Revised Solicitation Q and A Round 2 Date 4.12.21.xlsx
XLSX spreadsheet 85 KB Posted
- Attached to
- Raised Floor Upgrade Federal contract opportunity
- Solicitation number
- HC102821R0012
- Issued by
- Defense Information Systems Agency
About this file
This document contains a question and answer file related to a federal solicitation for a raised floor upgrade project. Key details include: the solicitation number and name, which involves upgrading raised access floors in computer rooms to meet 2,500 pound static and 2,000 pound rolling load capacities. Work includes replacing all access floor panels with concrete core panels, upgrading the floor structure with new stringers, lifting existing racks, cleaning floors during replacement, and installing, connecting, testing and warranting equipment. The Defense Information Systems Agency is the contracting agency. Questions cover technical specifications, schedules, materials, and procedures. Answers provide clarification and approve or deny requests for specification changes.
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A Rd 1& 2 for Raised Floor
| Q&A Number | RFP Page | RFP Section/ Paragraph | Solicitation Amend # | CLIN/ Clause/ Appendix/ Attachment/ Other | Contractor Questions | Government Answer | Change Answer to: |
| 1 | 70-72 | 3 | 252.204-7019 NIST, 252.204-7020 & 252.204-7021 | Does the offeror need to currently hold a NIST and CMMC certificate? | No. This is not an IT or specialized service requirement so these clauses are not required. Amendment 03 to the solicitation removed these clauses. | ||
| 1 | 4, 5 | 3 | RFP Information Sheet under Past performance. | Will the government accept past performance from a subcontractor to be evaluated as acceptable or must the offeror hold the past performance? | Past performance information should only be provided for the prime contractor. The government will not evaluate subcontractor past performance. Also keep in mind that past performance is only evaluated on a pass/fail basis. | ||
| 2 | 10 | 6.2.1.1, 6.2.1.2 & 6.2.1.3 | 4 | PWS Task 2. RFP page 10 | Please give an accurate count of the existing equipment and confirm if the counts are to be used as a base line for units to be lifted. | Counts are already provided in the RFP within plus or minus 10% as this is an operating data center.. | |
| 2 | 4 | General Technical Question | Is there a trench plan available at CR1? | See drawing provided in response. | |||
| 2 | 4 | General Technical Question | If a trench plan is not available can you confirm the trenchs are all the same width throughout CR1? | See drawing provided in response. | |||
| 2 | 4 | General Technical Question | How many escorts will be assigned to the project? This will determine the amount of manpower used to mitigate project delays. | The government will provide adequate security escorts to meet all contract and site security requirements. Facility access is controlled and project phasing is required. | |||
| 2 | 4 | Preproposal Site Visit | Will DISA please provide the Vendor Sign In sheet for all site walk attendees? | The government will provide the site visit attendee list as part of the solicitation amendment on the beta.sam.gov website. | |||
| 2 | 4 | General Technical Question | Can the steel channel supporting the access floor over the trenches be supported with a mid-span steel pedestal? | Provide a shop drawing for review and approval to the COR. Maintenance access in the trench shall be maintained. | |||
| 2 | 4 | General Technical Question | Can the steel channel supporting the access floor over the trenches be supported with two evenly spaced pedestals? | Provide a shop drawing for review and approval to the COR. Maintenance access in the trench shall be maintained. | |||
| 2 | 4 | General Technical Question | Can the steel channel supporting the access floor over the trenches be replaced with tall seismic pedestals supplied by the access floor manufacturer? | Provide a shop drawing for review and approval to the COR. Maintenance access in the trench shall be maintained. | |||
| 2 | 7 | PWS .5.2 Task 2 | 4 | PWS Scope 5.2 Task 2 | The pedestals in CR 2B have been validated under a separate engineering study to meet criteria detailed in Appendix B. Our site inspection does not agree with the engineering study. The access floor in CR 2B is a wood core floor and the understructure does not have fillet welded pedestal heads required to meet the 2,500 Lb. load requirements. The access floor is a wood core panel and the understructure are not compatible with the Tate ConCore floor system. Please confirm that new understructure and stringers will be required | The existing pedestals utilize a screw connection flat top plate to receive the stringers, which meets the Concore 2500 requirements. See the attached engineering study that recommends reusign the existing pedestals nd stringers in CR2B. | |
| 2 | 4 | General Technical Question | To ensure continuity and not violate any warranties or service contracts in place, please advise us the contractor responsible for the maintenance and inspection of the fire suppression system and tanks. | Western States Fire Protection, |
141 Windy Meadows Dr, Schertz, TX 78154, Phone: (210) 967-4731 2 4 General Technical Question To ensure continuity and not violate any warranties or service contracts in place, please advise us the mechanical contractor responsible for the installation and maintenance of the IRC units. Pergravis®, LLC, 10012 North Dale Mabry Highway Suite 109, Tampa, FL 33618
| 2 | 4 | General Technical Question | CR 1, support of cable tray columns post floor replacement. Can we provide alternate means to anchor vertical supports? | Alternate means may be provided to be reviewed and approved by the COR. | |||
| 2 | 4 | General Technical Question | In Room CR 2B, should the existing wooden constructed ramp assemblies, rails and fascia be replaced as part of the project or should these components be incorporated into the replaced access floor? | Any wood shall be removed and replaced with a non-combustable material. See question and answer below. | |||
| 2 | 4 | General Technical Question | Will there be locations on site for dumpster, portable restroom, office trailer and if needed, storage unit? | Yes, please coordinate with the Site FM. | |||
| 2 | 10 | PWS 6.2.1.1 | 4 | PWS 6.2.1.1 | WDU; Chilled water distribution units are hard piped. The in row CRV units are hard piped. The specification states these devices need to remain operational throughout the replacement. These units will need to be disconnected from the chilled water loop to raise them in place. Will it be acceptable for temporary shutdown of the WDU and IRC only when the units are to be lifted? | Provide a shutdown plan to the COR for review and approval. Adequate cooling shall be maintained at all times. | |
| 2 | 10 | PWS 6.2.1.1 | PWS 6.2.1.1 | Trenches and support across trenches. Who is responsible for the structural engineering of the steel members and the mechanical attachment to the concrete that are to span the trenches? The access floor manufacturer does not offer any products or engineering services to address spanning the floor over trenches. Please advise what size of structural members to use and means of anchoring. | Provide 'u' channel that rests across the trench to be anchored by tapcon screws with 1-1/2" inbed to the COR for review and approval. | ||
| 2 | 10 | PWS 6.2.1.2 | 4 | PWS 6.2.1.2 | Trenches, same structural question as above. | Provide 'u' channel that rests across the trench to be anchored by tapcon screws with 1-1/2" inbed to the COR for review and approval. | |
| 2 | 11 | PWS 6.2.1.7 | 4 | PWS 6.2.1.7 | Perimeter edge stringers along the wall are not available from the manufacturer. Will the manufacturers’ engineered perimeter condition be acceptable? | Yes, manufacture's engineered perimeter pedestal supports are acceptable solution. | |
| 2 | 10 | PWS 6.2.1.4 | 4 | PWS 6.2.4.1 | 1/8” High Pressure Laminate: As of December 2020, Tate Access Floors has eliminated 1/8” HPL from their standard offering. Will 1/16” static dissipative high wear HPL be acceptable or will special production runs be required? | If it is proven that 1/8" HPL cannot be obtained, then the COR may approve a substitution during the material order process. | The PWS has been revised to permit the use of 1/16" standard HPL. |
| 2 | 11 | PWS 6.2.4.4 | 4 | PWS 6.2.4.4 | Spare parts. 10% of the solid panels would result in 28 skids of panels. Similar DISA projects have specified (4) solid panels for every 1,000 SF of access floor. Please confirm 10% spare stock is required? | 10% spare stoc is the requirement. The site may choose to locate the skids outside per their direction. | |
| 2 | 13 | PWS 6.2.11 | 4 | PWS 6.2.11 | Please provide size, quantity and MERV rating of all CRAH units and IRC units. | CR1 (Room 141) - Thirteen (13 ea) CRAHs, all 30 Tons,Minimum Efficiency Reporting Value (MERV) rating is unknown and not required for raised access floor replacement. |
CR1 (Rm 141) - Twenty four (24 ea) In-Row Coolers, all 10 Tons with two each Water Distribution Units.
CR2A (Room 143) - four (4 ea) CRAHs, all 30 Tons, MERV unknown.
CR2B (Room 142) - Four (4 ea) CRAHs, all 30 Tons, MERV unknown.
Master Floor Plan drawing provided to show locations.
| 2 | 13 | PWS 6.3.1 | 4 | PWS 6.3.1 | The existing SRG is supposed to be a bare copper 2’x2’ grounding grid. Per Appendix C the ground SRG ground conductors are to connect to a 4/0 perimeter grounding loop. Based on our site visit, the SRG conductors are NOT 2’x2’ but 4’x4’. No perimeter ground loop was located. | The SRG as installed is on a 4'x4" grid that shall remain. PWS Section 6.3.1 should have stated 4' x 4' grounding grid. Disregard Appendix C required 4/0 perimeter loop. The existing 2/0 perimeter ground loop shall remain as shown on Electrical Drawings E-109 through E-112. | |
| PWS changed to reflect the existing SRG per Appendix I. The existing SRG is a 4 x 4 grid with a 2/0 perimeter grounding loop. | |||||||
| 2 | 4 | SRG General Question | Per the PWS are we to remove and re-attach the SRG UL listed clamps, maintain the SRG and then test the SRG per Appendix C and E? | Yes. | |||
| 2 | 4 | SRG General Question | If the SRG is not installed per the Appendices, will the contractor be responsible to provide additional SRG conductors, UL Listed clamps, perimeter ground or new earth grounds? | Yes. | If the SRG is not installed per Appendix I and Appendix J; no, the contractor is not responsible. | ||
| 2 | 4 | SRG General Question | Will a grounding electrode plan or drawing be available? | Electrical Drawings are provided. see Drawings E-109 through E-117 show the existing site grounding location. | |||
| 2 | 4 | SRG General Question | Can we get a copy of the SRG AS BUILT drawings so we can understand the deficiencies in the existing system and determine what needs to be done to enhance the SRG? | Electrical Drawings are provided. see Drawings E-109 through E-117 show the existing site grounding location. There are no deficiencies. Existing SRG cabling to remain and shall be removed & reinstalled during access flooring replacement. | Please see Appendicews I and J. | ||
| 2 | 4 | SRG General Question | Can we get a copy of the facility electrical one line that would depict site grounding? | Electrical Drawings are provided. see Drawings E-109 through E-117 show the existing site grounding location. | |||
| 2 | 4 | SRG General Question | Can we get a copy of the grounding electrode plan that will identify facility ground and counterpoise locations? | Electrical Drawings are provided. see Drawings E-109 through E-117 show the existing site grounding location. | |||
| 2 | 4 | RFP page 4 | 4 | General Question | Is past performance included in the 20-page count for the Technical/Management Volume? | Since the past performance could be many pages, it is excluded from the count. | |
| 2 | 4 | RFP page 4 | 4 | General Question | Is the project schedule included in the 20 page count for the Technical/Management Volume? | Since the schedule could be many pages, it is excluded from the count. | |
| 2 | Gernal RFP | 4 | General Question | Should the completed and signed Standard Form 30's and 1449 be included in the proposal? | Yes. Not sure there is a specific volume. | ||
| 2 | Appendix B 3.4 | 4 | Appendix B 3.4 Cleaning and Protection | Typically, during the completion phase of the project, there are two standard ISO 14644-8 types of cleanings that take place inside a critical space. The day-to-day ISO 14644-8 cleanings for the subfloor has already been established as a requirement. Will there be a final ISO 14644-8 deep cleaning for the above floor and raised surface? | If a new raised floor is provided clean then made dirty by the contractor's efforts by project end, then yes the raised floor would need to be deep cleaned. | ||
| 2 | Appendix B 3.4 | 4 | Appendix B 3.4 Cleaning and Protection | For the resealing of the subfloor surface, is it for just the areas that have been patched or is it for all the areas that have not been sealed? | All areas that have not been sealed. | ||
| 2 | PWS Section 6.2 | 4 | PWS Section 6.2 | Will any cutting of floor panels be allowed in and around the dock area? If not, is there a distance away from the building that must be maintained for this process? | Cutting is allowed on outside dock and adjacent to the facility next to the dock. | ||
| 2 | PWS Section 6.2 | 4 | PWS Section 6.2 | Do the ramps in Room CR2B need to be replaced to support the same load as the new access floor panels? | Yes, the existing ramps must meet the same load characteristics as the raised floor. The ramps need to be replaced to match the same load characteristics. | ||
| 2 | Gernal RFP | 4 | General RFP | Are there any "black out" dates that we would not be able to work? If so, please identify them? | There may be "black out" dates, but they are unknown at this time. Access to the rooms under this scope has not been an issue in the past. | ||
| 2 | General RFP | 4 | General RFP | How long does it take to get someone approved to be added to our crew as the need for additional help arises? | A minimum of 24 hours is required for DISA San Antonio security review. Only U.S. citizens are allowed into the facility. | ||
| 2 | PWS Section 6.2 | 4 | PWS Section 6.2 | Is the existing railing by the ramps sufficient or does it need to be replaced? | Reusing the existing railing is acceptable as long as its safely reattached/supported. | ||
| 2 | PWS Section 6.2 | 4 | PWS Section 6.2 | The specification calls for 1/8" think HPL…Is 1/16" HPL Nevamar Gray Starlite acceptable for the access floor panel finish if we can't get the 1/8" HPL? | If it is proven that 1/8" HPL cannot be obtained, then the COR may approve a substitution during the material order process. | The PWS has been revised to permit the use of 1/16" standard HPL. | |
| 2 | General RFP | 4 | General RFP Comment | Recommendation for addition to RFP. Based on experience, we recommend the awarded contractor test the ground system prior to starting the disconnect of the system. This step is performed to ensure the grounding is working properly prior to the contractor touching the system. | The requirement is to provide the Government a working system as specified in the RFP at the end of the project, thus if the contractor wants to test the system prior to removal, they are allowed to. |
SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104 FOR OFFICIAL USE ONLY