HC102822R0040 updated questions and answers.docx

DOCX document 30 KB Posted

Attached to
832267579 DC Hawaii Raised Floor
Solicitation number
HC102822R0040
Issued by

About this file

This document contains answers to questions from offerors regarding a solicitation for electrical installation services at a Defense Information Systems Agency data center in Pearl Harbor, Hawaii. Key details include the scope of work involves purchasing and installing equipment to provide redundant power to identified computer room air handlers, including automatic transfer switches, breakers, feeders and underfloor conduit routing. The period of performance is one year from award. Offerors must provide their own travel costs and certified technicians if required by manufacturers for start up or testing. DISA will provide escorts as needed and has limited material laydown space. The revised proposal due date is September 15th.

View the file

Other files

File Type Posted
HC102822R0040 0001 solicitation amend 2.docx DOCX document
HC102822R0040 0001 solicitation amend.docx DOCX document
DC raised floor solicitation QA.docx DOCX document
01-02 - Identification Labeling and Marking Spec.docx DOCX document
NDA.docx DOCX document
MDP-A one-line.pdf PDF
VAL Template.docx DOCX document
Solicitation.docx DOCX document
Bldg 77 layout and panels.pdf PDF
Pre-Proposal Site Visit.docx DOCX document
01 33 00 - Submittal Procedures.docx DOCX document
26-01 Electrical Safety Program.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP Document

Document Section/Pg. No.
Question

All

Comment: Period of Performance will need to be revised based on new solicitation release date.

DISA Response:
Agreed. One year from award as stated in the POW.
Solicitation
SOW Section 8, page 13.
SOW states: (Note to COR: A travel plug number* will be required in order for the offeror’s proposal to cover travel.)

Question: Is the government providing a plug in number for travel or is the offeror to provide a travel number?

DISA Response:
The offeror is required to provide a travel cost for the project.
Solicitation
SOW Section , Subfactor 1,

page 56.

SOW States: In order for this subfactor to be rated Acceptable, the contractor shall submit a draft executable schedule with stated tasks for equipment installation that identifies all milestones that include start dates (draft schedule use July 1st as Day 1), … Question: What date should the offeror use for Day 1 on the project schedule?

DISA Response:
As stated in the SOW, July 1st is an example date. Offeror can use a arbitrary date with identified periods to demonstrate that each task can be completed within the PoP.
Solicitation
General
Will DISA grant an extension (minimum 1 week) on the proposal due date based on offeror receipt of

Q&A? Offerors have less than a week to price and pull proposals together for submission.

DISA Response:
Yes. Revised proposal due date is 15-Sept.
Solicitation
SOW 6.4.1
CRAH AC-3 has little to no clearance available on

either side. On the right side, unit AC-2 is adjacent, on the left, a BMS panel is adjacent. Installing the ATS “in close proximity” is almost impossible.

Would DISA accept installation of the ATS adjacent to panel EH-1, where there is sufficient space?

DISA Response:
Question is difficult to understand. Adjacent to the AC-3 CRAH unit, the wall takes a 90 degree bend with no obstructions. This would be the preferred location for any ATS unit. The area next to panel EH-1 is reserved for another project and unavailable for use.
Solicitation
SOW 6.4.5
The scope of work states: “Purchase and install new feeder conductors from previous CRAC AC-3 circuit breaker in EH-1 in room 189 to supply new ATS in room 164.” The rest of the SOW indicates that the ATS location is to be in room 189. Please confirm that ATS location is in room 189, the same room as

AC-3.

DISA response:
Yes. The intent is to locate the new ATS in room 189. New feeders to the CRAH unit will replace the existing feeders to CRAC AC-3.
Solicitation
SOW 6.5.1
Does DISA have a preference as to which bus “A” or

“B” within MDP-A the new breaker is installed on?

DISA response:
No. Panel MDP-A is normally supported by the building “A” bus. There are two sections to panel MDP-A but both sections are supported by the same feeder.
Solicitation
SOW 6.6.1
What is the intent of the 120V shunt trip on the new breakers? Is the contractor responsible for additional wiring to enable EPO or other reasons for shunt trip? If so, please provide additional information regarding size and routing for shunt

circuit.

DISA Response:
The intent of the shunt trip signal wires is to provide future option of connecting to EPO if necessary. There is no EPO connection requirement noted in the SOW.
Solicitation
SOW 6.6.1
If the proposed 400A breaker trip unit contains a manufacturer built-in self-rest feature, is use of the

self-test sufficient to validate the secondary injection testing requirement?

DISA response:
Negative. Secondar testing can either be accomplished at the factory with supporting paperwork or in the field with the required test kit.
Solicitation
SOW 6.6.1
Dielectric breaker testing is typically reserved for

Medium voltage and High Voltage breakers. These breakers are being installed in a 208V switchboard.

DISA

Data

Center

Hawaii Solicitation

No:

HC102822R0040 RFP Questions August

26,

RFP Document
Document Section/Pg. No.
Question

Does DISA require dielectric testing on the (2) new 208V breakers?

DISA response:
Testing can be performed at the factory to ensure correct breaker rating.
Solicitation
SOW 6.6.2
Please clarify the end point of the Remote Distribution Cabinet feeds. No RDCs were identified in Room 189 during the site walk. New panels mounted on the wall were already fed. Where are

the new feeds intended to be landed in Room 189?

DISA response:
The feeders are intended to feed future DISA GFE. For length of feeders, please provide quote to reach further row of IT cabinets.
Solicitation
SOW 6.8.2
As discussed above, installed breakers are low voltage and are typically not NETA tested. Does DISA require a certified NETA testing agency to perform the testing, or can contractor self-perform,

given the simplicity of the tests required.

DISA response:
Testing required for all 480 – 600V breakers.
Solicitation
SOW 6.9.4
What is the “Cold-Aisle/Hot-Aisle” facility routing

standard? Are some conduit routing schemes prohibited?

DISA response:
All routing of underfloor conduit and circuits shall be done in established hot aisles.
Solicitation
SOW 6.9.5
Larger conductors are typically not available in full color jackets. This project includes 400A feeders, that may be of a cable size larger than that where colored jackets are available. Is colored tape acceptable in lieu of full-colored jacket for larger

wire sizes?

DISA response:
All attempts shall be made for colored jackets on conductors. Colored phase tape is acceptable.
Solicitation
SOW 6.9.8
Does DISA have any projections for any pending Periods of Non-Disruption during the anticipated

construction timeframe?

DISA response:
DISA does not have any projections for any PONDs at this time. DISA is a warfighter support organization which can require a POND as real-world activities dictate. All PONDs will be communicated when announced.
Solicitation
SOW 6.11.3
Please confirm that breakers, ATS, and other electrical distribution material required in this scope are not considered “equipment.” I.e., does the contractor need manufacturer certified technicians

for this scope?

DISA response:
Material supported for this scope is considered DISA equipment and thus requires certified technicians for any start up or testing as manufacturer requires.
Solicitation
SOW Section 11
Please confirm that escorts are provided by the

government at no cost to contractor. Is there a limit to number of installers per escort? If installers have a security clearance, are escorts required?

DISA response:
DISA will provide escorts for all areas needing access for this project.
Solicitation
General
Does DISA have a preference (when an option

exists) for overhead or underfloor conduit routing?

DISA response:
Preference is always under raised floor. If in other areas of the building, conduit can be routed above false ceiling. Absolutely no exterior routing of conduit is allowed for this scope of work.
Solicitation
General
Does DISA have a site laydown area available for

tools, conduit, etc.?

DISA response:
There is very little room for laydown of material. The enclosed generator yard can be used for material laydown as long as access is maintained for all equipment and approved by the site facilities manager.
Solicitation
General
During the walk through, a set of Master As-builts, dated 6/10/21 was located in printed copy. Will DISA provide a PDF version to the winning

contractor?

DISA response:
Yes. Drawings can be provided in pdf.