOLTING
SPECIFICATION 60 48 00 WELDING
SPECIFICATION 60 62 00 CORRUGATED METAL PIPE
SPECIFICATION 60 63 00 CONCRETE BOX CULVERTS AND STORM DRAINS
SPECIFICATION 60 64 00 REINFORCED CONCRETE PIPE
SPECIFICATION 60 65 00 MANHOLES AND INLETS
SPECIFICATION 60 66 00 HEADWALLS AND WINGWALLS
SPECIAL DIVISIONS
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
TABLE OF CONTENTS
USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 3
SPECIFICATION 60 68 00 SLUICE GATE
SPECIFICATION 60 69 00 SLUICS GATE MAINTENANCE
SPECIFICATION 60 79 00 ABANDON & PLUG STRUCTURE
SPECIFICATION 60 81 00 POLYVINYL CHLORIDE PIPE
SPECIFICATION 60 98 00 CLEAN EXISTING STRUCTURES
DIVISION 90 - MISCELLANEOUS
SPECIFICATION 90 79 00 HEAVY DUTY VEHICULAR GATE
SPECIFICATION 90 80 00 REMOVE, REFURBISH AND REPLACE HEAVY DUTY
VEHICULAR GATE
SPECIFICATION 90 81 00 BOULDERS
SPECIFICATION 90 82 00 GEOTEXTILE FABRIC
-END OF SPECIFICATION-
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
TABLE OF CONTENTS
USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 4
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
LIST OF CONTRACT DRAWINGS
USIBWC Contract No.: IBM05D0001 Page 00.01.15 - 1
INTRODUCTORY INFORMATION 00.01.15
LIST OF CONTRACT DRAWINGS
The Contract Drawings applicable to this Contract are entitled: “United States Section International Boundary and Water Commission, Upper Rio Grande Flood Control Project, Rehabilitation Improvements for the Rio Grande Canalization Protective Levee System, Mesilla Levee Segment – Phase I, Doña Ana County, New Mexico.” An index of drawings is identified on the title sheet, and includes the following:
INDEX OF SHEETS - MESILLA LEVEE SEGMENT – PHASE I
SHEET NO. DESCRIPTION
GENERAL
1.0 TITLE SHEET
2.01-2.08 PROJECT LAYOUT
2.09-2.16 SURVEY CONTROL POINTS
3.01 – 3.02 GENERAL NOTES
4.01 ESTIMATE OF QUANTITIES
5.01 – 5.03 SUMMARY OF QUANTITIES
5.04 SUMMARY OF SMALL STRUCTURES
TYPICAL SECTIONS
6.01 EXISTING TYPICAL SECTIONS
6.02 – 6.06 PROPOSED TYPICAL SECTIONS
LEVEE DETAILS
7.01 – 7.39 ALIGNMENT DATA SHEETS
8.001 – 8.046 MW1 REACH PLAN & PROFILE
8.047 – 8.097 ME2 REACH PLAN & PROFILE
8.098 – 8.148 MW2 REACH PLAN & PROFILE
8.149 – 8.166 MW1 REACH ACCESS RAMPS PLAN & PROFILE
8.167 - 8.185 ME2 REACH ACCESS RAMPS PLAN & PROFILE
8.186 - 8.209 MW1 REACH ACCESS RAMPS PLAN & PROFILE
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
LIST OF CONTRACT DRAWINGS
USIBWC Contract No.: IBM05D0001 Page 00.01.15 - 2
09.01 – 09.45 BORE LOGS
10.001 – 10.116 MW1 REACH CROSS SECTIONS
10.117 – 10.249 ME2 REACH CROSS SECTIONS
10.250 – 10.378 MW2 REACH CROSS SECTIONS
11.01 MISCELLANEOUS SIGN DETAILS
12.01 – 12.09 STRUCTURE LAYOUTS
12.10 – 12.33 CULVERT LAYOUTS
12.34 – 12.51 MISCELLANEOUS DETAILS
EROSION
13.01 – 13.02 STORM WATER POLLUTION PREVENTION PLANS (SW3P)
ENVIRONMENTAL COMMITMENTS / MITIGATION
14.01 ENVIRONMENTAL PERMITS, ISSUES AND COMMITMENTS (EPIC)
STANDARDS
15.01 GENERAL NOTES AND SEQUENCE OF WORK
15.02 – 15.09 BARRICADES / TRAFFIC CONTROL
15.10 – 15.12 SIGN STANDARDS
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
LIST OF SCHEDULES
USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 1
INTRODUCTORY INFORMATION 00.01.20
LIST OF SCHEDULES
1. Schedule of Submittals. For this Project, the requirements for submittals are identified on the Contract Drawings and Technical Specifications (Divisions 01, 02, 31, 33, 34, 35, 50, 60, and 90). For this project, a schedule of submittals includes, but may not be limited to the following: (The Contractor shall refer to each Technical Specification for a full description of applicable submittals and submittal requirements.)
SPECIFICATION Submittal 01 32 00 Construction Progress Documentation Progress Schedule 01 39 00 Safety Accident Prevention Plan 01 46 00 Quality Control / Quality Assurance Contractor Quality Control Plan, Certifications for
Testing Personnel 01 51 00 Temporary Utilities 01 56 00 Barricades and Signs Traffic Control, Barricade and Signing Plans
Written Certification of Temporary Barriers 01 57 00 Temporary Erosion, Sedimentation, And
Environmental Controls FEM Qualifications
SW3P
Construction Plan
01 59 00 Temporary Controls For Work Areas / Project-Specific Locations
Staging Area Plan Layout
SW3P
Hazardous Materials Tests Hazardous Waste Manifests
01 69 00 Control of Materials Materials Source Identification and Certifications 01 70 00 Mobilization 01 71 00 Field Engineering Survey Plan and Submittals 01 77 00 Contract Close-Out As-Built Plans, Reports, Drawings
Final Inspection / Testing Records 02 02 00 Existing Conditions & Facilities Flood Protection Plan
Video Tape 31 04 00 Remove Concrete 31 05 00 Removing Stabilized Base and Asphalt
Pavement 31 11 00 Preparing Right of Way 31 12 00 Obliterate Roadway 31 14 00 Remove / Stockpile Existing Materials 31 81 00 Proof Rolling 31 92 00 Vegetation for Erosion Control Seeding Plan 33 46 00 Pipe Underdrain 34 01 00 Clean Existing Channel
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
LIST OF SCHEDULES
USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 2
35 41 00 Construction Of Levee Plan of Operations, Testing Facilities, Testing Results for Classification of Fill Material, Nuclear-Density Operator Certification, Test Results for Construction, Designs and Details for Contractor Repairs, Dewatering Controls, Excavation or Fill Support Details Moisture Content Adjustment Plan
35 42 00 Rip Rap Geotextile Membrane, Data, Product Warranty & Certification Submittal
35 43 00 Toe Drain Manufacturer’s Literature, Samples, & Written Material Specs
Sequence of Toe Drain Installation
50 11 00 Roadway Embankment 50 12 00 Roadway Excavation 50 20 00 Roadway Base 50 91 00 Provide and Install New Traffic Signs 50 94 00 Delineator and Object Marker Assemblies 60 01 00 Flowable Backfill 60 02 00 Trench Excavation Protection 60 10 00 Excavation and Backfill for Structures Details and Design Calculations 60 20 00 Concrete Structures Falsework and/or Forming Plans Submittals
Construction Methods Submittal Epoxy, Steel dowels, Construction joint Material, and
Steel Bolts Product information and testing Certifications
60 21 00 Hydraulic Cement Concrete Plant Admixture Certifications
Concrete Mix Design Grout Mix Design
60 38 00 Clean and Seal Joints Information from the sealant manufacturer showing recommended equipment and installation procedures.
60 40 00 Reinforcing Steel Chemical Analysis Report
Material Certifications 60 41 00 Steel Structures Erection Drawings
Welding Shop Drawings Welding, Bolting and Fabrication Procedures
Non-Conformance Reports Bolt Correction Methods
60 42 00 Metal For Structures Mill Test Reports, Supplemental Test Documentation, and Certifications
60 45 00 Galvanizing
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
LIST OF SCHEDULES
USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 3
60 46 00 Cleaning and Painting Steel Cleaning and Painting Certifications Painting Methods Containment Plan
Loads Analysis MSDS Sheet
60 47 00 Structural Bolting 60 48 00 Structural Field Welding Certified Testing Reports
Welder Certification or Qualification
WPS
Laboratory Certification Straightening Procedure
60 62 00 Corrugated Metal Pipe 60 63 00 Concrete Box Culverts and Storm Drains 60 64 00 Reinforced Concrete Pipe 60 65 00 Manholes and Inlets 60 66 00 Headwalls and Wingwalls 60 67 00 Slope End-Safety and Treatment 60 68 00 Sluice Gate Gate and Lift Mechanism Shop Drawings and
Manufacturer’s Qualifications Design Calculations
60 69 00 Sluice Gate Maintenance Shop Drawing Replaced/Remanufactured Parts
60 79 00 Abandon and Plug Structure 60 81 00 Polyvinyl Chloride Pipe Material Certification 60 96 00 Removing Existing Structures 60 98 00 Clean Existing Structures 90 79 00 Vehicular Gate
90 80 00 Remove, Refurbish, and Reinstall Heavy Duty Vehicular Gate
90 81 00 Boulders Rough Dimensions of Boulders 90 82 00 Geotextile Fabric Catalog Cut and Samples of Materials
Manufacturer’s Certification and Installation Procedures
2. Schedule of Assemblies, Materials, and Estimated Quantities. For this Project, the schedules of assemblies, material specifications and associated estimated quantities are identified on the Contract Drawings and Technical Specifications (Divisions 01, 02, 31, 33, 34, 35, 50, 60, and 90). Estimated quantities for each Bid Item are shown on Plan Sheet No. 4.01; and estimated quantities are also summarized by plan sheet on Plan Sheet Nos. 5.01 and 5.04.
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
LIST OF SCHEDULES
USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 4
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
EXISTING CONDITION INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.19 - 1
AVAILABLE INFORMATION 00.31.19
EXISTING CONDITION INFORMATION
The existing condition of the levee has been evaluated by the Government, and is included in a report entitled “Condition Assessment of U.S. International Boundary & Water Commission, Texas and New Mexico Levees” by the US Army Corps of Engineers (USACE) dated June 2004, and the “Flood Simulation Study of Rio Grande Levees Near Las Cruces, New Mexico, Using Seismic and Electrical Geophysical Methods” dated May 2007.The applicable sections of this report are available to the Contractor for the purposes of understanding the existing condition of the levee within the project limits of this Contract. Additionally, geotechnical investigations were performed during the final design of the project, and the associated geotechnical data and reports are identified in 00.31.32 Geotechnical Data herein.
- END OF SPECIFICATION -
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
EXISTING CONDITION INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.19 - 2
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
SURVEY INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.21 - 1
AVAILABLE INFORMATION 00.31.21
SURVEY INFORMATION
For these Contract Drawings, surveying and data collection was performed as follows:
(1) Light Detection and Ranging (LIDAR) was obtained from the Government and used for preliminary information.
(2) Control was performed in April / May 2009 by Frank X. Spencer & Associates., who developed and provided the following (at .01-foot accuracy):
(a) Control. The surveyor established points at cross-roads to establish horizontal and vertical control; control sheets were developed for each control point set, signed and sealed by a New Mexico Registered Professional Land Surveyor (RPLS), as appropriate. The control sheet includes a drawing of the control point with a 3-point tie to existing physical features, description of the control point, X,Y & Z coordinates and the coordinate system. Plan Sheet No. 2.08-2.09, within the Contract Drawings includes the control information data for all the control points set for the project, signed and sealed by the RPLS.
(b) Benchmarks. The surveyor established bench marks along project limits; vertical benchmarks were set at 1000-foot intervals at the right of way (ROW) line of the levee reach. A tabulation of the benchmarks is shown on Plan Sheet No. 2.11 – 2.16 the Contract Drawings.
(3) Ultimately, an aerial survey (at 0.1-foot accuracy) was performed in April / May 2009 by Martinez Corporation who developed and provided the following, which was used as the basis of design:
(a) Field Control for Photogrammetry. The surveyor set panels for aerial photogrammetry along the levee reach for a low-level flight (1500 feet). Panels were set along the flight path at 800-foot intervals and wing panels were set at cross-roads or 2400-foot intervals. The surveyor performed a global positioning (GPS) survey to establish X-Y-Z coordinates of the panel points.
(b) Aerial Photogrammetry. The aerial photogrammetry was developed as follows:
1. Black and white photography at a 1-inch = 250-foot photo scale (1500 feet above ground level (AGL))
2. Data Processing. The aerial photography was scanned at 12 microns to produce 0.25-foot pixel resolution; aerial triangulation process was performed to orient individual stereo pairs.
3. Planimetric and Topographic Data Compilation. Planimetric and topographic data was compiled (suitable for 1-inch = 50-foot map scale showing 1-foot contours.
4. Digital Orthophotos. A digital elevation model (DEM) or should this be DTM? was created for the project area to support the orthophoto rectification; rectified mosaic digital
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
SURVEY INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.21 - 2 images to hold 0.25-foot ground pixel resolutions suitable for a 1-inch = 50-foot map scale.
(4) Supplemental ground surveys were performed by SLI Engineering Inc., Frank X and Spencer & Associates as follows:
(a) Voids. A topographic survey was performed by the surveyors to fill-in the voids of the aerial planimetrics; additionally, the surveyor performed topographic survey on existing structures, including bridges, inlets, culverts and irrigation structures.
(b) ROW Verification. The surveyors recovered and staked ROW points from available ROW maps supplied by the Government. This ROW information is shown on the plan / profile sheets of the Contract Drawings.
(c) Utility Survey. The surveyors coordinated with utility notification companies to get utilities marked in the field; the surveyor performed field location of underground utilities as marked by utility companies along the levee reach and intersecting streets. These locations are shown on the plan / profile sheets of the Contract Drawings. NOTE: IT IS THE CONTRACTOR’S
RESPONSIBILITY TO VERIFY LOCATIONS OF ALL EXISTING UTILITIES (SHOWN
AND NOT SHOWN ON THE CONTRACT DRAWINGS) PRIOR TO CONSTRUCTION.
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
ENVIRONMENTAL ASSESSMENT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.24 - 1
AVAILABLE INFORMATION 00.31.24
ENVIRONMENTAL ASSESSMENT INFORMATION
The Project’s environmental documentation for the Rio Grande Canalization Project includes the following:
1) Final Environmental Assessment Flood Control Improvements to the Rio Grande Canalization Project, December 2007;
2) Final Environmental Impact Statement River Management Alternatives for the USIBWC Rio Grande Canalization Project, June 2004;
3) Record of Decision on River Management Alternatives EIS for the Rio Grande Canalization Project, June 2009.
All of these documents are available on the USIBWC website at:
www.ibwc.state.gov/Organization/Environmental/reports_studies.html.
http://www.ibwc.state.gov/Organization/Environmental/reports_studies.html.
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
ENVIRONMENTAL ASSESSMENT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.24 - 2
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
EXISTING HAZARDOUS MATERIAL INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.26 - 1
AVAILABLE INFORMATION 00.31.26
EXISTING HAZARDOUS MATERIAL INFORMATION
There is no available information regarding hazardous materials within / adjacent to the Project limits and/or right of way.
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
EXISTING HAZARDOUS MATERIAL INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.26 - 2
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
GEOTECHNICAL DATA
USIBWC Contract No.: IBM05D0001 Page 00.31.32 - 1
AVAILABLE INFORMATION 00.31.32
GEOTECHNICAL DATA
Geotechnical investigations were performed by Raba-Kistner Consultants, Inc.
The Contractor may request a copy of the report from the Government.
The data and report are not intended as a representation or warranty of continuity of conditions between soil borings nor of groundwater levels at dates and times other than date and time when measured. The Government will not be responsible for interpretations or conclusions drawn there from by the Contractor.
Data are solely made available for the convenience of Contractor. Additional test borings and other exploratory operations may be made by Contractor subsequent to award of the Contract at no additional cost to the Government.
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
GEOTECHNICAL DATA
USIBWC Contract No.: IBM05D0001 Page 00.31.32 - 2
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
PERMIT APPLICATION
USIBWC Contract No.: IBM05D0001 Page 00.31.43 - 1
AVAILABLE INFORMATION 00.31.43
PERMIT APPLICATION
No information is available regarding required permit applications. The Contractor will be required to research the need for any required permits. For the Work under this Contract, the Contractor shall be responsible for coordinating and obtaining all permits required by Federal, state, and local entities.
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
PERMIT APPLICATION
USIBWC Contract No.: IBM05D0001 Page 00.31.43 - 2
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 1
X (EASTING) Y (NORTHING)
MW1 151+00.00 151+21.88 1,458,335.94 495,703.11 36-inch RCP IBWC / L 2.61 Plug structure MW1 185+50.00 185+72.86 1,457,467.58 492,373.44 QTY 4 - 5-foot X 5-foot RCB Irrigation IBWC / L 2.62 Clean channel on both sides MW1 240+18.00 240+99.25 1,458,803.82 487,414.24 30-inch RCP IBWC / L 2.64 Plug structure MW1 299+74.00 299+87.13 1,459,849.15 481,759.82 30-inch RCP Irrigation IBWC / L 2.66 Install flap gate on river side; Clean channel on both sides MW1 341+00.00 341+20.34 1,461,243.54 477,878.10 24-inch RCP IBWC / L 2.69 Plug structure MW1 416+35.00 416+56.43 1,462,272.02 470,527.39 30-inch RCP IBWC / L 2.70 Plug structure MW1 490+00.00 490+52.58 1,461,251.09 463,246.23 30-inch RCP IBWC / L 2.75 Plug structure
MW1 504+52.00 505+02.49 1,461,171.31 461,814.65 48-inch CMP Irrigation IBWC / L 2.76 Add headwall,wingwalls, and flap gate on river side; Clean channel on river side
MW1 584+80.00 585+39.22 1,463,996.67 454,944.38 30-inch RCP Drainage IBWC / L 2.79 Plug structure
MW1 590+36.00 590+90.10 1,463,532.21 454,652.60 5-foot X 4-foot RCB Drainage IBWC / L 2.80 Extend culvert, replace headwall, wingwalls, and flap gate on river side; Clean channel on river side
ME2 26+49.00 28+62.38 1,473,301.28 445,661.42 48-inch RCP Irrigation USBR / L 2.29 Ltr 5/5/39 Plug structure ME2 165+35.00 168+87.90 1,484,820.30 438,034.44 30-inch RCP USBR / L 2.30 Ltr 11/5/38 Plug structure ME2 197+75.00 200+58.31 1,487,265.43 436,016.32 30-inch RCP Irrigation USBR / LSF/G-954 Replace flap gate on river side ME2 230+10.00 232+66.91 1,489,740.02 433,973.88 QTY 2 - 4-foot X 4-foot RCB Irrigation IBWC / L 2.31 Replace headwall on land side; Clean channel on both sides ME2 396+00.00 398+55.54 1,498,584.88 421,356.50 30-inch RCP Irrigation USBR / L 2.37 Ltr 9/23/39 Extend RCP and replace headwall on river side ME2 415+60.00 418+14.01 1,500,262.15 420,402.91 42-inch RCP IBWC / L 2.40 Plug structure ME2 444+70.00 447+23.71 1,501,291.60 417,783.59 30-inch RCP IBWC / L 2.41 None. (Already plugged with concrete) ME2 531+70.00 537+84.40 1,506,684.39 411,001.23 QTY 2 - 4-foot X 4-foot RCB Irrigation IBWC / L 2.44 Repair wingwall on river side MW2 321+40.00 323+53.37 1,494,838.11 426,282.55 42-inch RCP Drainage IBWC / L 2.33 Plug structure
MW2 323+40.00 325+54.30 1,494,957.68 426,121.08 30-inch RCP Irrigation USBR / L 2.34 Extend RCP, replace headwall, wingwalls and flap gate on river side
MW2 353+85.00 356+01.17 1,495,621.06 423,244.85 24-inch RCP Drainage IBWC / 2.35 Plug structure MW2 363+45.00 365+59.33 1,495,717.09 422,299.26 QTY 2 - 5-foot X 6-foot RCB Irrigation IBWC / 2.36 Clean channel on river side MW2 463+62.00 466+52.90 1,501,203.62 415,279.20 48-inch RCP Irrigation IBWC / 2.42 Install flap gate on river side; Clean channel on river side MW2 594+50.00 601+39.31 1,510,112.93 405,495.08 24-inch RCP IBWC / L 2.45 Plug structure
PROPOSED RECOMMENDATIONSSTRUCTURE
USAGE OWNER / USIBWC LICENSEREACH
COORDINATESCENTERLINE
STATION STRUCTURE SIZE
BASELINE
STATION
AVAILABLE INFORMATION 00.31.50
OTHER PROJECT INFORMATION
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 2
(a) Structure Centerline Station No. 151+21.88 (Baseline Station No. 151+00.00; X=1458335.94, Y=495703.11) This facility is Located on the Mesilla Segment 1(West Levee) at Centerline Station 151+21.88. This facility is owned by the USIBWC; and, it has been abandoned and/or covered.
Figure 151+21.88: Layout of Structure at 151+21.88
Photo 151+21.88: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 3
Structure Recommendation Summary: The structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION TYPE AND SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
151+21.88 1-36” RCP
CONDITION Abandoned/ Covered
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 4
(b) Structure M.P No. 48.75, Centerline Station No. 185+72.86 (Baseline Station No. 185+50.00; X=1457467.58, Y=492373.44) This facility is Located on the Mesilla Segment 1(West Levee) at River Mile Point 48.75 Picacho Lateral Waste Way No. 39. This facility is owned by the USIBWC; and, it is used to irrigate the land side of the levee. It has control gates on the river side which allow it to remain closed during the event of a flood.
Figure 185+72.86: Layout of Structure at 185+72.86
Photo 185+72.86-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 5
Photo 185+72.86-02: Looking at end treatment, located on land side
Photo 185+72.86-03: Looking at sluice gates, located on river side
Structure Recommendation Summary: The channel on both the land and river side needs to be cleaned.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
185+72.86 4-5’x5’ MBC 15° Wingwalls 15° Wingwalls 4 -62”x62” Sluice
CONDITION GOOD GOOD GOOD
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 6
(c) Structure Centerline Station No. 240+99.25 (Baseline Station No. 241+18.00; X=1458803.82, Y=487414.24) This facility is Located on the Mesilla Segment 1(West Levee) at Centerline Station 240+99.25. This facility is owned by the USIBWC; and, it has been abandoned and/or covered.
Figure 240+99.25: Layout of Structure at 240+99.25
Photo 240+99.25: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 7
Structure Recommendation Summary: The structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION TYPE AND SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
240+99.25 1-30” RCP
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 8
(d) Structure M.P No. 46.6, Centerline Station No. 299+87.13 (Baseline Station No. 299+74.00; X=1459849.15, Y=481759.82) This facility is Located on the Mesilla Segment 1(West Levee) at River Mile Point 46.6 Lateral A Waste Way No. 39A. This facility is owned by the USIBWC; and, it is used to irrigate the land side of the levee.
Figure 299+87.13: Layout of Structure at 299+87.13
Photo 299+87.13-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 9
Photo 299+87.13-02: Looking at end treatment, located on land side
Photo 299+87.13-03: Looking at end treatment, located on river side
Structure Recommendation Summary: A flap gate needs to be installed on the river side. The channel on both the land and river side needs to be cleaned.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
299+87.13 1-30” RCP 15° Wingwalls 15° Wingwalls
CONDITION GOOD GOOD
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 10
(e) Structure Centerline Station No. 341+20.34 (Baseline Station No. 341+00.00; X=1461243.54, Y=477878.10) This facility is Located on the Mesilla Segment 1(West Levee) at Centerline Station 341+20.34. This facility is owned by the USIBWC; and, it has been abandoned and/or covered.
Figure 341+20.34: Layout of Structure at 341+20.34
Photo 341+20.34: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 11
Structure Recommendation Summary: The structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION TYPE AND SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
341+20.34 1-24” RCP
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 12
(f) Structure Centerline Station No. 416+56.43 (Baseline Station No. 416+35.00; X=1462272.02, Y=470527.39) This facility is Located on the Mesilla Segment 1(West Levee) at Centerline Station 416+56.43. This facility is owned by the USIBWC; and, it has been abandoned and/or covered.
Figure 416+56.43: Layout of Structure at 416+56.43
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 13
Photo 416+56.43: Aerial Photo of Location of Structure
Structure Recommendation Summary: The structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION TYPE AND SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
416+56.43 1-30” RCP
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 14
(g) Structure Centerline Station No. 490+52.58 (Baseline Station No. 490+00.00; X=1461251.09, Y=463246.23) This facility is Located on the Mesilla Segment 1(West Levee) at Centerline Station 490+52.58. This facility is owned by the USIBWC; and, it has been abandoned and/or covered.
Figure 490+52.58: Layout of Structure at 490+52.58
Photo 490+52.58: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 15
Structure Recommendation Summary: The structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION TYPE AND SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
490+52.58 1-30” RCP
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 16
(h) Structure M.P No. 42.7, Centerline Station No. 505+02.49 (Baseline Station No. 504+52.00; X=1461171.31, Y=461814.65) This facility is Located on the Mesilla Segment 1(West Levee) at River Mile Point 42.7 Main Picacho Lateral Waste Way No. 40. This facility is owned by the USIBWC; and, it is used to irrigate the land side of the levee. It has a control gate on the land side which restricts outflow to the river.
Figure 505+02.49: Layout of Structure at 505+02.49
Photo 505+02.49-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 17
Photo 505+02.49-02: Looking at headwall and weir structure, located on land side
Photo 505+02.49-03: Looking at metal pipe, located on river side
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 18
Structure Recommendation Summary: A headwall, wingwalls, and flap gate need to be installed on the river side. The channel on the river side needs to be cleaned.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
505+02.49 1-48” CMP Weir Structure 6’x4’ Slide Gate at
Weir structure, 7’ in front of headwall
CONDITION GOOD GOOD
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 19
(i) Structure Centerline Station No. 585+39.22 (Baseline Station No. 584+80.00; X=1463996.67, Y=454944.38) This facility is Located on the Mesilla Segment 1(West Levee) at Centerline Station 585+39.22. This facility is owned by the USIBWC; and, it is used to convey storm water runoff from the land side of the levee to the river. It has a control gate on the river side which allows it to remain closed during the event of a flood.
Figure 585+39.22: Layout of Structure at 585+39.22
Photo 585+39.22-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 20
Photo 585+39.22-02: Looking at end treatment, located on land side
Photo 585+39.22-03: Looking at flap gate, located on river side
Structure Recommendation Summary: Structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
585+39.22 1-30” RCP 45° Wingwalls 45° Wingwalls 32” Flap
CONDITION GOOD
Minor chips and vertical crack on top of pipe Fair
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 21
(j) Structure M.P No. 41.2, Centerline Station No. 590+90.10 (Baseline Station No. 590+36.00; X=1463532.21, Y=454652.60) This facility is Located on the Mesilla Segment 1(West Levee) at River Mile Point 41.2 Picacho Drain. This facility is owned by the USIBWC; and, it is used to convey storm water runoff from the land side of the levee to the river. It has a control gate on the river side which allows it to remain closed during the event of a flood.
Figure 590+90.10: Layout of Structure at 590+90.10
Photo 590+90.10-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 22
Photo 590+90.10-02: Looking at flap gate, located on river side
Photo 590+90.10-03: Looking at end treatment, located on land side
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 23
Structure Recommendation Summary: The culvert needs to be extended and the headwall, wingwalls, and flap gate replaced on the river side. The channel on the river side needs to be cleaned.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
590+90.10 1-5’x4’ SBC 15° Wingwalls 15° Wingwalls 6’x6’ Flap
CONDITION GOOD GOOD Poor
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 24
(k) Structure Centerline Station No. 28+62.38 (Baseline Station No. 26+49.00; X=1473301.28, Y=445661.42) This facility is Located on the Mesilla Segment 2(East Levee) at Centerline Station 28+62.38 Del Rio Lateral. This facility is owned by the USBR; and, it is used to irrigate the land side of the levee. It has a control gate on the river side which allows it to remain closed during the event of a flood.
Figure 28+62.38: Layout of Structure at 28+62.38
Photo 28+62.38-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 25
Photo 28+62.38-02: Looking at sluice gate, located on land side
Photo 28+62.38-03: Looking at end treatment, located on river side
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 26
Structure Recommendation Summary: The structure needs to be plugged with concrete since it is heavily silted over and by plugging it, the number of openings in the levee will be reduced.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
28+62.38 1-48” RCP 0° Wingwalls 5° Wingwalls Sluice
CONDITION GOOD GOOD Silt build-up in channel
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 27
(l) Structure Centerline Station No. 40+00.00 This facility is Located on the Mesilla Segment 2(East Levee) at Centerline Station 40+00.00.
Photo 40+00.00-01: Looking at cable way, located on river side
Structure Recommendation Summary: None.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
40+00.00 Cable Way to measure water surface N/A N/A N/A N/A
CONDITION
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 28
(m)Structure M.P No. 35.5, Centerline Station No. 168+87.90 (Baseline Station No. 165+35.00; X=1484820.30, Y=438034.44) This facility is Located on the Mesilla Segment 2(East Levee) at River Mile Point 35.5. This facility is owned by the USBR.
Figure 168+87.90: Layout of Structure at 168+87.90
Photo 168+87.90: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 29
* Structure was not found out in the field. Size was taken from alignment map.
Structure Recommendation Summary: The structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
168+87.86 30” RCP*
CONDITION
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 30
(n) Structure Centerline Station No. 200+58.31 (Baseline Station No. 197+75.00; X=1487265.43, Y=436016.32) This facility is Located on the Mesilla Segment 2(East Levee) at Centerline Station 200+58.31 Del Rio Lateral WW. This facility is owned by the USBR; and, it is used to irrigate the land side of the levee. It has two control gates, one on river side and one on land side, which allow it to remain closed during the event of a flood.
Figure 200+58.31: Layout of Structure at 200+58.31
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 31
Photo 200+58.31-01: Aerial Photo of Location of Structure
Photo 200+58.31-02: Looking at flap gate, located on river side
Photo 200+58.31-03: Looking at sluice gate, located on land side
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 32
Structure Recommendation Summary: The flap gate on the river side needs to be replaced.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
200+58.31 1-30” RCP 0° Wingwalls 0° Wingwalls 30” Sluice 30” Flap
CONDITION GOOD GOOD GOOD Poor
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 33
(o) Structure M.P No. 34.9, Centerline Station No. 232+66.91 (Baseline Station No. 230+10.00; X=1489740.02, Y=433973.88) This facility is Located on the Mesilla Segment 2(East Levee) at River Mile Point 34.9 Mesilla Lateral Waste Way No. 15. This facility is owned by the USIBWC; and, it is used to irrigate the land side of the levee. It has control gates on the river side which allow it to remain closed during the event of a flood.
Figure 232+66.91: Layout of Structure at 232+66.91
Photo 232+66.91-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 34
Photo 232+66.91-02: Looking at end treatment, located on land side
Photo 232+66.91-03: Looking at sluice gates, located on river side
Structure Recommendation Summary: The headwall needs to be replaced on the land side. The channel on both the land and river side needs to be cleaned.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
232+66.91 2-4’x4’ MBC 15° Wingwalls 30° Wingwalls 2-4’x4’ Sluice
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 35
(p) Structure Centerline Station No. 398+55.54 (Baseline Station No. 396+00.00; X=1498584.88, Y=421356.50) This facility is Located on the Mesilla Segment 2(East Levee) at Centerline Station 398+55.54 Brazito River Lateral WW. This facility is owned by the USBR; and, it is used to irrigate the land side of the levee. It has a control gate on the land side which allows it to remain closed during the event of a flood.
Figure 398+55.54: Layout of Structure at 398+55.54
Photo 398+55.54-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 36
Photo 398+55.54-02: Looking at sluice gate, located on land side
Photo 398+55.54-03: Looking at end treatment, located on river side
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 37
Structure Recommendation Summary: The pipe needs to be extended and the headwall replaced on the river side.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
398+55.54 1-30” RCP Headwall 0° Wingwalls Sluice
CONDITION GOOD GOOD Fair
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 38
(q) Structure Centerline Station No. 418+14.01 (Baseline Station No. 415+60.00; X=1500262.15, Y=420402.91) This facility is Located on the Mesilla Segment 2(East Levee) at Centerline Station 418+14.01. This facility is owned by the USIBWC; and, it has been abandoned and/or covered.
Figure 418+14.01: Layout of Structure at 418+14.01
Photo 418+14.01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 39
Structure Recommendation Summary: The structure needs to be plugged with concrete.
END TREATMENT GATE
STRUCTURE
STATION TYPE AND SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
418+14.01 1-42” RCP
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 40
(r) Structure Centerline Station No. 447+23.71 (Baseline Station No. 444+70.00; X=1501291.60, Y=417783.59) This facility is Located on the Mesilla Segment 2(East Levee) at Centerline Station 447+23.71. This facility is owned by the USIBWC; and, it has been abandoned and/or covered.
Figure 447+23.71: Layout of Structure at 447+23.71
Photo 447+23.71: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 41
Structure Recommendation Summary: None.
END TREATMENT GATE
STRUCTURE
STATION TYPE AND SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
447+23.71 1-30” RCP
CONDITION Plugged w/Concrete
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 42
(s) Structure Centerline Station No. 537+84.40 (Baseline Station No. 531+70.00; X=1506684.39, Y=411001.23) This facility is Located on the Mesilla Segment 2(East Levee) at Centerline Station 537+84.40 Waste Way #18. This facility is owned by the USIBWC; and, it is used to irrigate the land side of the levee. It has control gates on the river side which allow it to remain closed during the event of a flood.
Figure 537+84.40: Layout of Structure at 537+84.40
Photo 537+84.40-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 43
Photo 537+84.40-02: Looking at end treatment, located on land side
Photo 537+84.40-03: Looking at sluice gates, located on river side
Structure Recommendation Summary: The wingwalls on river side need to be repaired.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
537+84.40 2-4’x4’ MBC 45° Wingwalls 45° Wingwalls 2-4’x4’ Sluice
CONDITION GOOD Headwall-GOOD;
Wingwall-Spalling GOOD
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 44
(t) Structure M.P No. 33.2, Centerline Station No. 323+53.37 (Baseline Station No. 321+40.00; X=1494838.11, Y=426282.55) This facility is Located on the Mesilla Segment 2(West Levee) at River Mile Point 33.2 Santo Tomas River Drain. This facility is owned by the USIBWC; and, it is used to convey storm water runoff from the land side of the levee to the river. It has one control gate on the river side which allows it to remain closed during the event of a flood.
Figure 323+53.37: Layout of Structure at 323+53.37
Photo 323+53.37-01: Aerial Photo of Location of Structure
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 45
Photo 323+53.37-02: Looking at headwall, located on land side
Photo 323+53.37-03: Looking down towards headwall, located on river side
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 46
Structure Recommendation Summary: The structure needs to be plugged with concrete since it is heavily silted over and by plugging it, the number of openings in the levee will be reduced.
END TREATMENT GATE
STRUCTURE
STATION
TYPE AND
SIZE LAND SIDE RIVER SIDE LAND SIDE RIVER SIDE
323+53.37 1-42” RCP 180° Wingwalls 180° Wingwalls 42” Flap
CONDITION Fair Fair Poor
MESILLA LEVEE SEGMENT – PHASE I
Doña Ana County, New Mexico Contract No. IBM05D0001 Order No. IBM09T0030
OTHER PROJECT INFORMATION
USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 47
(u) Structure M.P No.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .