HL Flats DCSpec CONTRACT DOCUMENTS APPENDICES 2025.pdf
PDF 14 MB Posted
- Attached to
- 2025 GISD Surveillance Camera RFP
- Solicitation number
- RFP-GIS-250000002674-2
- Issued by
- Genesee County, Michigan
About this file
This document is a comprehensive Bidding and Contract Document for the Houghton Lake Flats Wildlife Floodings project, issued by the Michigan Department of Natural Resources (MDNR) and the Department of Technology, Management and Budget (DTMB). The project involves regrading and flattening existing dike embankments, replacing check dam weir structures, and replacing pump stations within the North and South Unit Floodings of the Houghton Lake Flats. The work will temporarily impact 0.16 acres and permanently impact 1.80 acres of existing wetlands, involving approximately 6,625 cubic yards of fill material and 5,825 cubic yards of excavation. The impoundments will be drawn down 1.7 vertical feet at a rate not exceeding 0.5 feet per day. The project is located in Roscommon County, Lake Township, and has been authorized by a permit from the Michigan Department of Environment, Great Lakes, and Energy (EGLE), valid from June 30, 2023, to June 30, 2025.
The project is funded through state resources and requires strict compliance with environmental regulations, including soil erosion control, wetland protection, and dam safety standards. The geotechnical investigation revealed that the dikes are primarily constructed of sand, with varying slope angles and soil compositions. Recommendations include using geocells to stabilize steep slopes, implementing erosion control measures, and constructing access roads with specific aggregate specifications. The project involves careful management of water levels, soil conditions, and environmental impacts, with detailed requirements for construction methods, material disposal, and site restoration. The contract includes provisions for monitoring, reporting, and ensuring compliance with state and federal environmental regulations throughout the project's duration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bidding and Contract Document (R 03/25) Project Name: Houghton Lake Flats Wildlife Floodings File No.7561/18123.DPL
APPENDIX I
GLOSSARY
GLOSSARY
Activity An element in the Progress Schedule establishing a requisite step, or the time and resources required, for completing the part of the Work associated with that Activity.
Addenda Written instruments that are used by the Owner and/or Professional to incorporate interpretations or clarifications, modifications, and other information into the Bidding Documents. An Addendum issued after Bid opening to those Bidders who submitted a Bid, for the purpose of re-bidding the Work without re-advertising, is referred to as a post-Bid Addendum.
Agency- Any unit, section, division, department, or other instrumentality of the State that benefits from the Work.
Alternate Refers to work specified in the Bidding Documents for which the Bidder must bid a Bid Price.
Apparent Low Bidders: Those Bidders whose Base Bid, when added to those specific Alternates the Owner intends to accept, yields the three lowest sums of Bid and Alternates. Additional Bidders may be considered Apparent Low Bidders if their Bid, when added to those specific Alternates the Owner intends to accept, yields a sum within 10% of the lowest of the Apparent Low Bidder’s sum. If a qualified disabled veteran meets the requirements of the contract solicitation, provides acceptable responses to both Part One and Part Two of the Best Value Construction Bidder Evaluation to achieve a Best Value recommendation and with the veteran’s preference is the lowest responsive, responsible, best value Bidder it is considered the Apparent Low Bidder.
Archaeological Feature Any prehistoric or historic deposit of archaeological value, as determined by a representative of a State Agency that is duly authorized to evaluate such findings and render such judgments. An Archaeological Feature deposit may include, but is not limited to Indian habitations, ceremonial sites, abandoned settlements, treasure trove, artifacts, or other objects with intrinsic archaeological value and that relate to the history and culture of the State of Michigan.
Authorized Technical Data Information and data contained in a report of exploration and tests of subsurface conditions. Also, any physical data (dimension, location, conditions, etc.) contained in those Drawings of physical conditions of existing surface and subsurface facilities.
Best Value- The bids will be evaluated for best value based on price and qualitative components that may include but are not limited to technical design, technical approach, quality of proposed personnel, and management plans, per PA 430 of 2012.
Bid Written offer by a Bidder for the Work, as specified, which designates the Bidder’s Base Bid and Bid Prices for all Alternates.
The term Bid includes a re-bid.
Bidder The Person acting directly, or through an authorized representative, who submits a Bid directly to the Owner.
Bidding Documents The proposed Contract Documents as advertised, and all Addenda issued before execution of the Contract.
Bid Price The Bidder’s price for a lump sum item of work, or the product of the Bidder’s unit price for an item of Unit Price Work times the quantity given on the Bid Form for that item.
Bid Security A security serving as a guarantee that the Bidder will conform to all conditions.
Bidding RequirementsThe Advertisement, Instructions to Bidders, Supplementary Instructions, Information for Bidders, Bid Form, Bid Form Attachments, and qualification submittals, as advertised and as modified by Addenda, and any other Section included within Division 0 of the Bidding Documents for the purpose of governing bidding and award of the Contract.
Board The Administrative Board of the State of Michigan.
Bond Security furnished by the Contractor, as required by the Contract Documents.
Business Day Any Day except Saturdays, Sundays and holidays observed by the Owner.
Bulletin A request used by the Owner to describe a change in the Work under consideration by the Owner and to request the Contractor to submit a proposal for the corresponding adjustment in Contract Price and/or Contract Time, if any.
Calendar Day Every day shown on the calendar, Saturdays, Sundays, and holidays included.
Cash Allowance An Owner-specified sum included within the Contract Price to reimburse the Contractor for the actual purchase/furnished cost of materials and/or equipment or other designated items, as specifically provided in the Contract Documents.
Although the scope (e.g., the required quantity) of any Work covered by a Cash Allowance is sufficiently detailed in the Contract Documents for the purposes of bidding the required labor costs, Subcontract costs, construction equipment costs and general conditions costs and Fee, it is understood that the required materials, equipment or other designated items are of uncertain purchase cost at the time of Bid or are yet to be specified in more detail by the Professional as to quality, appearance, durability, finish and such other necessary features affecting purchase price.
Change Order A written order issued and signed by the Owner, which amends the Contract Documents for changes in the Work or an adjustment in Contract Price and/or Contract Time, or both.
Construction Mechanic A skilled or unskilled mechanic, laborer, worker, helper, assistant, or apprentice working on a state project but shall not include executive, administrative, professional, office, or custodial employees.
Contract Award The official action of the Board, the Director-SFA or the Director-DCD awarding the Contract to the Contractor.
Contract Documents Written and graphic documents that form the legal agreement between the Owner and the Contractor, consisting of this document, completed Bid and Contract forms, terms and conditions of the contract, specifications, drawings, addenda, Notice of Award, Notice-to-Proceed and contract change orders.
Contract Price The total compensation, including authorized adjustments, payable by the Owner to the Contractor (subject to provisions for Unit Price Work).
Contract TimesThe Contract Times for the entire Work are the periods allowed, including authorized adjustments, for Substantial Completion and final completion of the Work. The Contract Times for a designated portion of the Work are the periods allowed for Substantial Completion and final completion of any such portion of the Work, as specified in the Contract Documents.
Contractor Business enterprise with which the Owner has entered into the Contract.
Correction Period A period during which the Contractor must, in accordance with the Contract Documents, (a) correct or, if rejected, remove, and replace Defective Work, and (b) maintain warranties for materials and equipment in full force and effect.
Cost of the Work Involved The sum of all costs that would be, or were, necessarily incurred by the Contractor in providing any Work Involved with the related change, less the costs that would be, or would have been, incurred by the Contractor to provide such Work without the related change.
Defective As determined by the Professional, an adjective which when referring to or when applied to the term “Work” refers to (a) Work not conforming to the Contract Documents or not meeting the requirements of an inspection, test, or approval, or (b) Work itemized in a Punch List which the Contractor fails to complete or correct within a reasonable time after issuance of the Punch List by the Professional.
Delay Any act or omission or other event that in any manner adversely affects or alters the schedule, progress or completion of all or any part of the Work. Delay is a generic term intended to include deferral, stoppage, slow down, interruption and extended performance, and all related hindrance, rescheduling, disruption, interference, inefficiency and productivity and production losses.
Department (DTMB) Department of Technology, Management and Budget of the State of Michigan.
Director- The Director of the Department.
Director-SFA- The Director of DTMB State Facilities Administration.
Director-DCD- The Director of DTMB State Facilities Administration, Design and Construction Division.
Division Each of the numbered, distinct parts (starting with Division 0) into which the Specifications are divided.
Drawings Part of the Contract Documents showing the Work. Drawings must neither serve nor be used as Shop Drawings.
Emergency A condition affecting the safety or protection of persons, or the Work, or property at or adjacent to the site.
State Facilities Administration (SFA)-Entity in the Department responsible for design, construction, and operations and maintenance of facilities.
Fee for the Work Involved (Fee) An established, percentage mark-up on the Cost of the Work Involved which is allowed to the Contractor for (a) reasonable administrative costs, and (b) negotiated, reasonable profit on the Cost of the Work Involved.
Hazardous Material Asbestos containing materials (ACMs), Polychlorinated biphenyls (PCBs), petroleum products, such construction materials as paint thinners, solvents, gasoline, oil, etc., and any other like material the manufacture, use, treatment, storage, transportation, or disposal of which is regulated by federal, state, or local Laws governing the protection of public health, natural resources, or the environment.
Invitation To Bid (ITB) - The solicitation document presenting the terms and conditions that will become part of the Contract when the Bid is accepted.
Law(s) Means federal, state, and local statutes, ordinances, orders, rules and/or regulations.
MCL The Michigan Compiled Laws of the State of Michigan.
Means and Methods Includes means, methods, techniques, sequences and/or procedures applicable to the Work.
Notice of Award Written notice accepting the Bid to the lowest responsive, responsible Bidder and designating the Contract Price (and establishing the Alternates accepted by the Owner).
Notice-to-Proceed Written notice issued by the Project Director directing the Contractor to commence the construction activities and establishing the start date of the Contract Time.
On-Site Inspection– The Professional’s on-site examination of the Contractor’s completed or in progress Work to determine and verify to the Project Director that the quantity and quality of all Work complies with the requirements of the Contract Documents.
Owner The State of Michigan, with whom the Contractor has entered into the Contract and for whom the Work is to be provided.
Owner Field Representative A State employee or consultant, acting collaboratively with the Project Director, providing on-site, periodic observation and documentation of the Work for compliance with the Contract Documents.
Partial Use The use, by the Owner, of a designated portion of the Work before accomplishing Substantial Completion of the entire Work. Partial Use does not mean Substantial Completion of the portion of the Work placed in use by the Owner.
PersonIndividuals, partnerships, corporations, receivers, trustees, joint ventures or any other legal entity and any combinations of any of them.
Political Subdivision Any county, city, village, or other local unit of the State, including any agency, department, or instrumentality of any such county, city, village, or other local unit.
PostBid Submittal A Qualification Submittal required of the Bidder selected under Section 00100 - 22 before Contract Award, and which is used by the Owner in the evaluation of the Bid of the selected Bidder.
Professional Services Contractor (PSC or Professional) The individual or business entity who has the authority to practice the design disciplines required by the Contract Documents. An Agency with appropriate licensing may replace the PSC in their role if a consultant is not used.
Project The total construction, which includes the Work and possibly other work completed by others, as indicated in the Contract Documents.
Project Director- Designated State employee(s) (a) Responsible for directing and supervising the Professional’s services during the period allowed for completion of the Work; and/or (b) Acting as representative for the Owner and for the enforcement of the Contract Documents, approving payment to the Contractor and coordinating the activities of the State, Owner, Professional and Contractor.
Project Schedule Work Schedule that shows the Contractor's approach to planning, scheduling, and execution of the Work and that accurately portrays completed Work as to sequencing and timing, as provided in the Contract Documents.
Project Specifications The Contract Documents organized into Divisions. "Technical Specifications" means Divisions of the Specifications consisting of technical descriptions of materials, equipment, construction systems, standards, and workmanship.
Provisionary Allowance An amount included within the Contract Price to reimburse the Contractor for the cost to furnish and perform Work that is uncertain because, for example, it is indeterminate in scope and may not be shown or detailed in the Contract Documents.
Punch List A list of minor items to be completed or corrected by the Contractor, any one of which do not materially impair the use of the Work for its intended purpose.
Qualified Disabled Veteran (QDV)- QDV as defined by Public Act 22 of 2010, MCL 18.1241.3 and supported by a DD214 Proof of Service and Discharge, a Veterans Administration rating decision letter, proof of disability (if the disability is not indicated on the DD214), and appropriate legal documents setting forth the 51% natural persons QDV ownership.
Record Documents Drawings, Specifications, Addenda, Change Orders, Change Authorizations, Bulletins, inspection, test and approval reports, photographs, written clarifications and interpretations and all other documents recording, or annotated to show, all revisions and deviations between the as-built installation and the Contract Documents, all approved Submittals and all clarifications and interpretations.
Records Books, reports, documents, electronic data, and other evidence relating to the bidding, award and furnishing and performance of the Work.
Recycled Material Recycled paper products, structural materials made from recycled plastics, re-refined lubricating oils, reclaimed solvents, recycled asphalt and concrete, recycled glass products, re-treaded tires, ferrous metals containing recycled scrap metals and all other materials that contain (a) waste materials generated by a business or consumer, (b) materials that have served their intended purpose, and/or (c) materials that have been separated from solid waste for collection, recycling and disposition in the percentage determined by the State as provided by Law.
Request for Payment The form provided by the Owner (Payment Request DTMB-0440) to be used by the Contractor in requesting payment for Work completed, which must enclose all supporting information required by the Contract Documents.
Schedule of Values A schedule of pay items, which subdivides the Work into its various parts and which details, for each itemized part, cost and pricing information required for making payments for Work performed. The sum of all pay item costs in the Schedule of Values must equal the Contract Price for the Work.
Shop Drawings Includes drawings, diagrams, illustrations, standard schedules, performance charts, instructions and other data prepared by or for the Contractor to illustrate some part of the Work, or by a Supplier and submitted by the Contractor to illustrate items of material or equipment.
Soil Erosion and Sedimentation Control– The planning, design and installation of appropriate Best Management Practices designed and engineered specifically to reduce or eliminate the off-site migration of soils via water runoff, wind, vehicle tracking, etc.
Soil erosion and sedimentation control in the State of Michigan is regulated under The Natural Resources Environmental Protection Act; Soil Erosion and Sedimentation Control, 1994 PA 451, Part 91, as amended, MCL 324.9101 et seq. Soil erosion and sedimentation control associated with this Contract is monitored and enforced by the DTMB-SFA.
State The State of Michigan in its governmental capacity, including its departments, divisions, agencies, boards, offices, commissions, officers, employees, and agents. Non-capitalized references to a state refer to a state other than the State of Michigan.
State Construction Code The Michigan State Construction Code Act, 1972 PA 230, as amended, MCL 125.1501 et seq.
Subcontractor A Person having an agreement with the Contractor to provide labor at the site and furnishing materials and/or equipment for incorporation into the Work.
Submittals Includes technical Submittals, Progress Schedules and those other documents required for submission by the Contract Documents. The term "technical Submittal" includes Shop Drawings, brochures, samples, Operation and Maintenance (O&M) Manuals, test procedures and any other Submittal the Contract Documents require the Contractor to submit to demonstrate how the items covered, after installation or incorporation into the Work, will conform to the information given in the Contract Documents and be compatible with the design of the completed Work as a functioning whole as indicated in the Contract Documents.
Substantial Completion The Work, or a portion of the Work designated in the Contract Documents as eligible for separate Substantial Completion, has been completed in accordance with the Contract Documents as determined by the PSC, to the extent that the Owner can use or occupy the entire Work, or the designated portion of the Work, for the use intended without any outstanding, concurrent Work at the site, except as may be required to complete or correct Punch List items.
Supplier A manufacturer or fabricator, or a distributor, material man or vendor representing a manufacturer or fabricator, who has an agreement with the Contractor to furnish materials and/or equipment.
Underground UtilitiesPipelines, piping, conduit, duct, cables, wells, tanks, tunnels and appurtenances, or other similar facilities, installed underground to convey or support conveyance of potable water, sprinkler or irrigation water, fire protection systems, electricity, gases, steam, petroleum products, sewerage and drainage removal, telephone, communications, cable TV, traffic, or control systems.
Unit Price Work The work involving specified quantities (i.e., related Work quantities) which, when performed, is measured by the Professional and paid using the measured quantities and unit prices contained in the Contract Documents. Performance of Unit Price Work for undefined quantities is contingent upon conditions encountered at the site, as determined, and authorized by the Professional.
Unit Price Work, Specific Work of specified and defined quantities (i.e., quantities are detailed in, and can be taken-off from, the Contract Documents) that when performed is measured by the Professional and paid based on the measured quantities and unit prices contained in the Contract Documents.
Work- (as in “the Work,” "the entire Work”) The entire completed Construction required by the Contract Documents. The Work results from furnishing and performing all services, obligations, responsibilities, management, supervision, labor, materials, equipment, construction equipment, general conditions, permits, taxes, patent fees and royalties, testing, inspection and approval responsibilities, warranties, temporary facilities, small tools, field supplies, Bonds, insurance, mobilization, close-out, overhead and all connections, devices and incidental items of any kind or nature required and/or made necessary by the Contract Documents.
Work Involved, any Work Involved Existing or prospective Work (a) reflected in any notice, proposal, or claim, or (b) reflected in changes ordered or in process, or (c) affected by Delay.
Revision Date: 3/2025
APPENDIX II
SPECIAL WORKING CONDITIONS
DEPARTMENT OF NATURAL RESOURCES
The Work comprising this Project will be performed at a site of the Department of Natural Resources. The Contractor must comply with all rules and regulations pertaining to such sites and must conform to the following rules:
1. The Contractor must always provide a competent Superintendent satisfactory to the Department of Natural
Resources on the work site during working hours with full authority to act for him. It must be the Contractor's responsibility to furnish the Department of Natural Resources with the name, address, and telephone number of the responsible person to contact for Emergency during after hour, weekend, and holiday periods.
2. Access to and egress from the site must be via routes specifically designated by the Department of Natural
Resources authorized representative.
3.1 No Work must be performed at the site on Saturdays, Sundays, holidays or during night hours without the written permission from the Department of Natural Resources; and
3.2 No Work must be performed prior to November 3, 2025.
3.3 No Work during the following holidays:
Memorial Day weekend, between 3:00 pm, Friday May 22, 2026, and 6:00 am, Tuesday, May 26, 2026.
Independence Day, between 3:00 pm, Friday July 3, 2026, and 6:00 am, Monday, July 6, 2026.
4. Areas on the site for employee parking, toolboxes, material lay down, etc., must be assigned by the Department of Natural Resources. All firearms, weapons, alcoholic beverages, or explosives must be removed from vehicles before entering the site.
5. Heavy equipment such as bulldozers and power shovels must be locked or immobilized in an acceptable manner when not in use. No tools, small pipe, copper, or wire must remain on the site overnight, unless acceptably locked inside shanties or tool chests. There will be no exchange, loaning or borrowing of tools, equipment or manpower between the Department of Natural Resources and the Contractor.
6. The Contractor must comply with the special condition requirements of the Department of Natural Resources and the United States Army Corps of Engineers Permit Sections appended to these specifications.
APPENDIX III
SPECIAL PROJECT PROCEDURES
SOIL EROSION AND SEDIMENTATION CONTROL PROJECT PROCEDURES FOR
CONTRACTORS ON DTMB OWNED AND MANAGED PROPERTIES
1. Comply with Part 91, Soil Erosion and Sedimentation Control of the Natural Resources and Environmental
Protection Act 1994 PA 451, as amended.
2. Contact the DTMB, SFA, Design and Construction Division to discuss the implementation of soil erosion and sedimentation control (SESC) on the Project with DTMB SESC Officer. Phone (517) 388-3045 or Email DTMB-SESC@michigan.gov.
3. Following the award of a contract, the Contractor will be required to prepare and issue for approval an SESC Implementation Plan, which indicates the Contractor’s intended implementation of SESC on the project including a schedule and sequence. The Environmental Health and Safety Section, upon approval of the implementation plan, will issue to the Contractor an “Authorization to Proceed with Earth Change” document, which is to be posted at the job site. This document is issued in lieu of a permit from the county. Earthwork shall not begin prior to the issuance of this Authorization. Upon receipt of the Authorization document, the Contractor may begin earth change activities.
4. See below the “Checklist for Contractor’s SESC Implementation Plan” for details of the required information necessary for the Contractor to create the SESC Implementation Plan. The intent of this plan is to ensure that the Contractor has reviewed and understands the SESC provisions within the plans and specifications.
5. CHECKLIST FOR CONTRACTOR’S SOIL EROSION AND SEDIMENTATION CONTROL
IMPLEMENTATION PLAN (For projects that include earth changes or disturb existing vegetation):
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION, DESIGN AND CONSTRUCTION DIVISION
SOIL EROSION AND SEDIMENTATION CONTROL PROGRAM
P.O. Box 30026, Lansing, Michigan 48909
PROJECT TITLE:
PROJECT LOCATION:
PROJECT FILE NUMBER:
INDEX NUMBER:
Prior to the start of earthwork, the Contractor must submit a Soil Erosion and Sedimentation Control (SESC) Implementation Plan to the Michigan Department of Technology, Management and Budget, Soil Erosion and Sedimentation Control Program. The intent of this plan is to ensure that the Contractor has reviewed and understands the SESC provisions within the plans and specifications. The following checklist will provide Contractors with assistance in creating the SESC Implementation Plan.
The SESC Implementation Plan must include:
1. A written plan or letter demonstrating:
The Contractor’s means and methods for the implementation of SESC provisions included within the plans and specifications and compliance with the provisions of Part 91 of PA 451 of 1994, as amended.
The Contractor’s plan for dust control.
The Contractor’s plan for inspection and maintenance of temporary SESCs.
2. A map, location plan, drawing, or amended copy of the Project SESC or grading plan showing:
The locations of any stockpiles of soil associated with the Project The temporary SESC controls associated with stockpiles of soil The Contractor’s suggested or proposed additions or relocations of any temporary or permanent SESCs.
associated with the Project plans and specifications (subject to approval by Engineer and DTMB) Location of site entrances, exits and vehicle routes Location of site superintendent’s/project manager’s site trailer or office (for SESC Inspector check-in)
3. A schedule for the installation and removal of temporary controls and the installation of permanent soil erosion and sedimentation controls in relation to the overall construction schedule.
Submit the above items to the above address.
Upon approval of the Contractor’s plan, an “Authorization to Proceed with Earth Change” will be issued by DTMB, Design and Construction Division.
DEMOLITION/REMODELING PROJECT PROCEDURES
Furnish all equipment, materials, labor, and services necessary to complete all building demolition required in connection with the existing building, in order to permit the installation of new Work. The goal of the Owner is to generate the least amount of waste or debris possible. However, inevitable waste and debris that are generated shall be reused, salvaged, or recycled, and disposal in landfills shall be minimized to the extent economically feasible. The Contractor will be required to prepare waste management plan for the collection, handling, storage, transportation, and disposal of the waste generated at the construction site for the Owner’s review and approval. The Contractor will be required to produce waste management progress reports.
1. Locations: Notations are made in various places on the Drawings to call attention to building demolition which is required; however, these Drawings are not intended to show every item to be removed. The Contractor and the Subcontractors for the various trades must remove the materials related to their respective trades as required to permit the construction of the new Work as shown.
2. Permits: The Contractor must secure from the appropriate agencies all required permits necessary for proper execution of the work before starting work on the project site. All fees for securing the permits must be paid by the Contractor, including all inspection costs which may be legally assessed by the Bureau of Construction Codes in accordance with the authority granted under the Public Act 1980 PA 371, as amended.
3. Enclosures: Where it is necessary to make alterations to walls, floors or roof of the existing building, the Contractor must provide and maintain dustproof partitions to separate the parts where Work is being done from the adjoining parts occupied by the State Agency. Where any parts are opened and exposed to the elements, the Contractor must provide weather tight enclosures to fully protect the structure and its contents.
4. Waste Management Plan: The management plan must address waste source identification and separation, returns, reuse and salvage, recycling, landfill options, alternatives to landfilling, materials handling procedures and transportation.
5. Preparation: Protect all existing Work that is to remain and restore in an approved manner any such Work that becomes damaged.
5.1 Rubbish and debris resulting from the Work must be removed immediately from the site by the Contractor.
However, any recyclable materials must be recycled; the Contractor will be required to use alternatives to landfills for waste disposal such as reuse or recycle of asphalt, bricks, concrete, masonry, plastics, paint, glass, carpet, metals, wood, drywall, insulation, and any other waste materials to the extent practical.
5.2 Unless otherwise specified, the Agency will remove existing furniture, drapery tracks, draperies, window blinds, and other equipment items, which might interfere with the new construction.
6. Coordination: Demolition work, in connection with any new unit of Work, must not be commenced until all new materials required for completion of that new item of Work are at hand.
7. Waste Management Plan Progress Reports: Submit an updated report with the payment requests. The progress reports shall include:
a. The amount of waste sent to a landfill, tipping fees paid and the total disposal cost. Include supporting documents such as manifests, weight tickets, receipts and/or invoices.
b. Records for each material recycled/reused/salvaged from the project including the amount, date removed from the job site, destination, transportation cost, recycled materials, and the net cost/ savings.
c. Breakdown of waste by type generated to date.
d. Recycling/salvage/landfill rates.
e. Percent of waste recycled/salvaged to date.
APPENDIX IV
PROJECT SIGN FOR PROJECTS COSTING IN EXCESS OF
$500,000
RESERVED
APPENDIX V
PREVAILING WAGE RATE SCHEDULES
AND FEDERAL PROVISIONS ADDENDUM
Federal Provisions Addendum
This addendum applies to purchases that will be paid for in whole or in part with funds obtained from the federal government. The provisions below are required and the language is not negotiable. If any provision below conflicts with the State’s terms and conditions, including any attachments, schedules, or exhibits to the State’s Contract, the provisions below take priority to the extent a provision is required by federal law; otherwise, the order of precedence set forth in the Contract applies. Hyperlinks are provided for convenience only; broken hyperlinks will not relieve Contractor from compliance with the law.
1. Equal Employment Opportunity
If this Contract is a “federally assisted construction contract” as defined in 41 CFR Part 60-1.3, and except as otherwise may be provided under 41 CFR Part 60, then during performance of this Contract, the Contractor agrees as follows:
(1) The Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to the following:
Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination;
rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.
(2) The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin.
(3) The Contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with the Contractor's legal duty to furnish information.
(4) The Contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers' representatives of the Contractor's commitments under this section, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
(5) The Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
(6) The Contractor will furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the administering agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
(7) In the event of the Contractor's noncompliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations, or orders, this Contract may be canceled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further Government contracts or federally assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
(8) The Contractor will include the portion of the sentence immediately preceding paragraph (1) and the provisions of paragraphs (1) through (8) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The Contractor will take such action with respect to any subcontract or purchase order as the administering agency may direct as a means of enforcing such provisions, including sanctions for noncompliance:
Provided, however, that in the event a Contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the administering agency, the Contractor may request the United States to enter into such litigation to protect the interests of the United States.
The applicant further agrees that it will be bound by the above equal opportunity clause with respect to its own employment practices when it participates in federally assisted construction work: Provided, That if the applicant so participating is a State or local government, the above equal opportunity clause is not applicable to any agency, instrumentality or subdivision of such government which does not participate in work on or under the contract.
The applicant agrees that it will assist and cooperate actively with the administering agency and the Secretary of Labor in obtaining the compliance of contractors and subcontractors with the equal opportunity clause and the rules, regulations, and relevant orders of the Secretary of Labor, that it will furnish the administering agency and the Secretary of Labor such information as they may require for the supervision of such compliance, and that it will otherwise assist the administering agency in the discharge of the agency's primary responsibility for securing compliance.
The applicant further agrees that it will refrain from entering into any contract or contract modification subject to Executive Order 11246 of September 24, 1965, with a contractor debarred from, or who has not demonstrated eligibility for, Government contracts and federally assisted construction contracts pursuant to the Executive Order and will carry out such sanctions and penalties for violation of the equal opportunity clause as may be imposed upon contractors and subcontractors by the administering agency or the Secretary of Labor pursuant to Part II, Subpart D of the Executive Order. In addition, the applicant agrees that if it fails or refuses to comply with these undertakings, the administering agency may take any or all of the following actions: Cancel, terminate, or suspend in whole or in part this grant (contract, loan, insurance, guarantee); refrain from extending any further assistance to the applicant under the program with respect to which the failure or refund occurred until satisfactory assurance of future compliance has been received from such applicant; and refer the case to the Department of Justice for appropriate legal proceedings.
2. Davis-Bacon Act (Prevailing Wage)
If this Contract is a prime construction contracts in excess of $2,000, the Contractor (and its Subcontractors) must comply with the Davis-Bacon Act (40 USC 3141-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”), and during performance of this Contract the Contractor agrees as follows:
(1) All transactions regarding this contract shall be done in compliance with the Davis-Bacon Act (40 U.S.C.
3141- 3144, and 3146-3148) and the requirements of 29 C.F.R. pt. 5 as may be applicable. The contractor shall comply with 40 U.S.C. 3141-3144, and 3146-3148 and the requirements of 29 C.F.R. pt. 5 as applicable.
(2) Contractors are required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor.
(3) Additionally, contractors are required to pay wages not less than once a week.
3. Copeland “Anti-Kickback” Act
If this Contract is a contract for construction or repair work in excess of $2,000 where the Davis-Bacon Act applies, the Contractor must comply with the Copeland “Anti-Kickback” Act (40 USC 3145), as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”), which prohibits the Contractor and subrecipients from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled, and during performance of this Contract the Contractor agrees as follows:
(1) Contractor. The Contractor shall comply with 18 U.S.C. § 874, 40 U.S.C. § 3145, and the requirements of 29 C.F.R. pt. 3 as may be applicable, which are incorporated by reference into this contract.
(2) Subcontracts. The Contractor or Subcontractor shall insert in any subcontracts the clause above and such other clauses as FEMA or the applicable federal awarding agency may by appropriate instructions require, and also a clause requiring the Subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all of these contract clauses.
(3) Breach. A breach of the contract clauses above may be grounds for termination of the contract, and for debarment as a Contractor and Subcontractor as provided in 29 C.F.R. § 5.12.
4. Contract Work Hours and Safety Standards Act
If the Contract is in excess of $100,000 and involves the employment of mechanics or laborers, the Contractor must comply with 40 USC 3702 and 3704, as supplemented by Department of Labor regulations (29 CFR Part 5), as applicable, and during performance of this Contract the Contractor agrees as follows:
(1) Overtime requirements. No Contractor or Subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.
(2) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (1) of this section the Contractor and any Subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such Contractor and Subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (1) of this section, in the sum of $27 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph
(1) of this section.
(3) Withholding for unpaid wages and liquidated damages. The State shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Contractor or Subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (2) of this section.
(4) Subcontracts. The Contractor or Subcontractor shall insert in any subcontracts the clauses set forth in paragraph (1) through (4) of this section and also a clause requiring the Subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (1) through (4) of this section.
5. Rights to Inventions Made Under a Contract or Agreement
If the Contract is funded by a federal “funding agreement” as defined under 37 CFR §401.2 (a) and the recipient or subrecipient wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work under that “funding agreement,” the recipient or subrecipient must comply with 37 CFR Part 401, “Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements,” and any implementing regulations issued by the awarding agency.
6. Clean Air Act and the Federal Water Pollution Control Act
If this Contract is in excess of $150,000, the Contractor must comply with all applicable standards, orders, and regulations issued under the Clean Air Act (42 USC 7401-7671q) and the Federal Water Pollution Control Act (33 USC 1251-1387), and during performance of this Contract the Contractor agrees as follows:
Clean Air Act
1. The Contractor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq.
2. The Contractor agrees to report each violation to the State and understands and agrees that the State will, in turn, report each violation as required to assure notification to the Federal Emergency Management Agency or the applicable federal awarding agency, and the appropriate Environmental Protection Agency Regional Office.
3. The Contractor agrees to include these requirements in each subcontract exceeding $150,000 financed in whole or in part with Federal assistance provided by FEMA or the applicable federal awarding agency.
Federal Water Pollution Control Act
1. The Contractor agrees to comply with all applicable standards, orders, or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq.
2. The Contractor agrees to report each violation to the State and understands and agrees that the State will, in turn, report each violation as required to assure notification to the Federal Emergency Management Agency or the applicable federal awarding agency, and the appropriate Environmental Protection Agency Regional Office.
3. The Contractor agrees to include these requirements in each subcontract exceeding $150,000 financed in whole or in part with Federal assistance provided by FEMA or the applicable federal awarding agency.
7. Debarment and Suspension
A “contract award” (see 2 CFR 180.220) must not be made to parties listed on the government-wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (51 FR 6370; February 21, 1986) and 12689 (54 FR 34131; August 18, 1989), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.
(1) This Contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt.
3000. As such, the Contractor is required to verify that none of the Contractor’s principals (defined at 2 C.F.R. § 180.995) or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. § 180.940) or disqualified (defined at 2 C.F.R. § 180.935).
(2) The Contractor must comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into.
(3) This certification is a material representation of fact relied upon by the State. If it is later determined that the contractor did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to the State, the Federal Government may pursue available remedies, including but not limited to suspension and/or debarment.
(4) The bidder or proposer agrees to comply with the requirements of 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C while this offer is valid and throughout the period of any contract that may arise from this offer. The bidder or proposer further agrees to include a provision requiring such compliance in its lower tier covered transactions.
8. Byrd Anti-Lobbying Amendment
Contractors who apply or bid for an award of $100,000 or more shall file the required certification in Exhibit 1 – Byrd Anti-Lobbying Certification below. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, officer or employee of Congress, or an employee of a Member of Congress in connection with obtaining any Federal contract, grant, or any other award covered by 31 U.S.C. § 1352. Each tier shall also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient who in turn will forward the certification(s) to the awarding agency.
9. Procurement of Recovered Materials
Under 2 CFR 200.322, Contractors must comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act.
(1) In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired—
1. Competitively within a timeframe providing for compliance with the contract performance schedule;
2. Meeting contract performance requirements; or
3. At a reasonable price.
(2) Information about this requirement, along with the list of EPA- designated items, is available at EPA’s Comprehensive Procurement Guidelines web site, https://www.epa.gov/smm/comprehensive- procurement-guideline-cpg-program.
(3) The Contractor also agrees to comply with all other applicable requirements of
Section 6002 of the Solid Waste Disposal Act.
10. Additional FEMA Contract Provisions.
The following provisions apply to purchases that will be paid for in whole or in part with funds obtained from the Federal Emergency Management Agency (FEMA):
(1) Access to Records. The following access to records requirements apply to this contract:
a. The Contractor agrees to provide the State, the FEMA Administrator, the Comptroller General of the United States, or any of their authorized representatives access to any books, documents, papers, and records of the…