attmt4_IBM10B0002_amend A003_all3BidderQuestions_set2.pdf

PDF 9 KB Posted

Attached to
RECOVERY- Mesilla Phase 1 Levee Improvements Federal contract opportunity
Solicitation number
IBM10B0002
Issued by
International Boundary and Water Commission U.S.-Mexico

About this file

Attachment 4 to Amendment A003 IBM10B0002 Mesilla

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY- Mesilla Phase 1 Levee Improvements, newest first.
File Type Posted
IBM10B0002-Abstract Spreadsheet.xls XLS spreadsheet
IBM10B0002 amendment A004.pdf PDF
attmt1_IBM10B0002 amend A003 Mesilla_Addendum_SummaryofPlan_Spec_Revisions_12_11.pdf PDF
IBM10B0002 amend A003.pdf PDF
attmt2_IBM10B0002_amend A003_MesillaBidderQuestions.pdf PDF
attmt3_IBM10B0002_amend A003 Hatch_Mesilla_Canutillo_Questions_set1.pdf PDF
attmt5_IBM10B0002_amend_A003_MesillaQuestions_SET 16_12.pdf PDF
IBM10B0002_amend A002.pdf PDF
IBM10B0002_Mesilla-quest ans.pdf PDF
IBM10B0002 amend A001.doc.pdf PDF
IBM10B0002_prebidattendees.pdf PDF
J.1_wage determination.pdf PDF
J.5_sf24_f.pdf PDF
J.2_IBWC 117.pdf PDF
J.3_IBWC 110.pdf PDF
J.4_IBWC 116.pdf PDF
J.6_sf28.pdf PDF
IBM10B0002.pdf PDF
J.7_06.Mesilla - 100 Specifications.2009_11_13.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BIDDER QUESTIONS SUMMARY

Project: Rehabilitation of Improvements for the Rio Grande Canalization Protective Levee System

River Segment Upper Rio Grande By:

Task Order: IBM09T0030 S&B Infrastructure, Ltd.

Client: IBWC Combined Bidders Questions Hatch, Canutillo & Mesilla Date: 12/11/2009

Ite m

N o.

B id

P kg

Date Contractor Contractor Comment Agree (Y/N) S&B Response Comments Respon der

All three Hatch, Canutillo , Mesilla

12/10/09 Skanska USA Civil West RMD

This message is sent regarding the Specification 60 69 00, Sluice Gate Maintenance, in the above-referenced projects. We have the following concerns:It seems that the existing gates on these projects are from different manufacturers. We will require a list of the manufacturer of each gate to know who to contact. Coordinating with suppliers is the responsibility of the Contractor

All three Hatch, Canutillo , Mesilla

12/10/09 Skanska USA Civil West RMD

It is difficult at this time to determine the condition and the scope of the maintenance required at each individual gate. We request that the specification describe exactly what the Government wants done to each gate to be able to have the manufacturers give us a price for the work.

It is unclear about whether this is in refernce to vehicular gates or hydro gates. In each case, the Contractor is responsible for contructing the gates to the final specification and verifying the condition of the gates prior to construction.

All three Hatch, Canutillo , Mesilla

12/10/09 Skanska USA Civil West RMD

In lieu of the above information, we believe it would be better if this work be handled as an allowance. Please let us know if this is something the Government would consider. IBWC is responsible for this decision