Final_Industry_Day_Questions_and_Answers.docx

DOCX document 63 KB Posted

Attached to
HC-130 PSI
Solicitation number
HSCG38-12-I-H00007
Issued by

View the file

Other files

File Type Posted
Attachment_5_USCG_HC-130H_Schedule_of_Supplies_Services_Feb_2012_(formula_corrections_for_totals).xlsx XLSX spreadsheet
Solicitation_Amendment_0002_Feb_2013.doc DOC document
Solicitation_Amendment_0001_Jan_2013.doc DOC document
Attachment_8_-_USCG_Supplied_Ground_Support_Equipment__(Revised_Dec_2012).xlsx XLSX spreadsheet
Attachment_5_USCG_HC-130H_Schedule_of_Supplies_Services_Dec_2012.xlsx XLSX spreadsheet
Attachment_4_-__USCG_HC-130H_and_HC-130J_Reference_List_-_Updated_04_Dec_2012.xlsx XLSX spreadsheet
Attachment_6_USCG_HC-130J_Schedule_of_Supplies_Services_Dec_2012.xlsx XLSX spreadsheet
Non_Disclosure_Agreement_with_Instruc.pdf PDF
Presolicitation_Notice_LRS_PSI.doc DOC document
Presolicitation_Notice_LRS_PSI.doc DOC document
DOD_Distribution_Statements.docx DOCX document
Industry_Day_Attendees.doc DOC document
Distribution_Statements_-_US_Government_(2).docx DOCX document
Attachment_3_-_Government_Supplied_Aviation_Material.xlsx XLSX spreadsheet
Notice_for_Industry_Day.doc DOC document
DRAFT_LRS_PSI_Solicitation.doc DOC document
Attachment_11_DD-254_Security_Classification.pdf PDF
Attachment_10_Government_Furnished_Property_Report.doc DOC document
Industry_Day_Registration_Form.doc DOC document
Attachment_4_-__USCG_HC-130H_and_HC-130J_Reference_List_SK_9-25-12.xlsx XLSX spreadsheet
Attachment_9_-_USCG_HC-130J_Rolls_Royce_PBH_Parts.xlsx XLSX spreadsheet
Attachment_8_-_USCG_Supplied_Ground_Support_Equipment__(Revised_16_Aug_12).xlsx XLSX spreadsheet
LRS_PSI_Past_Performance_Questionnaire.doc DOC document
Attachment_7_-_USCG_Aircraft_List_(10-1-12).xlsx XLSX spreadsheet
Attachment_1_-_USCG_HC-130H_PSI_Basic_Specification.xlsx XLSX spreadsheet
Attachment_6_USCG_HC-130J_Schedule_of_Supplies_Services_-_10-12-12.xlsx XLSX spreadsheet
Attachment_3_-_Government_Supplied_Aviation_Material.xlsx XLSX spreadsheet
Attachment_12_-_A1U_TCTO.pdf PDF
DRAFT_LRS_PSI_Solicitation.doc DOC document
Attachment_2_-_USCG_HC-130J_PSI_Basic_Specification.xlsx XLSX spreadsheet
Attachment_5_USCG_HC-130H_Schedule_of_Supplies_Services_-_10-12-12.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DOCUMENT

SECTION / PARAGRAPH / PAGE NUMBER

QUOTE

QUESTION

ANSWER

Attachment 4

Could you please provide the distribution statements for Attachment 4. Currently it only lists alphabets without defining the distribution for that letter.
See attached.

Process Guide CGTO PG-85-00-290A and DOD Instruction 5230.24

LRS PSI Solicitation

In the LRS_PSI_ Solicitation it states that there shall be a contractor Non Disclosure Agreement (NDA) WITH Lockheed but I can’t find the name of the person we should contact to establish the NDA. Do you have that information?

Brittany R. Perry Contracts Negotiator, C-130 Contracts Lockheed Martin Aeronautics Company Work: 770/494-3106 Fax: 817/762-9642

SOW

Section 2.2.2/pg 9 Non Recurrent Repairs
The RFP states: “Pending receipt of disposition instructions, BER items/part/components shall be stored at the contractors facility separated from “Ready for Issue (RFI)” items.”
Would the Government consider adding a response time regarding storage in this section? Concern: Items stored for long periods of time tend to accumulate and impact supply chain repair cycles and return to Ready For Use status.
Disposition instructions will be given to contractor within 90 days of BER determination.
SOW
Section 2.4/pg 11 Parts Support
The RFP states: “However the contractor shall utilize ALC Instructions 13020.10A Local Manufacture of Parts by ALC…”
Will ALC provide the support specified in those instructions including but not limited to producing drawings, machining, and other requirements? Concern: ALC instructions may be changed due to engineering requirements or tolerances. Clarifying who will provide the information to the contractor upon effective date for implementation would add clarity.
ALC will provide drawing support but machining and other requirements are the responsibility of the contractor. Machining and other requirements can be completed by USCG personnel if deemed to be in best interest of USCG. Contractor will be notified by COR when ALC instructions have changed. MPCs, drawings, tech orders, etc. should be checked for currency by contractor prior to use. If drawing is greater than 30 days old the contractor should ask for new drawing.
SOW
Section 2.6/pg 12 Aircraft Sheet Metal Shop Support
The RFP states: “HC-130J enhanced cargo handling system inspections and repairs.”
Will the ALC provide (J) model maintenance and parts break down instructions?

Will the manuals for this equipment be provided and will the USCG have an agreement with the USAF for TMAPS access?

J model manuals are available on TMAPs. Pubs access is discussed in the RFP.

Access to proprietary data is between Lockheed Martin and the contractor.

SOW
Sections 3.1/pg 15 Key Personnel and HSAR 3052.215-70/pg 66 Key Personnel or Facilities (Dec 2003)
The RFP states: “The contractor shall provide personnel with adequate skills to perform the requirements of this SOW and ALC required on-site support efforts. Key personnel shall meet or exceed the requirements specified below.”
This section lists certain Key Personnel, for which resumes are to be provided.

Would the Government accept additional Key Personnel and their resumes to be included, which the Contractor deems essential to the successful performance of the contract?

No, please submit the required resumes.

SOW
Section 5.5.8/pg 30 Special Requirements
The RFP states: “The contractor shall enter weight and balance information in the automated weight and balance system in accordance with AWBS program guide?
Will the contractor have access to the USCG AWBS system?

Concern: Switching from contractor databases to USCG and others can lead to configuration control issues. Clarity here would be greatly appreciated.

Yes. Weight and Balance information needs to be entered and delivered in USCG AWBS format. Process Guide provided as a reference.

SOW
Section 6.0/pg 31 Reporting requirements
The RFP states: “If the PSI card has an associated ACMS cover sheet, the ACMS cover sheet shall be provided to the COR.”
Many of the routine cards have ACMS cards as a reference. Is it the USCG’s intent that every reference card cover sheet be provided to the COR?

Concern: This will create a backlog of reviews for the COR and possible delays in flow. Would the USCG consider a onetime approval and recurring approvals on “changed or updated cover sheets?”

If ACMS card is a task, then cover sheets shall be provided to COR. If ACMS card is a reference to the PSI card, then it does not need to be provided.

Back-log should not be a concern.

SOW
Section 7.0/pg 35 Government Furnished Material
The RFP states: “The contractor shall be responsible for calibration and depot maintenance of all equipment listed in attachment 8.”
Can you confirm that the contractor will have the financial responsibility for scheduling, calibration, and depot maintenance of GFM? And clarify how the decision will be made on Beyond Economical Repair issues?

Concern: Test equipment repairs generally require long periods of “out of service” time. If possible, will additional gear be available from the USCG on case-by-case basis?

Yes, in accordance with the Government Furnished Property clause the contractor shall properly maintain Government property. The contractor’s maintenance program shall enable the identification, disclosure, and performance of normal and routine preventative maintenance and repair.

BER will be determined on case by case basis between the contractor and USCG No additional equipment will be provided unless deemed to be in the best interest of USCG. The contractor should plan for long lead times for calibration/repairs. Calibrations and repairs should be in accordance with the applicable manuals.

SOW
Section 11.2/pg 41 Shipping Response Times
The RFP states: “Any component listed on Attachment (3) that requires repair or replacement shall be shipped by the contractor no later than 48 hours after discovery of need for replacement.”
Will specialty items be coded to allow the contractor flexibility to retain the end item until the “planned” milestone is completed?

Can this be 48 hours after receipt of replacement part?

Concern: Components have different configurations with regard to fittings and other items that must be removed from the old component to the new component. The new component should be fully installed and “form, fit, and function” inspected.

Shipment of non RFI component back to ALC later than 48 hours after discovery of need for replacement shall be approved on a case by case basis with the COR.

SOW
Section FAR 52.252-1/pg 88 Solicitation Provisions: Proposal Submission
The RFP states: “Proposals shall not exceed 75 pages (double sided for a total of 150 pages) on 8 ½ x 11 paper using Times New Roman 12 point font, margins are at the discretion of the offeror, this applies to the non price factors (listed below) located in Clause FAR 52.212-2 Evaluation-Commercial Items (JAN 1999).”
May a foldout page of 11x17 size be used for graphics, where such a graphic will more effectively communicate information to the evaluator?

If printed on one side of the page, would such an 11x17 foldout be counted as two (2) pages, for page limitation purposes?

For graphics 11 x 17 is acceptable and will be counted as one page if only one side of the sheet is used.

SOW
Section FAR 52.252-1/pg 88 Solicitation Provisions: Proposal Submission
The RFP states: “Proposals shall not exceed 75 pages (double sided for a total of 150 pages) on 8 ½ x 11 paper using Times New Roman 12 point font, margins are at the discretion of the offeror, this applies to the non price factors (listed below) located in Clause FAR 52.212-2 Evaluation-Commercial Items (JAN 1999).”
For tables, artwork and other graphics the 12 point TNR font will make the graphic difficult to fit on a page, and in most cases will not fit well with the non-text portions of the graphic. May a smaller font be used for text contained within tables and graphics, such as Arial Narrow 9 point font?
This is acceptable as long as the document is legible.
SOW
Section FAR 52.252-1/pg 88 Solicitation Provisions: Proposal Submission
The RFP states: “The apparent successful offeror shall submit a Subcontracting Plan and DHS Form 700-23 (4/11) or waiver request prior to award which will be evaluated and incorporated into the resultant contract.”
Would the Government prefer that the Subcontracting Plan and DHS Form 700-23 be included as an Attachment to Factor IV Price, and not subject to page limitations?

OR would it be preferable to include the Subcontracting Plan as an Attachment to Factor I Technical Capability, and if included there the Plan would not be subject to the page limitations?

Is this Subcontracting Plan excluded from the page count limitations? Please clarify.

Subcontracting Plans are not to be submitted with the proposal. The proposed awardee (apparent successful offeror) will be required to submit a plan prior to contract award

SOW
Section FAR 52.252-1/pg 88 Solicitation Provisions: Proposal Submission
The RFP states: “The contractor shall submit a completed SF1449 Solicitation/Contract/Order For Commercial Items, pricing, all required evaluation submittals, and completed FAR 52.212-3 Offeror Representations and Certifications – Commercial Items (APR 2011), Alt I (APR 2011) or certify that ORCA has been completed. Review the solicitation carefully as there are required fill-ins throughout the solicitation document.”
Are the required contractual terms and conditions, SF1449 and other required forms, representations, and certifications, and required fill-ins to be contained in Factor IV Price?
Factor IV is price and consists of the base and option year pricing.

Read FAR 52.212-2, Price in the RFP.

SOW
Sections SF-33 Notes, PWS 1.1/FAR Clause 52.216-19 Order Limitations/Statement of Work Paragraph 1.1
Under the notes to the SF33, the RFP States “The USCG shall order a minimum of $10,000,000 of the estimated quantities designated in the Schedule of Supplies/Services.” In addition, under Paragraph 1.1 of the Statement of Work (SOW), the RFP states, “The minimum guaranteed amount for the IDIQ contract will be $10,000,000.” However, under FAR 52.216-19 Order Limitations (Oct 1995), paragraph a) minimum order states, “When the Government requires supplies or services covered by this contract in an amount of less than $69.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.”
Based on the statements in the SF33 and the Statement of Work Paragraph 1.1, shouldn’t the provisions of FAR Clause 52.216-19, Order Limitations be modified to the minimum order value of $10,000,000.
There is no SF33 associated with this requirement.

There is a $8,000,000 guarantee at time of award. Far clause 52.216-19 is for individual task orders issued under the contract after the $8,000,000.

SOW
Attachment 5 – USCG HC-130H Schedule of Supplies/Services

Attachment 6 – USCG HC-130J Schedule of Supplies/Services

Attachment 5 and Attachment 6 to the Request for Proposal include the schedule of Supply/Services for the HC-130H and HC-130J, respectively. Within each attachment includes separate pages for each program year that includes CLINS numbered from H-CG-001 through H-CG-0359 and J-CG-001 through J-CG-0359. However, each program year contains the same CLIN Numbers.
Is the USCG’s intent to have the same exact CLIN Numbers for each year?

Concern: Having the same CLIN throughout the life of the contract sometimes causes issues with cost accounting and auditing / management of funding.

Would the USCG consider changing CLINs to reflect the following: H-CG-X001 through H-CG-X0359, and J-CG-X001 through J-CG-X0359, where X represents the year of the program, i.e. 1, 2, etc?

The Schedule of Supplies/Services will be revised to reflect 0 for the base year, 1 for Option Year 1, 2 for Option Year 2, 3 for Option Year 3 and 4 for Option Year 4.

SOW
Sections 2.2.2/pg 7 Non Recurrent Repairs

Section 4.3.2/pg 21 Government Furnished Material (GFM)

Section 4.3.3/pg 21 Component Replacement / Repair Capability

The RFP states: “in no case shall a request for GFM be submitted less than fourteen calendar days prior to the required date of delivery.”
Does this apply to the FCF and delivery phase?

Concern: A USCG component that fails during preflight/engine runs for the FCF will have to wait 14 days. If this is true, will the day-for-day delay be approved and schedule adjusted?

Yes Exceptions to this rule will be handled on a case by case basis by the COR.

General
N/A
N/A
Will the Government consider proposals on subsets of the total scope of the RFP or will only proposals covering the total scope be considered?

Total scope only.

SOW
Section 1.1/para 1
The PSI is the depot level inspection of the HC-130 series aircraft to ensure airworthiness through detailed non-destructive inspection procedures. Additionally, these inspections ensure compliance with Aircraft Structural Integrity Program (ASIP) requirements.

Who provides definition of tasks to meet MIL-STD-1530C (ASIP) requirements?

Is there a Force Structural Maintenance Plan available?

What is the reporting mechanism for the Individual Aircraft Tracking Program?

These would include defining the specific ASIP inspections for that input cycle, collecting the results, and tracking crack growth in an Individual Aircraft Tracking System.

USCG personnel provide ASIP requirements. All ASIPs will be issued on the CG-103.

Yes there is a Force Structural Maintenance Plan.

ACMS is the reporting mechanism.

ASIP inspections are on the FFP Depot Level Repair List. Discrepancies found during inspections shall be entered on applicable ACMS Card and submitted to COR.

SOW
Section 1.1/para 1
The PSI is required to be completed every 48 months...
Is this 48 month interval calculated as input-to-input, or delivery-to-input?

Delivery to input.

SOW
Section 1.1/para 1
The maximum number of PSI aircraft expected to be at an overhaul facility at one time are three HC-130H’s and one HC-130J in PSI with one HC-130H or HC-130J in the rapid modification production line

What is the likelihood that a single aircraft will undergo both PSI and RMPL processes in a single depot visit?

Is there a provision for schedule relief in that case?

This is likely to occur and schedule relief will occur on case by case basis.

If the RMPL work is outside the scope of PSI, additional days will be allotted to contractor.

General
Section 1.1/para 2
The Government intends to utilize a competitive, single award, IDIQ….
Would the government consider multiple awards or would any potential subcontracts fall under the Prime Contractor of a single-award contract?
One single IDIQ contract will be awarded.

Any subcontracts will be between the prime and the subcontractor. All work associated with this requirement is to be performed at one location with the exception of painting.

SOW
Section 1.1/para
In order to help ensure timely delivery of Contractor Furnished Material (CFM) Parts, the ALC intends to fund a task order for each aircraft in PSI and have the on-site COR approve the contractor acquisition of CFM parts from Aviation Maintenance Management Information System (AMMIS) approved sources of supply and/or manufactures list.
Is this process already established and in place (ALC “intends” to fund…)?

Will access to AMMIS be available during bid phase?

A Clin for parts will be funded under the task order.

Access to AMMIS will not be available during the proposal process.

SOW
Section 1.1/para 6
The contractor may request additional days if delays are Government caused.
Who makes the determination that a given delay was Government caused"? What is considered a Government caused delay?"
If delay is caused by Government inaction. This would be a mutual decision between the contractor and the COR.

If there is a disagreement the issue would be handled through the disputes clause.

SOW
Section 1.1/para 7
The contractor may be required to have up to four aircraft in PSI work at any given time.
Is there a guaranteed minimum number of aircraft in PSI?
No. $10M guaranteed, this could be RMPL, TCTO, Paint, etc.
SOW
Section 1.1/para7
The contractor shall execute a program to complete each PSI aircraft within 220 calendar days after induction for de-paint. Flow days start accruing on the date of aircraft arrival for de-paint (Milestone 2) and end upon completion of Milestone 12.
Please clarify the total flow time. Induction for de-paint normally occurs after the completion of induction testing. Is the intent that the 220 calendar days include induction testing prior to induction for depaint?
220 days is from arrival at contractor facility until acceptance by USCG personnel. (Milestone 2 – 12). PII happens at USCG operational unit and this is not included in 220 day requirement.
SOW
Section 2.1/para 1
The Government will then make a determination on each discrepancy and authorize the work effort for the repair phase to correct discrepancies noted and approved.
In what time frame will the Government make these determinations?
In the most reasonable amount of time possible but no greater than 7 working days.
SOW
Section 2.2.1/para 1
These repairs are defined as the FFP repairs noted on the CLIN sheet.
Are these pre-approved/pre-developed standard repairs?
Yes
SOW
Section 2.2.2/para 5
In no case shall a request for GFM be submitted less than fourteen (14) calendar days prior to the required date of delivery. In no case shall an acceptable required date of delivery be less than fourteen (14) calendar days in the future from the request of any/all GFM.
Is there a contingency plan to include schedule relief for emergency" GFM replacement materials?"
This will happen on a case by case basis approved by COR.
SOW
Section 2.4/para 4
Additionally, the LRS PL at the ALC will work with the contractor’s supply department to ensure all ALC SICR processes are followed for acquiring CFM components.
Please identify the ALC SICR processes required to be followed when acquiring CFM components.
The SICR Instruction is on the DVD.
SOW
Section 2.4/para 6
All parts made at the contractor’s facility must be approved by LRS Engineering and subsequently enrolled into AMMIS, via the ALC SICR process and have applicable drawings created and part numbers assigned.
What is the level of detail contained in all parts"?

Does this include minor clips, angles, repair doublers, freeze plugs, etc?

This is subject to any parts that have a designated part number in IPB or a part number on a drawing.

SOW
Section 2.4/various
“PL Engineering”, “LRS PL Engineering”, “LRS Engineering”.
Please clarify these entities.
These all have the same meaning. Product Line, Long Range Surveillance Product Line.
SOW
Section 2.6
The contractor shall have the capability to make repairs and complete overhauls to the flight controls and aircraft skin for both PSI aircraft and components returned from the operational fleet.
Is tooling provided, or engineering drawings available for flight control overhaul tooling (balance jigs, assembly jigs, et c.)?
All tooling provided is on the government supplied equipment list.
SOW
Section 3.1/All
The contractor shall provide personnel with adequate skills to perform the requirements of this SOW and ALC required on-site support efforts
How firm is the requirement for all key personnel to have HC-130 experience?
As described in the RFP. RFP states HC-130 aircraft or similar type.
SOW
Section 3.1.4/para 1
The contractor shall maintain design responsibilities for non-standard repairs with final approval resting with the Government.
Please clarify “design responsibilities”.

What is the approval process for engineering dispositions of non-standard/non-recurring repairs?

Will on-site personnel provide final engineering approval or does approval come from ALC LRS PL Engineering from office?

Is there a guaranteed maximum suspense for approval responses from Engineering authority?

Is there opportunity to gain some sort of Limited Engineering Authority, whereby contractor engineers can provide disposition with after-the-fact oversight by ALC?

Non-standard repairs is handled iaw RFE process. Non-recurring repairs are handled iaw section 2.2.2 of SOW Final approval comes from either on-site LRS PL Engineering Rep or from LRS PL Engineering Rep at USCG ALC.

No, there is not a guaranteed max suspense.

No, there is not an opportunity to gain Limited Engineering Authority. LRS PL Engineering will approve all non standard repairs per RFE process.

SOW
Section 4.1/para 1
CLINS H-CG-0001 and J-CG-0001 (and the corresponding option period CLINS) are defined as FFP, and shall include all work listed in the PSI task list included in Attachment 1 and 2.
Will inspection work cards be provided for review during proposal phase?
YES. See reference DVDs.
SOW
Section 4.2.1/para 1
The contractor shall send a field team (accompanied by a qualified USCG maintenance person) to complete pre-inspection of inbound aircraft at operational USCG Air Stations for PSI approximately 180 days in advance to coordinate & facilitate ordering of specialized parts for the PSI and to complete a thorough inspection of the aircraft. The contractor shall use a USCG supplied checklist for evaluating the condition of the in-bound aircraft and recommend changes to ensure critical parts are ordered and waiting for the aircraft upon arrival for the PSI.
How much time is allowed to conduct this inspection?

How much disassembly will be allowed? Will the inspection checklist be available for review during bid phase?

Is it the intent of the USCG that this inspection precludes a full inspection upon arrival at the contractor's facility?

72 hours to conduct inspection subject to operational unit availability.

See checklist for disassembly requirements. Yes – in TMAPs and will be provided on DVD.

No, the PII is only to allow contractor to order long lead time parts found to be in need of replacement. Full inspection will be required for all aircraft in PSI.

SOW
Section 4.2.12/para 2
Once the painting is completed, the contractor shall do an aircraft weighing evolution (in accordance with appropriate PSI specification documentation) and also complete all applicable weight and balance paperwork.
Does the Aircraft Weight & Balance System contain all current weight & balance data?
Yes
SOW
Section 2.9/para 1
In the event that center wing box inspection services are required, the ALC will notify the contractor to ascertain the contractor’s capability to accept and perform additional work.
What are the determining criteria for CWB replacement?

Is there an Equivalent Flight Hour (EFH) bogie, or is it a combination of EFH and inspection results?

Will the determination be made before PSI input or is it the result of inspections after input? Is there an existing engineering package for CWB replacement?

Is it available from USCG?

USCG criteria. This RFP only calls for CWB inspections not replacements.

Determination of CWB inspections will be made prior to inductions. CWB replacement is not a part of this RFP.

CWB Inspection TCTO is on DVD.

SOW
Section 4.3.3/para 3
Delivery is considered complete when any GFM is received at the contractor’s facility.
Please clarify that received" is not physically received, but includes inspection of the GFM for defects prior to official receival.
Received is received at contractor’s facility. Signature on delivery form from FEDEX, etc.
SOW
Section 4.8/para 1
The contractor shall immediately notify the COR and Ground Flight Representative (GFR) after any accident/incident (including fire) resulting in any disabling injury, fatality, or damage to Government property exceeding $10,000.
Will the GFR be located at the contractor facility?
No the GFR will be located at ALC.
SOW
Section 5.2/para 1
Aircraft received for PSI having skin patches or other repairs installed by the field level shall be evaluated for suitability for continued operational service. Repairs that are determined not to affect the aircraft's airworthiness and will remain serviceable for the next 48 to 60 months shall not be replaced. Temporary repairs shall not be reworked to permanent repairs unless safety of flight is affected.
What is the basis for suitability evaluation? Who makes the determination (ALC Engineering, QA, contractor engineering)?

Is there a definition of Safety of Flight" structure and systems?

LRS Engineering thru COR with input from contractor.

Safety of Flight has been eliminated. SOW now states in Section 5.2, “Temporary repairs shall not be reworked to permanent repairs without approval from COR.”

SOW
Section 5.2/para 2
Corrosion removal exceeding material removal limits in accordance with TOs 1C-130A-23 and 1C-130J-23 requires disposition by USCG certified structural engineer and concurrence of the Coast Guard ALC LRS Engineering.
Please clarify exceeding material removal limits". Does this imply that any corrosion removal beyond TO limits requires prior approval?

Is the "USCG certified structural engineer" an onsite USCG engineer, or a USCG-certified contractor engineer?

Yes.

Intent is to have an onsite USCG engineer or direct representative.

SOW
Section 5.3/para 1
All radio, radar, communication/navigation systems shall be made operational if installed and operational upon arrival. When components of radio, radar, communication/navigation systems are missing upon arrival of the aircraft, slave sets shall be used to ensure that the systems are serviceable. Slave sets shall be removed prior to aircraft departure. Items found to be inoperative or uninstalled at delivery shall be documented and may be carried forward (NBNC) or corrected at the Coast Guard’s discretion. Repair of equipment documented as unserviceable (if approved by the COR) will be considered as a non recurrent repair.
Will the slave sets" be provided as GFE?

There appears to be no recognition that the contractor will by necessity be required to perform a full inspection of each aircraft at the time it arrives at their facility, including functional system checks.

The state of the aircraft will likely have changed significantly during the 180 days between the pre-inspection and induction at the facility.

We respectively request that the Government recognize this in the Statement of Work and address the processes for variances between the state of the aircraft at the pre-inspection and the state of the aircraft upon arrival at the contractor's facility.

Yes, when needed.

There is a PSI procedure card for receipt/acceptance of aircraft. If a component is installed and operational on arrival at contractor facility, it should be installed and operational upon delivery to USCG.

Pre inspections are for the benefit of ordering long lead time parts and ensuring contractor knows health of aircraft.

The contractor should realize that upon completion of the PII, the aircraft will continue to fly in an operational environment and continue to corrode and develop fatigue. The purpose of the PII is to order the long lead time parts and let the contractor gauge the status of the aircraft. Upon arrival at PSI facility, contractor shall follow Milestones and maintenance cards to handle other discrepancies. See SOW for guidance.

SOW
Section 5.5.7/para 1
Correct all discrepancies found in accordance with NAVAIR 01-1A-505-1.
Is this considered a core effort, or O&A?
Handled on a T&M basis as a Non Recurrent Repair.
SOW
Section 5.6/para 1
The USCG will provide Government certified NDI inspectors to perform inspections and/or evaluate performance and techniques of contractor supplied inspectors.
Are there any specialty probes, probe adapters, transducers, or other NDI equipment required to perform any of the program inspections?

Will Inspection Standards be provided, or engineering drawings to fab the standards?

USCG supplying inspectors and equipment.

The USCG will be supplying the Inspectors

SOW
Section 6/para J
The contractor is solely responsible for the integrity of any structural part(s) installed on the aircraft.
Does this include Government Furnished Material? Is there a time limitation/warranty or indemnity clause associated with this requirement?
See warranty clause of RFP. GFM is responsibility of the Government.
SOW
Terms and Conditions/ Payments, Materials C (2)
Give credit to the Government for cash and trade discounts, rebates, scrap, commissions, and other amounts that are identifiable to the contract.
Not all scrap in fabrication can be attributed to a single contract. Is it the Governments intent that process be altered such that all scrap can be attributed and accounted for for this contract?
If possible, credit USCG as available. Do not put any special procedures in place that will cause extra costs to Government.
SOW
General

Section 1.0 refers to an onsite COR for CFM. Section 5.0 says ALC Product Line personnel will maintain on-site technical expertise at the contractor’s facility". The PSI, depot level repairs and all other aspects of this SOW performed by the contractor will have significant daily oversight from the LRS PL QA Inspectors. Paragraph 5.2 says "Corrosion removal exceeding material removal limits in accordance with TOs 1C-130A-23 and1C-130J-23 requires disposition by USCG certified structural engineer and concurrence of the Coast Guard ALC LRS Engineering".

Who will have signature authority for routine Over and Above efforts and Discrepancy Reports?

COR will have signature authority with input from onsite QA inspectors.

General

What data rights does the Coast Guard have for C-130J Aircraft and Maintenance data?
Government use rights.

General

Will the Coast Guard consider a bid based on a prime and subcontractor team performing work at dual sites?
No (except for de-paint/paint)
SOW
Section 4.3.1/FFP Depot Level Repair
Are the listed items to be priced as stand-alone tasks or in conjunction with PSI activities?
Stand alone FFP items.
SOW
Section 4.3.1/FFP Depot Level Repair
Are activities that are duplicated by mandatory PSI tasks or other FFP Depot Level Repair tasks to be priced within each listed task item?
Each FFP Depot Level Repair task shall be stand alone repair tasks.
SOW
Section 4.3.1/FFP Depot Level Repair
Are all materials (except those listed in Attachment 3) that may be required for any specific FFP Depot Level Repair to be included in the price?
Yes. FFP items include everything required to complete FFP item.
SOW
Section 4.2.8/Milestone 8, Reassembly
Would consideration for partial application of the lower wing finishing system be appropriate for those areas covered by the external fuel tank pylons & the aft nacelle fairings for those vendors that want to maintain work dock continuity and their EPA Title 5 paint facility certification?
No, see RFP 5.4.3.2.
SOW
Contractor Flight Crews
Will the FFP Depot Level Repair line item be used to provide price for support of the PSI or be part of the PSI Basic FFP?
No. USCG flight crews will complete all ferry flights to/from PSI facility and to/from de-paint/paint facility.
SOW
Contractor Flight Crews
Will travel for contractor flight crews be included in the FFP or as a reimbursable cost?
No. USCG flight crews will complete all ferry flights to/from PSI facility and to/from de-paint/paint facility.

Attachments 1, 2, 5 and 6

Will the gov’t release the current work documents for the PSI and the ASIP’s into a bidder’s library?
No. It will be provided on a DVD.

A1U Mod CLIN

Is this activity to be priced as stand-alone or in conjunction with PSI?
Stand-alone.

A1U Mod CLIN

Is the contractor responsible for full kit provisioning?
No. USCG will provide kit.

A1U Mod CLIN

Will the developer of the installation be allowed to participate in this solicitation?
Yes.
SOW
Section 5.3
Are the Slave Sets GFE?
All GFE is listed as Attachment 3. When deemed necessary by the Government slave sets will be provided as GFE.
SOW
Section 3.0
In reference to the second paragraph, first sentence. Is this sentence referring to the NDA between the offeror and the Original Equipment Manufacturer?
Yes.
SOW
Section 4.2.1
The pre-inspection shall be accomplished approximately 180 days before induction. However, paragraph 4.5 requires the first induction 120 days after contract award. This may not allow enough time to accomplish the pre-inspection task prior to first induction.
First pre-inspection will be completed as soon as possible prior to induction. Any parts that cause delays due to reduction in time will be handled on a case by case basis with COR.
SOW
Section 8.2
This paragraph states that, “the contractors repair facility shall be capable of performing all aircraft and engine workload.” The paragraph continues that, “only de-painting and painting activities may be performed by a qualified facility.” The RFP specifically allows these tasks to be subcontracted yet no other RFP tasks can be contracted. This is a requirement to benefit DRS. DRS does not have de-paint/paint capabilities.
All work except for de-paint/paint must be completed at contractor’s PSI facility.
SOW
Section 5.6

Why does the USCG provide certified NDI inspectors to perform inspections?

This is not a typical requirement for depot repair?

This gives USCG QA check that we desire to have.

SOW
Section 4.1

This paragraph states that the FFP shall include all work listed in the PSI task list?

Paragraph 4.2.5 states milestone 5 inspection cards shall be completed. Then paragraph 5.6 states the USCG will, “perform inspections.”

What specific NDI tasks in the PSI task list are accomplished by the USCG?

All NDI requiring specific NDI equipment and specifically qualified NDI personnel will be completed by USCG personnel. For example, visual inspections can be completed by contractor but an eddy current will be completed by USCG personnel.

SOW
Section 5.6
What are the specific certifications of the USCG NDI inspectors?
USCG certifies our inspectors to USCG National standards (NAS 410).
SOW
Section 8.2

This paragraph requires space for 28 USCG support personnel and specifically states, (non-touch). Are the USCG NDI personnel part of the 28?

How many USCG personnel are assigned to accomplish NDI inspections?

NDI inspectors will not be included in 28 personnel and will come to facility on an as needed basis.

SOW
Section 8.2

Similarly sized programs required one or two on-site Government support personnel.

Please provide a description of tasks/ responsibilities for the 28 USCG personnel for a 7 aircraft per year operation.

QA and other tasks deemed necessary by USCG. Surveillance is key to USCG program success.

FAR 52.217-5

The contractor shall complete a Non-disclosure Agreement. Is this NDA with the USCG or Original Equipment Manufacturer?
There will be a NDA between the company and the USCG for access to DVD.

There will be a NDA between the awardee and the OEM for access to HC-130J information.

FAR 52.212-2

Is the relocation cost of the 28 government personnel from Elizabeth City to a new PSI site a factor of the evaluation?
No

FAR 52.212-2

Is the relocation cost of PSI, Engine, and Propeller GFE/CFE from Elizabeth City to a new site a factor of the evaluation?
No
SOW
Pg 5
Since there are no current CONUS C-130 experienced MROs that have T-56 engine and propeller shop capability to meet the requirements as stated in the SOW, How does the USCG consider this a competitive solicitation when engines and props could be shipped and repaired off-site perhaps at a lower cost to the government?
There are qualified T-56 engine and propeller shops with the capability to meet this requirement.

The USCG requires on-site QA of engine and propeller work.

SOW
Pg 6
If a contractor does not have a paint & strip facility does this mean that the depainting and painting is not part of the evaluated PSI price or is this for a drop in aircraft off the PSI cycle of 48 months?
De-paint and paint is included in PSI cost. There is a separate FFP CLIN for de-paint and paint in the event there is a need for drop-in work.
SOW
Pg 7
Is the facility required to have a FAR Part 145 Repair Station certificate?
No

Pg 7

What are the Quality requirements? Is AS9100C inclusive of 9110 3rd party certified a requirement?
The contractor shall be Ground and Flight Risk (GFR) compliant and ISO 9000 certified. See SOW 8.2.
If the contractor does not have an on-site de-paint/paint facility, does the contractor have to verify in the proposal a subcontract with the de-paint/paint facility it intends to use in the performance of the contract?
See FAR 52.212-2 – Evaluation which requires in-depth information be submitted on depaint/paint facility.

Pg 7

Will the government reimburse the contractor for the ferry flight crews travel to and from the de-paint/paint facility or should this cost be part of the proposed PSI proposal price?

Do the Ferry crews have to meet Coast Guard flight service requirements or are other service requirements acceptable i.e. Air Force or Navy?

Ferry crews will be USCG personnel.

Pg 7

If the contractor does not have an on-site de-paint/paint facility thus causing 3 additional flights, along with the cost of the ferry crews, should the cost of the additional fuel for the 3 additional flights also be included in the price of the PSI or is the government going to assume that additional cost?
Ferry crews will be USCG personnel.

Pg 7

For depaint and paint aircraft being done off site from PSI, do we include the shipping cost back to the depaint/paint facility after the ferry flight back to the PSI facility?

Should this cost be included in the CLIN depaint H-CG-203 and should the painting of the flight controls be included in paint CLIN H-CG-204 and should those CLINs include shipping costs?

All flight control painting costs should be included in FFP for PSI. If you need to ship components, then all costs should be included in FFP.

Pg 10

Is the engineering support personnel only for standard repairs of a UDLM or if you need a DER for a non-standard repair is the DER engineer separately priced?
Engineering Support is needed for development of standard and non standard repairs. Due to USCG aircraft not being controlled by FAA airworthiness but certified as airworthy by USCG personnel, DER services are not needed.

Pg 10

Does this statement mean that the FFP CLIN pricing for repairs should include the material to make the repairs or do you want the price to replace the component?

If not, how do you know what the material cost and/or the cost to repair the component will be, until you see the extent of the repair?

Yes. FFP CLINs shall include all costs with the applicable task. Contractor’s experience should help estimate material costs. Any contractor proposed replacement of parts needs LRS Engineering approval. Any items in Attachment 3 are not included in FFP CLIN pricing.

Pg 12

What elements make up a climate controlled facility or is it IAW the TO on the T-56? Please define
Climate control is defined as completely enclosed from weather elements and capable of controlling temperature and humidity.

Pg 12

Who repairs the modules?
The USCG sends out for repair.

Pg 12

Are RFI modules provided GFP?
Yes, see attachment 3.

Section 2.8/Pg 13

It is not mentioned in this paragraph, but, since the engine is being torn down, should the assumption be that the engine has to be tested?

If so, is it correct to assume that a test cell would be required?

How is this being done currently?

Will the Coast Guard allow use of their test cell?

If so, is there a cost involved?

Yes, on the wing.

No test cell required, tested on aircraft.

Tested on aircraft.

Not applicable.

Section 2.8/Pg 13

If you do not have to have a de-paint/paint facility on site, what is the purpose behind having to have a T-56 engine shop on site when this capability can be subcontracted?

Why is the CG requiring the engine to be torn down?

Since this is a FAR Part 12 contract why can’t the engine be shipped off site for repair?

USCG wants oversight of all PSI tasks and T-56 maintenance procedures.

And to ensure flight readiness. Not every engine will be torn down. This will be done as needed.

For USCG ACMS requirements.

Using FAR Part 12 for Commercial Items does not have anything to do with whether the Coast Guard allows off site subcontractors or requires all work to be completed in one facility.

Section 2.8/Pg 13

What elements make up a climate controlled facility on the AE2100D3 or is it IAW the TO? Please define.
Climate control is defined as completely enclosed from weather elements and capable of controlling temperature and humidity.

Section 2.8/Pg 13

Is the USCG providing the Tech Orders etc. on the AE2100D3?
Yes. See TMAPS and Rolls Royce FSR/OEM

The USCG will not expect these engines to be disassembled by the contractor. Rolls Royce may visit your facility to do this.

S ection 2.11/Pg 14

This paragraph 2.11 conflicts with the statement in paragraph 2.10 that the first 2 aircraft installations will be on a T&M basis.
The first A1U installation will be on T&M basis if ordered to validate current TCTO and develop FFP. Other items completed on RMPL will need one aircraft to develop TCTO and 2nd to validate prior to FFP establishment.

Section 3.0/Pg 14

As part of the proposal submittal, will the USCG require substantiation documentation of a partnering agreement with the OEM or an OEM service center designation letter?
The proposed awardee will need to submit documentation to show they have access to the data through the OEM.

It is not required at the time of proposal submission.

Section 3.0/Pg 15

Lockheed Martin has been approached about establishing an NDA/PIA in order to view and utilize the proprietary C-130J tech data, drawings and publications. Contractors have been told by LM that it is their policy not to establish a NDA/PIA for the C-130J model data.

How is the government going to address this issue prior to final RFP?

If the Coast Guard does not provide the tech data will this be a sole source award to LM?

LM has stated this will be handled on a case by case basis. Contractor should work with LM to obtain this required document. USCG has no control over LM proprietary data.

USCG anticipates several contractors gaining a NDA/PIA with LM.

This is not a sole source award.

Section 3.1.3/Pg 16
“It is highly desired that this individual have an extensive knowledge of USCG aeronautical engineering policy as outlined in Commandant Instruction Manual CIM 13020.1 (series)”
What does this statement mean (the end of paragraph 3.1.3) and how is the USCG going to evaluate the depth of a contractor’s Production Manager’s extensive knowledge of CIM 13020.1 series on USCG aeronautical engineering policy?
As stated in RFP, this is a “desired” attribute. Please submit detailed resume that articulates their experience.

Section 3.1.4/Pg 16

Do these individuals have to be an accredited engineer?
No.

Section 3.1.4/Pg 14

Since the contractor has to maintain design responsibility, is a DER required?
No.
Section 3.1.5/Pg 16
“It is highly desirable that these individuals have an extensive knowledge of USCG aeronautical engineering policy as outlined in Commandant Instruction Manual CIM 1320.1(series).”
What does this statement mean (end of paragraph 3.1.5) and how is the USCG going to evaluate the depth of a contractor’s Aircraft Lead Mechanic’s extensive knowledge of CIM 13020.1 series on USCG aeronautical engineering policy?
As stated in RFP, this is a “desired” attribute. Please submit detailed resume that articulates their experience.

Section 3.1.6/Pg 16

Please define “working as an engine mechanic?” Does the individual have to have worked in a T-56 overhaul facility or does working around T-56 engines qualify?

If a person is FAA powerplant licensed mechanic with experience on T-56 and other turbine engines what is the purpose of having to have 8 years experience on the T-56 and 3 years on the AE2100D3 engine except to add cost to the government?

No. For the engine shop chief, “working around T-56 engines” does NOT qualify. This individual shall have a minimum of eight years working as an engine mechanic on T-56 engines with at least three years of experience on the AE2100D3 engines.

The purpose is to have an engine shop chief with experience.

Section 3.1.6/Pg 16

In paragraph 3.1.6, how is the USCG going to evaluate the leadership skills and how is the USCG going to evaluate the depth of a contractor’s Engine Shop Chief’s extensive knowledge of CIM 13020.1 series on USCG aeronautical engineering policy?
As stated in RFP, this is a “desired” attribute. Please submit detailed resume that articulates their experience.

Section 4.2.1/pg 18

Will the Coast Guard provide a detailed pre-inspection schedule for each tail number by CG Air Station for the next 5 years so the contractor can develop the cost for the pre-inspection (H-PSI-0001) which has to be included in the PSI basic pricing IAW CLIN H-CG-0001?
No. See references (DVD) and Attachment 7 with applicable tail numbers, locations and flight hours.

Section 4.2.2/pg 18

Why is milestone 2 absent from attachment 1 and 2 for de-paint and paint?
There is not a specific PSI task card for de-paint.

Section 4.2.2/pg 18

Is the de-paint & paint effort included in the PSI basic work specification and should it be priced in CLIN H-CG-0001?
Yes. See 2.1 of the SOW.

Section 4.2.2/pg 18

If de-paint and paint is accomplished at a subcontracted facility and there is an aircraft discrepancy which requires maintenance work prior to flight back to the Prime contractor’s facility, will the USCG pay for the mechanics travel to the de-paint facility and T&M for the work on the aircraft?
These repairs will be handled on a case by case basis and if deemed necessary, they will be handled as a Non Recurrent Repair and the applicable travel CLIN will be utilized if necessary.

Section 4.2.10/pg 20

Will the depaint/paint facility be required to have a written and approved ground and flight risk plan in order to be GFR compliant?
Yes. See Section 8.2 Contractor Facilities.

Section 4.2.10/pg 20

If de-painting/painting is accomplished at a subcontracted facility will the GFR clauses be flowed down to the subcontractor?
Yes. See Section 8.2 Contractor Facilities.

Section 4.2.12/pg 20

Please define climate control capability for depaint/paint facility?
Climate control is defined as completely enclosed from weather elements and capable of controlling temperature and humidity. See RFP for requirements for controlling and recording relative humidity, etc.

Section 4.2.12/pg 20

There is a CLIN for contractor provided FCF crews, but is there a CLIN for contractor provided Ferry Crews?

Should this price include travel or will it be reimbursed by the government?

How many days should we assume per ferry light and will we be reimbursed for the crew for anytime over that stated period?

No. USCG will supply ferry crews.

Section 4.5/pg 24

If a subcontracted facility is used for de-paint, does the 220 calendar days start accruing when the aircraft arrives at the Prime’s facility or does it start when the aircraft arrives at the de-paint facility?
220 days starts accruing at beginning of milestone 2 (upon arrival at contractor’s facility or subcontracted de-paint facility)

Section 5.4.3.3/pg 27

“All operations shall be accomplished indoors…” Please define environmentally controlled facility?
Climate control is defined as completely enclosed from weather elements and capable of controlling temperature and humidity.

Section 5.4.3.4/pp 27-28

Shouldn’t sealing be accomplished prior to painting?
Yes. RFP has been changed.

Section 5.6/pg 30

Since the PSI requires numerous NDI inspections and since the USCG is going to supply Government Certified NDI inspectors, should the NDI inspection hours included under the current PSI-B contract CLIN for the basic inspection, now be removed from the FFP proposal CLIN H-CG-001 on the new contract?
Yes, please do not include cost of actual NDI. Set up (panel removals, cleaning, etc.) will still be responsibility of contractor.

All NDI requiring specific NDI equipment and specifically qualified NDI personnel will be completed by USCG personnel. For example, visual inspections can be completed by contractor but an eddy current will be completed by USCG personnel.

Section 7.0/pg 35

Is the USCG providing any GFP for the T-56 engine shop or prop shop?
Yes, see attachment 8.

Section 8.0/pg 36

What is the purpose of the pricing for the GFP in attachment 8?
FAR 45.201 requires that the name, part number, description, manufacturer, model number, NSN, quantity, and unit acquisition cost be in the solicitation and contract.

Section 8.2/pg 37

In the price evaluation of the proposal, does the USCG intend to evaluate the cost of moving 28 military and civilian personnel to the winning contractor’s facility?
No.

Section 8.2/pg 37

Will the personnel, especially the NDI/QA, be available at the winning contractor’s facility within the 120 days after contract award and input of the first aircraft under this contract?
Yes.

Section 8.2/pg 37

If an outside subcontractor is used for de-paint and paint do they also have to be GFR compliant within 120 days of contract award?
Yes.

Section 8.2/pg 38

Since this is primarily a FAR part 12 contract, why do all the repairs modifications and other efforts have to be performed at a single site, when strip & paint is allowed to be out-sourced, if it could be cost advantageous to the government to out-source other efforts such as props and engines?
USCG requires QA oversight on all processes and procedures associated with PSI.

Using FAR Part 12 for Commercial Items does not have anything to do with whether the Coast Guard allows off site subcontractors or requires all work to be completed in one facility.

Section 8.2/pg 38

Please define environmentally controlled paint hanger?
Climate control is defined as completely enclosed from weather elements and capable of controlling temperature and humidity.

Section 8.2/pg 38

For storage purposes on engines, propellers and avionics equipment please define the requirements for a climate controlled facility?
Climate control is defined as completely enclosed from weather elements and capable of controlling temperature and humidity.

Section 8.2/pg 39

Since there is the possibility that LOX servicing may be required during the de-paint/paint process, is the subcontracted facility required to have that capability?
Yes. See Section 8.2 of the SOW.

Section 8.2/pg 39