FY27 CDBG Street Resurfacing and ADA Improvement Project
This document contains Special Provisions for the City of Pasadena's FY27 CDBG Street Resurfacing and ADA Improvement Project, which supplements the Standard Specifications for Public Works Construction, 2024 Edition. The project involves resurfacing Fair Oaks Avenue from Washington Boulevard to Mountain Street and Los Robles Avenue from Washington Boulevard to Orange Grove Boulevard, with potential improvements including removal and reconstruction of damaged concrete curb, gutter, sidewalk, curb ramps, driveway aprons, and cross gutters; adjustment of utility manholes; replacement of traffic signal loop detectors; installation of raised pavement markers; and miscellaneous appurtenant work. The base contract duration is 40 working days, with the City reserving the right to delete bid items, revise quantities, or take other permitted actions prior to contract award based on received bids and available funds.
The contract will be awarded to the responsive and responsible bidder submitting the lowest and best bid, with mobilization and demobilization costs considered incidental to the work and included in the prices bid for various bid items. Key requirements include submission of an engineered Traffic Control Plan signed and sealed by a registered engineer, preparation and implementation of a Best Management Practices (BMP) Plan for storm water and non-storm water pollution control, and compliance with Pasadena Municipal Code Section 9.36.070 governing work hours and restrictions. The Contractor must provide traffic control devices including up to four Changeable Message Signs, notify affected transit agencies at least one week in advance of any service disruptions, coordinate with school districts for work scheduling within school zones with specific time restrictions (7:00 a.m. to 9:00 a.m. and 2:00 p.m. to 4:00 p.m. on weekdays), and notify affected residents and businesses at least one week prior to construction. The project is partially funded with federal Community Development Block Grant (CDBG) Program funds. Special provisions include detailed specifications for Asphalt Rubber Hot Mix (ARHM) with crumb rubber manufactured in California, crack sealing requirements, field density testing with specific compaction tolerances, and liquidated damages of $1,200 per day for missed transit notifications and $250 per transition per day for failure to maintain temporary pavement transitions.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP 1
Department of Public Works
Special Provisions
Project Name: FY27 CDBG Street Resurfacing and ADA Improvement
Project Manager: Tiffiny Chen
The following Special Provisions supplement and amend the Standard Specifications for Public Works Construction, 2024 Edition. As a reference convenience, these Special Provisions have been arranged into a format which parallels the Standard Specifications
SP 2
TABLE OF CONTENTS
SPECIAL PROVISIONS
PART 1 – GENERAL PROVISIONS
SECTION 1- GENERAL, TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE,
AND SYMBOLS
SUBSECTION 1-7 AWARD AND EXECUTION OF CONTRACT
SECTION 2 – SCOPE OF THE WORK
SUBSECTION 2-5 THE CONTRACTOR’S EQUIPMENT AND FACILITIES
2-11 WORK ZONE RESTRICTIONS AND COMMUNITY COORDINATION
SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK
SUBSECTION 6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK
SECTION 7 – MEASUREMENT AND PAYMENT
SUBSECTION 7-3 PAYMENT
PART 3 – CONSTRUCTION METHODS
SECTION 300 – EARTHWORK
SUBSECTION 300-1 CLEARING AND GRUBBING
SECTION 302 – ROADWAY SURFACING
SUBSECTION 302-5 ASPHALT CONCRETE PAVEMENT
SUBSECTION 302-17 CRACK SEALING
SUBSECTION 302-18 FIBER REINFORCED ASPHALT CONCRETE (not applicable)
PART 6 TEMPORRAY TRAFFIC CONTROL
SECTION 601 – TEMPORARY TRAFFIC CONTROL FOR CONSTRUCTION AND
MAITNENANCE WORK ZONES
SUBSECTION 601-1 GENERAL
SUBSECTION 601-2 TEMPORARY TRAFFIC CONTROL PLAN (TCP)
SUBSECTION 601-3 TEMPORARY TRAFFIC CONTROL (TTC) ZONE DEVICES
SUBSECTION 601-4 TEMPORARY TRAFFIC STRIPING AND PAVEMENT MARKINGS
BID ITEMS
Traffic Control Plan & Implementation
Storm Water Pollution Prevention – Best Management Practices (BMP) Plan & Implementation
Asphalt Rubber Hot Mix (ARHM)
SP 3
Fiber Reinforced Asphalt Concrete (FR-ARHM-GG-C)
Asphalt Leveling Course
Cold Mill Header Cut & Transitions
Digout or Remove and Replace 4" AC
Portland Concrete Cement (PCC) Curb and Gutter
PCC Access Ramp, Sidewalk, Driveway Apron and Cross Gutter
Remove & Replace Curb/Parkway Drain
Utility Adjustments
Remove And Install Traffic Loops
Survey Monuments, Centerline (Cl) Ties & Benchmarks
Thermoplastic Striping And Pavement Markings And Signs
SP 4
SPECIAL PROVISIONS
PART 1 – GENERAL PROVISIONS
SECTION 1- GENERAL, TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF
MEASURE, AND SYMBOLS
SUBSECTION 1-7 AWARD AND EXECUTION OF CONTRACT
Add to Subdivision 1-7.1 General:
Based on the bids received and the funds available at the time of award, the City may, at its sole discretion, delete bid items, revise quantities, or take any action permitted by law prior to contract award.
BASE BID: FY27 CDBG STREET RESURFACING AND ADA IMPROVEMENT
Number of Working Days: 40 Days
Unless otherwise specified in the Contract Documents, the Contract will be awarded to the responsive and responsible bidder submitting the lowest and best bid, as determined by the City.
Where Additive Alternate bid items are included in the Bid Schedule, the lowest bid shall be determined based upon the total bid price consisting of the Base Bid together with all
Additive Alternate bid items.
Following determination of the lowest and best bid, the City reserves the right to award the
Contract based upon the Base Bid and any combination of Additive Alternate bid items, as determined to be in the best interest of the City.
The City further reserves the right to incorporate any Additive Alternate item(s) into the Work by
Contract Change Order at any time prior to the last Contract Working Day. Prices bid for Additive
Alternate items shall remain firm for the duration of the Contract, and no additional compensation shall be allowed beyond the amounts identified in the Contractor’s bid proposal.
SECTION 2 – SCOPE OF THE WORK
SUBSECTION 2-5 THE CONTRACTOR’S EQUIPMENT AND FACILITIES
Subdivision 2-5.4 shall be revised to address Haul Routes & Staging Areas:
The Contractor shall comply with Pasadena Municipal Code (PMC) 9.36.070 – Construction
Projects, which governs work hours and related restrictions. In addition, the Contractor shall refer to the following traffic map:
• Construction Staging and Traffic Management Plan – Truck Routes
All haul routes and staging areas for the work shall be submitted to the City for approval. Staging
SP 5
areas within the City’s public right of way will require a permit.
Contractor-owned equipment and employees’ personal vehicles shall not be parked on the traveled way or on any street with restricted traffic at any time. If construction equipment is parked overnight in designated parking lanes, the Contractor shall install barricades and other appropriate warning devices.
Add to Section 2 the following Subsection:
2-11 WORK ZONE RESTRICTIONS AND COMMUNITY COORDINATION
2-11.1 SCHOOL ZONES
The Contractor shall schedule all work within school zones during summer, winter, or spring recess whenever possible. This requirement applies to any work within 1,000 feet of a school, on roadways leading directly to a school, or on streets adjacent to a school.
The Contractor shall:
• Notify the appropriate school district and coordinate activities to maximize safety and minimize inconvenience.
• Provide the City Project Manager with copies of correspondence and notifications for each affected school.
• Whenever feasible, schedule work after schools have closed for the summer session.
Restrictions:
Work within school zones is prohibited from 7:00 a.m. to 9:00 a.m. and 2:00 p.m. to 4:00 p.m.
on weekdays when school is in session.
No work shall occur in school zones during the first week of school.
The Contractor must coordinate with the designated school districts at least one week prior to any planned street closures or openings.
2-11.2 TRANSIT ROUTE
The Contractor shall maintain complete access to all transit locations throughout construction. If full access cannot be provided, no more than two (2) consecutive bus stops on the same side of the street may be closed at the same time.
When transit stop locations are expected to be inaccessible due to construction activities, the
Contractor shall notify the affected transit agencies at least one week in advance. Notifications must be sent via email to the agencies listed below. The City Project Manager shall be included
SP 6
on all email correspondences.
METRO
1. Mattie Jones, 213-922-5023, JONESM@metro.net
2. David Daniels, danielsd@metro.net
3. Francisca Montes-Jurado, MontesjuradoF@metro.net
4. Events Desk, eventsdesk@metro.net
Pasadena Transit
General email at transit@cityofpasadena.net and:
1. Sebastian Hernandez, 626-744-7661, shernandez@cityofpasadena.net
2. Britt Card, 626-744-7682, bcard@cityofpasadena.net
3. Valerie Gibson, 626-744-7452, vgibson@cityofpasadena.net
Foothill Transit
1. Henry Lopez, 626-931-7225, hlopez@foothilltransit.org
2. Josh Landis, 626-931-7224, jlandis@foothilltransit.org
LADOT
1. Janna Smith, 213-972-5098, janna.smith@lacity.org
2. Yanna Loewy, yanna.loewy@lacity.org
The City will subject the Contractor to liquidated damages in the amount of $1,200 per day for each missed notification.
2-11.3 NOTIFICATION OF AFFECTED RESIDENTS/BUSINESSES
The City will provide the Contractor with a sample notification letter. The Contractor shall be responsible for preparing the project-specific notification and for distributing the general information letter to all affected residents and businesses.
The notification letter and any supplemental notices shall be submitted to the City for review and approval at least one week prior to mobilization. No work on any street shall begin until the required notifications have been approved and distributed.
Notification shall be provided to affected residents and businesses no less than one week in advance of construction. The Contractor shall make a good faith effort to personally contact the tenant(s) of abutting properties and hand-deliver the notice. Leaving the notice at a doorway, gate, or fence is permitted only after multiple unsuccessful contact attempts.
When hand delivery is not possible, the Contractor shall provide the City Project Manager with a log of addresses and the date and time of each attempted contact.
mailto:JONESM@metro.net mailto:danielsd@metro.net mailto:MontesjuradoF@metro.net mailto:eventsdesk@metro.net mailto:transit@cityofpasadena.net mailto:shernandez@cityofpasadena.net mailto:bcard@cityofpasadena.net mailto:vgibson@cityofpasadena.net mailto:hlopez@foothilltransit.org mailto:jlandis@foothilltransit.org mailto:janna.smith@lacity.org mailto:yanna.loewy@lacity.org
SP 7
Failure to strictly comply with these notification requirements may result in the City Project
Manager suspending the work without time extension until the issue is resolved.
Additional notification to the affected businesses and residents shall be prepared by the City and distributed by the Contractor for driveway closures five working days in advance of the work.
No removal work is allowed until the additional notification has been distributed to the affected residents and businesses. In the event there is a disconnect in coordination for driveway accessibility, the Contractor shall be responsible for providing steel plates for immediate driveway accessibility, as required by business and residents.
SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK
SUBSECTION 6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK
Add to Subdivision 6-1.1 Construction Schedule:
The Contractor shall provide the City Project Manager and City Inspector with at least three (3) business days’ notice of any changes to the approved baseline schedule or monthly schedule update prior to commencing work on a street not previously scheduled.
SECTION 7 – MEASUREMENT AND PAYMENT
SUBSECTION 7-3 PAYMENT
Add to Subdivision 7-3.4 Mobilization and Demobilization:
Mobilization and demobilization costs shall be considered incidental to the Work and included in the prices bid for the various bid items. Such costs shall include, but are not limited to: preparation and implementation of project phasing; monthly project schedule submittals; staging and detour plans; Construction and Demolition (C&D) administrative fees and deposits; all required insurance and bonds; shop drawing preparation and submittals; a construction trailer for weekly project meetings; a full-time, on-site superintendent; temporary pedestrian and vehicular access; and coordination with other ongoing construction activities.
This shall be considered full compensation for the foregoing, and no additional compensation will be allowed.
SP 8
PART 3 – CONSTRUCTION METHODS
SECTION 300 – EARTHWORK
SUBSECTION 300-1 CLEARING AND GRUBBING
Add to Subdivision 300-1.2 Root Pruning and Tree Trimming:
Tree trimming shall be performed solely to provide clearance for equipment on overhanging branches and must be approved by the City’s Arborist.
Root Pruning Guidelines:
• Root pruning may only be performed on one side of a tree once every two years.
• Severing roots larger than 2 inches in diameter requires prior approval from the Forestry
Inspector.
• All pruning cuts must be clean, with no shredded edges, and made using an appropriate cutting tool (e.g., axe).
• Root pruning or shaving into the base of the trunk is strictly prohibited.
• Heavy equipment shall not be used to remove or pull roots.
• Do not operate or drive heavy equipment within the root zone (defined as the area beneath the tree canopy).
• Shaving to reduce the diameter of large roots is recommended over severing.
• If the Forestry Inspector’s presence is required onsite to identify roots for pruning, roots should be exposed beforehand. Marking paint will be used to indicate where a root may be severed.
Notification Requirement:
The Contractor shall notify the City Inspector, as well as Kenny Graham at (626) 744-3880 or
Kgraham@cityofpasadena.net, or Darnell Bailey at darnellbailey@cityofpasadena.net prior to performing any selective root pruning.
The cost of tree trimming and root pruning shall be included in the prices bid for other related items; no additional compensation will be allowed.
SECTION 302 – ROADWAY SURFACING
SUBSECTION 302-5 ASPHALT CONCRETE PAVEMENT
The third paragraph of Paragraph 302-5.9.2 Joints shall be modified to read as follows:
mailto:Kgraham@cityofpasadena.net mailto:darnellbailey@cityofpasadena.net
SP 9
The Contractor shall construct temporary pavement transitions at all paving joints greater than one inch (1") prior to opening the paved surface to traffic. This requirement shall apply to both longitudinal and transverse joints for leveling and surface courses.
Temporary pavement transitions shall have a maximum slope of twenty to one (20:1), unless otherwise approved by the Project Manager, and shall be constructed over Kraft paper or another approved bond breaker such that removal of the temporary transition leaves a clean pavement notch. Temporary transitions may be constructed using either cold mix or hot mix asphalt. Temporary transitions shall be removed prior to placement of subsequent pavement surfaces.
The Contractor shall continuously maintain all temporary pavement transitions until final paving operations are completed. Each temporary transition shall be inspected daily by the Contractor, including weekends and holidays, and repaired as necessary to maintain safe conditions and compliance with these provisions.
Failure to comply with these requirements may result in liquidated damages in the amount of
Two Hundred Fifty Dollars ($250) per transition, per day, or the actual cost incurred by the City to perform corrective work, whichever is greater. Assessment of liquidated damages shall not relieve the Contractor from responsibility for third-party claims or damages resulting from failure to maintain safe pavement conditions.
Full compensation for furnishing, constructing, maintaining, repairing, and removing temporary pavement transitions shall be considered as included in the various items of Work and no additional compensation shall be allowed therefor.
Add to Section 302 the following Subsection 302-17 Crack Sealing:
SUBSECTION 302-17 CRACK SEALING
GENERAL
This work consists of routing, cleaning, and sealing cracks in existing asphalt concrete and/or portland cement concrete pavement surfaces as shown on the Plans or as directed by the City
Project Manager.
Crack sealing is intended to prevent the intrusion of water and incompressible materials into the pavement structure.
MATERIALS
Crack sealant shall be a hot-applied, rubberized asphalt joint sealant conforming to ASTM
D3405, Grade as recommended by the manufacturer for the ambient pavement temperature
SP 10
range at time of installation.
Sealant shall be supplied by the manufacturer in original containers clearly labeled with:
• Product name
• Lot/batch number
• Manufacturer’s recommended heating and application temperatures
• Date of manufacture
Backer rod, when required, shall be closed-cell polyethylene foam, compatible with the sealant.
SURFACE PREPARATION
Cracks to be sealed shall be routed to a uniform rectangular reservoir unless otherwise approved by the City Project Manager.
Typical routing dimensions:
• Minimum width: ½ inch
• Minimum depth: ½ inch
All cracks shall be thoroughly cleaned by:
1. Mechanical brushing
2. Blowing with oil-free compressed air
3. Hot-air lance (if moisture or debris remains)
Cracks shall be clean, dry, and free of dust, vegetation, and loose material prior to sealing.
PLACEMENT
Sealant shall be heated and installed in strict accordance with the manufacturer’s recommendations.Sealant shall be placed using a pressure-fed wand or pour pot and shall fill the routed crack from the bottom up, without trapping air. The sealant shall be slightly crowned or flush with the pavement surface and shall not be overfilled. Excess material shall be removed from the pavement surface immediately.
Crack sealing shall not be performed when:
• Pavement temperature is below 40°F, or
• Pavement is wet, or
• Rain is imminent.
Sealed cracks shall be protected from traffic until the sealant has cooled and set sufficiently to prevent tracking.
Any spilled or smeared material on the pavement surface shall be removed immediately.
MEASUREMENT
Crack sealing will be measured by the linear foot of crack sealed, regardless of width or depth, SP 11 unless otherwise specified.
PAYMENT
Payment for “Crack Sealing” shall constitute full compensation for furnishing all labor, materials, tools, equipment, and incidentals necessary to comply with the requirements of the project plans, specifications, special provisions, and contract documents. No additional compensation shall be allowed therefor.
Add to Section 302 the following Subsection 302-18 Fiber Reinforced Asphalt Concrete:
SUBSECTION 302-18 FIBER REINFORCED ASPHALT CONCRETE (not applicable)
SP 12
PART 6 TEMPORRAY TRAFFIC CONTROL
SECTION 601 – TEMPORARY TRAFFIC CONTROL FOR CONSTRUCTION AND
MAITNENANCE WORK ZONES
SUBSECTION 601-1 GENERAL
Add to Subsection 601-1 General:
The Contractor shall comply with Pasadena Municipal Code (PMC) 9.36.070 – Construction
Projects, which governs work hours and related restrictions. In addition, the Contractor shall refer to the following traffic map:
• Traffic Control Lane Closure Map
If a conflict arises between the PMC requirements and the work hours indicated on these maps/plans, the work hours specified in the maps/plans shall take precedence.
Link: https://www.cityofpasadena.net/public-works/engineering-and-construction/public-works-permitting/
SUBSECTION 601-2 TEMPORARY TRAFFIC CONTROL PLAN (TCP)
Add to Subdivision 601-2.1 General:
Traffic control shall comply with the latest CA MUTCD, Section 601 of the Greenbook 2024, and the City of Pasadena Recurring Supplements.
An engineered traffic control plan, signed and sealed by a registered engineer, must be submitted for approval. The plan shall include detailed information on all required barricades, flaggers, signage, tapers, and traffic routing for the work area, based on the Contractor’s means and methods.
If construction is phased, the traffic control plan shall clearly depict each phase. Minor field adjustments to phased limits may be made by the Contractor; however, the Contractor assumes full liability for any field modifications.
The traffic control plan shall ensure safe traffic operations 24 hours per day, seven days per week for the duration of the work. All traffic deviations and detours must be reviewed and approved by the City Traffic Engineer and coordinated with Police, Fire, and Transit authorities at least one week prior to implementation.
Traffic shall be permitted to pass through the work site unless otherwise specified in the approved temporary traffic control plan and authorized by the City Project Manager. The Contractor must https://www.cityofpasadena.net/public-works/engineering-and-construction/public-works-permitting/ https://www.cityofpasadena.net/public-works/engineering-and-construction/public-works-permitting/
SP 13
maintain safe passage for vehicles and pedestrians at all times, ensuring a minimum of one lane of traffic in each direction unless an alternative arrangement is explicitly approved. Any partial or full closure of a street requires prior approval from the City Traffic Engineer and Project Manager and must be reflected in the approved traffic control plan.
The Contractor is responsible for obtaining all necessary permits from other agencies as required for occupation or implementation of temporary traffic control within other agency jurisdictions.
Permit fees shall be reimbursed by the City at actual cost, with no additional mark-up.
Add to Subdivision 601-2.2 Payment:
Full compensation for the temporary traffic control plan and notifications shall be made at the lump sum (LS) contract price bid for “Traffic Control” and shall constitute complete compensation for furnishing all labor, materials, tool and equipment for complying with the requirements of the project plans, specifications, special provisions, and contract documents.
SUBSECTION 601-3 TEMPORARY TRAFFIC CONTROL (TTC) ZONE DEVICES
Add to Subdivision 601-3.5 Signs and Signage:
When work is performed through an intersection and a cross street must be temporarily closed, the Contractor shall install a detour sign on the affected cross street. Advance signage shall also be provided indicating the closure. All signage shall be subject to review and approval by the City
Project Manager/Inspector.
Add to Paragraph 601-3.7.5 Portable Changeable Message Signs (PCMS):
For the duration of the contract, the Contractor shall supply up to four (4) Changeable Message
Signs (CMS) at all times, to be placed at locations designated by the City Project
Manager/Inspector. CMS units shall be positioned on streets scheduled for resurfacing as directed by the City Project Manager/City Inspector and installed no less than seven (7) days prior to the start of any work under this contract.
In addition, the Contractor shall maintain two (2) extra CMS units on standby for use during schedule changes. All CMS messages shall be promptly corrected upon discovery of any error and must be updated no later than the end of the day on which the error is identified.
Reiterate Paragraph 601-3.7.9 Payment:
No separate or additional payment will be made for traffic sign enhancement devices, such as flags, high-level warning devices, warning lights, PCMS, and flashing directional bars. Payment
SP 14
will be included in the contract unit price or lump sum price in the Bid for bid item “Traffic
Control”.
SUBSECTION 601-4 TEMPORARY TRAFFIC STRIPING AND PAVEMENT MARKINGS
Add to Subdivision 601-4.1 General:
Where existing delineation is obscured, damaged, removed, or reflectivity reduced; or where detours or temporary traffic lanes have been created through the construction zone, the
Contractor shall place and maintain temporary delineation until permanent striping is placed.
Add to Subdivision 601-4.5 Payment:
No separate or additional payment will be made for temporary traffic striping and pavement markings. Payment will be included in the contract unit price or lump sum price in the Bid for bid item “Traffic Control”.
SP 15
BID ITEMS
Traffic Control Plan & Implementation
The work includes preparing and implementing a Traffic Control Plan, as well as providing any ancillary temporary traffic measures necessary to perform the work in accordance with the project plans, specifications, special provisions, and contract documents.
Storm Water Pollution Prevention – Best Management Practices (BMP) Plan & Implementation
GENERAL
The work includes preparing a Best Management Practices (BMP) Plan, obtaining approval prior to mobilization, amending as necessary, and implementing BMPs for storm water and non-storm water pollution control in accordance with the City’s Building and Safety Best Management
Practice requirements, these Special Provisions, the project plans, specifications, and contract documents. This includes all activities related to BMP inspection, reporting, maintenance, personnel training, and all incidentals. BMPs shall incorporate methods and materials to ensure safety and environmental protection throughout construction, as well as any additional measures the City Project Manager deems appropriate.
Building and Safety BMP
Link: https://www.cityofpasadena.net/planning/building-and-safety/bs-applications-forms/#informational-handouts
In addition to complying with all applicable federal, state, and local laws and regulations, the
Contractor shall adhere to National Pollutant Discharge Elimination System (NPDES) requirements. The Contractor shall take all necessary precautions and implement BMPs to prevent discharges into the storm drain system, including pollutants from activities such as paving operations, concrete washouts, cold milling, and vehicle/equipment fueling.
Submission of a BMP Plan shall include the following certification:
“I certify that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to ensure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, to the best of my knowledge and belief, the information submitted is true, accurate, and complete. I am aware that https://www.cityofpasadena.net/planning/building-and-safety/bs-applications-forms/%23informational-handouts https://www.cityofpasadena.net/planning/building-and-safety/bs-applications-forms/%23informational-handouts
SP 16
submitting false and/or inaccurate information, failing to update the plans to reflect current conditions, or failing to properly and/or adequately implement BMP’s may result in revocation of grading and/or other permits or other sanctions provided by law.”
PAYMENT
Full compensation for this Work shall be made at the lump sum (LS) contract price bid for “Storm
Water Pollution Prevention – Best Management Practices (BMP) Plan & Implementation” and shall constitute complete compensation for furnishing all labor, materials, tool and equipment for complying with the requirements of the project plans, specifications, special provisions, and contract documents.
Asphalt Rubber Hot Mix (ARHM)
Asphalt-rubber hot mix shall conform to the specifications of 203-11 of the Standard
Specifications, Asphalt Rubber Hot Mix (ARHM). Placement of ARHM shall conform to Section
302-9 of the Standard Specifications except as modified herein.
MATERIALS
Asphalt-Rubber Binder
The binder to be mixed with the aggregate shall conform to Section 203-11 of the Standard
Specifications. The asphalt binder base stock prior to blending shall be PG 64-16.
ARHM Mixtures
The ARHM mixture shall be ARHM-GG-C and shall comply with Section 203-11.3 “Composition and Grading” of the standard specifications with the following exception:
1. Air Voids % Calif. Test 367 target and be produced in the range of 2.5 to 5.5.
2. For design and production Hveem stability shall be a 23 min.
3. VMA for design and production shall be between 18.0% and 23.0%.
The crumb rubber used on the project must originate and be manufactured in California.
Asphalt rubber binder shall utilize both scrap tire and natural rubber and shall comply with the requirements set forth in 203-11 of the Standard Specifications.
LAYOUT
The Contractor shall lay out and mark the limits of each paving pass for the surface course to conform to the approved lane line configuration. The layout shall be completed a minimum of twenty-four (24) hours prior to paving and shall be submitted to the City Inspector for approval before any paving begins.
SP 17
Where existing striping is to remain unchanged, the edges of the paving passes shall conform to the existing lane edges.
Where practicable, each travel lane shall be paved in a single continuous pass. In tapered transition areas, the shoulder shall be paved first, followed immediately by the adjacent through lane using a hot lap.
For paving operations that introduce new quarter points or grade breaks due to key cuts or other conditions, the Contractor shall provide equipment capable of adjusting to the revised surface profile at the required locations. Profile transitions shall be made within twelve (12) inches of the actual quarter point or grade break.
The Contractor shall take sufficient measurements during placement to verify that the full design asphalt concrete thickness is achieved at all quarter points, grade breaks, and transition areas.
Failure to provide the required thickness at any of these locations shall be cause for rejection of the work.
Corrective work for rejected areas shall include milling and removal of the new asphalt concrete from the roadway edge to the centerline or nearest interior lane line, as directed by the City
Project Manager, and repaving to the specified grade and thickness. The minimum length of any corrected area shall be fifty (50) feet.
TOLERANCES
The finished asphalt concrete surface shall be flush with, or up to one-quarter inch (0.02 feet) (6
mm) above, the gutter lip. In no case shall the finished pavement surface be lower than the gutter lip.
The average pavement thickness shall be equal to the thickness specified for the project.
For total pavement thicknesses less than four (4) inches, the minimum allowable thickness at any point shall be no more than one-quarter inch (1/4") less than the specified thickness.
For total pavement thicknesses of four (4) inches or greater, the minimum allowable thickness at any point shall be no more than one-half inch (1/2") less than the specified thickness.
Surface smoothness shall be verified using a twelve-foot (12') straightedge placed parallel to the centerline. Deviations in excess of the tolerances permitted by the contract documents shall be corrected at the Contractor’s expense.
PAVING MACHINES
Paragraph 302-5.4.5 Paving Machines of the Standard Specifications shall be supplemented as follows:
The Contractor shall utilize an Asphalt Material Transfer Vehicle (AMTV), also known as a
“Shuttle Buggy,” during placement of all asphalt concrete finish course materials on Arterial
SP 18
Streets.
The ski shall be constructed and installed to maintain a reference to the average elevation of the existing pavement along the length of the ski at the sensor point.
When placing surfacing adjacent to previously laid pavement constructed in accordance with these provisions, a joint-matching shoe of adequate size and type may be used in lieu of a 30-foot ski to properly sense the grade of the existing mat.
The ski shall be mounted to provide an accurate reference for the surfacing being placed, which may require positioning the ski ahead of and inside the outer limits of the screed. Automatic cross-slope control may be achieved using a ski and grade sensor on each side of the paving machine.
Automatic screed controls shall be installed so that occasional manual adjustments necessary to maintain the screed attitude parallel to the underlying pavement are readily accomplished.
The installation shall allow the automatic controls to be quickly disengaged, enabling the screed to be operated manually with minimal delay.
If the automatic screed controls fail to operate properly during any day’s work, the Contractor may manually control the spreading equipment for the remainder of that day, provided the work meets the quality requirements of Section 39-2 of the 2025 Caltrans Standard Specifications
(Unrevised).
If the methods and equipment used for automatic control do not achieve the required quality, paving operations shall be temporarily discontinued. The Contractor shall then make the necessary modifications to the equipment, or furnish alternative equipment conforming to these requirements, before resuming paving.
If the City Project Manager/Inspector determines that the existing grade or cross slope is too irregular for the automatic controls to achieve the specified quality, the Contractor shall discontinue use of automatic controls and adjust the spreading equipment manually. Automatic control may resume only when the City Project Manager provides such direction.
PLACEMENT
Paragraph 302-5.9.1 General of the Standard Specifications shall be revised to stipulate that asphalt concrete shall not be placed unless the atmospheric temperature is at least 55 degrees
Fahrenheit and rising.
Paving operations shall be scheduled and performed so that no unfinished longitudinal paving joints remain at the end of each day’s work. Where longitudinal joints are required, they shall be of the wedge type and constructed in accordance with the plan details. A proposed longitudinal joint layout shall be submitted to the City Project Manager for approval and reviewed during the
SP 19
pre-paving meeting.
ROLLING
Subsection 302-5.10, paragraph five of the Standard Specifications shall be revised to stipulate as follows :the number of rollers required for each paving operation shall be such that all rolling for density can be completed before the temperature of the asphalt concrete mixture drops below
140 degrees Fahrenheit.
Breakdown rolling shall commence immediately after asphalt concrete placement, except in cases where mix distortion or shoving occurs rather than compaction. In such instances, the Contractor shall allow the mix to cool sufficiently before proceeding with rolling. All rolling shall be performed with the drive wheel forward, and the advance and return passes shall follow the same line.
For leveling courses less than one inch (1") thick using D2 asphalt concrete, breakdown rolling shall consist of:
1. Three coverages with an 8 to 12-ton pneumatic roller
2. One finishing coverage with a steel wheel roller
Rolling may begin with a single pass of a steel wheel roller to allow the pneumatic roller sufficient time to warm up, avoiding tracking or picking up material from the mat. Pneumatic roller tires shall be treated with a non-petroleum-based product to prevent material pickup.
Failure to achieve effective breakdown rolling with the pneumatic roller after a reasonable warm-up period shall constitute cause to temporarily suspend paving operations until the Contractor can provide equipment capable of performing without pickup.
For all other leveling courses, the intermediate roller shall be a 12-16 ton pneumatic roller.
COMPACTION
The Contractor shall have hand-compaction equipment immediately available to compact all areas inaccessible to rollers. Hand-compaction shall be performed concurrently with breakdown rolling. If, for any reason, hand-compaction falls behind breakdown rolling, further placement of asphalt concrete shall be suspended until hand-compaction catches up. Acceptable hand-compaction equipment includes vibraplates and hand tampers, and hand torches shall be available for rework of areas that have cooled.
After compaction, the surface texture of all hand-worked areas shall match the surface texture of the machine-placed mat. Any thin courses, segregation, or other surface irregularities shall be corrected immediately upon discovery. Failure to promptly address these areas shall result in suspension of asphalt concrete placement until the areas are satisfactorily corrected, unless otherwise authorized by the City Project Manager.
FIELD DENSITY
SP 20
The second through fifth paragraph of Section 302-5.11.2 shall be deleted and replaced with the following:
Sublots for Compaction Testing shall be defined as follows:
1. Quantity-Based Sublots
Each 250 tons (or portion thereof) of asphalt placed on an individual street in a single paving day constitutes a sublot.
If more than 250 tons are placed on a street in one day, up to 50 tons above 250 may be included in the previous 250-ton sublot.
2. Multiple Streets
When paving multiple streets in a single day, each street shall be considered a separate sublot.
Streets where more than 250 tons are placed in a day may be subdivided into multiple sublots.
3. In-Place Density Requirements
The in-place density shall be between 92.0% and 97.0% of maximum theoretical unit weight.
Compaction shall be determined by coring. Three cores shall be taken per sublot, and the average of the three cores shall be used to determine the sublot’s compaction.
4. Core Sampling
The City Inspector shall determine core locations using random sampling charts per
CTM 356.
Cores shall be 4-inch or 6-inch diameter and sampled within 5 calendar days of paving.
The Contractor shall submit properly labeled cores to the City for testing.
The City Project Manager shall provide core test results within 3 working days of receipt.
5. Core Backfill
The Contractor shall backfill cores with hot mix asphalt the same day the cores are taken.
Failure to backfill on the same day will be subject to liquidated damages of $500 per day per location.
6. Deductions for Percent Maximum Theoretical Density
For sublots that do not meet the density requirements, the following table shall apply to determine deductions based on the average compaction of the sublot:
SP 21
Reduced Payment Factors for Percent of Maximum Theoretical Density
Mix Type B and C2 Percent of Maximum
Theoretical Density
Reduced Payment Factor
Mix Type B and C2 Percent of Maximum
Theoretical Density
Reduced Payment Factor
92.0 0.0000 97.0 0.0000
91.9 0.0125 97.1 0.0125
91.8 0.0250 97.2 0.0250
91.7 0.0375 97.3 0.0375
91.6 0.0500 97.4 0.0500
91.5 0.0625 97.5 0.0625
91.4 0.0750 97.6 0.0750
91.3 0.0875 97.7 0.0875
91.2 0.1000 97.8 0.1000
91.1 0.1125 97.9 0.1125
91.0 0.1250 98.0 0.1250
90.9 0.1375 98.1 0.1375
90.8 0.1500 98.2 0.1500
90.7 0.1625 98.3 0.1625
90.6 0.1750 98.4 0.1750
90.5 0.1875 98.5 0.1875
90.4 0.2000 98.6 0.2000
90.3 0.2125 98.7 0.2125
90.2 0.2250 98.8 0.2250
90.1 0.2375 98.9 0.2375
90.0 0.2500 99.0 0.2500
<90.0 Remove &
Replace
Remove &
Replace
SAMPLING
The City Inspector may sample the asphalt concrete from the truck bed, windrow, hopper for the spreading machine, or the mat at various intervals. The Contractor shall facilitate the sampling process.
COLD JOINTS
Cold joints are defined as previously placed pavement that has been in place for more than three hours. All cold joints, both longitudinal and transverse, shall be heated with a torch prior to applying tack coat and placement of adjoining pavement. Care shall be taken to avoid damaging the asphalt concrete by burning or causing excessive aging, as determined by the City Inspector.
Any material deemed damaged shall be removed by saw cutting to create a new cold joint, which shall then be torch-heated prior to paving.
TEMPORARY TRANSITIONS
The Contractor shall construct temporary pavement transitions at all paving joints exceeding 1
SP 22
inch prior to allowing traffic onto the paved surface. This applies to both longitudinal and transverse paving joints in leveling and surface courses.
Temporary pavement transitions shall:
• Have a slope of 20:1, or as approved by the City Inspector.
• Be constructed on Kraft paper or another suitable bond breaker so that, upon removal, a clean notch remains.
• Be constructed of either cold mix or hot mix asphalt.
Additionally, the Contractor shall construct temporary pavement transitions at all minor concrete features exceeding 1 inch, including, but not limited to:
• Curb returns (from beginning to end of the return)
• Cross gutters
• Spandrels or other small concrete elements within or adjacent to the pavement
The Contractor shall continuously maintain all temporary transitions until final paving. Each transition shall be inspected daily, including weekends and holidays, and repaired as necessary to comply with these provisions.
Failure to comply shall result in liquidated damages of $250 per day per transition, and/or the cost of City crews performing repairs if necessary to maintain public safety.
PAYMENT
Payment for Asphalt Rubber Hot Mix (ARHM) shall be made at the contract unit prices bid for this bid item. Such payment shall constitute full compensation for furnishing all labor, materials, tools, equipment, and incidentals necessary to comply with the requirements of the project plans, specifications, special provisions, and contract documents. No additional compensation shall be allowed therefor.
Fiber Reinforced Asphalt Concrete (FR-ARHM-GG-C)
GENERAL
The work consists of installing ARHM with fiber additive. Contractor shall follow the requirements set forth in the Standard Specifications and Special Provisions that govern ARHM in conjunction with the provisions of Section 302-18 “Fiber Reinforced Asphalt Concrete”. Where a conflict arises, Contractor shall follow the most stringent requirement.
PAYMENT
Payment for ARHM-GG-C with Fiber Additive shall be made at the contract unit prices bid for this
SP 23
bid item. Such payment shall constitute full compensation for furnishing all labor, materials, tools, equipment, and incidentals necessary to comply with the requirements of the project plans, Asphalt Leveling Course
This work consists of installing 0.5” Type D 3/8" PG 64-10 leveling course per Section 203 of the
Standard Specifications and preparing the existing street surfaces prior to the paving. Pavement surface preparation shall involve cleaning by sweeping the pavement surface or other method approved by the City Project Manager/Inspector. No loose particle shall remain on the pavement after cleaning. Thermoplastic striping and pavement markings, raised pavement markers, and raised pavement marker adhesive shall be removed. Manhole covers, utility vaults and surface of other utility facilities, survey monuments and benchmarks, shall be covered using a material approved by the City Project Manager/Inspector.
LEVELING, TRANSITIONS, AND ASPHALT CONCRETE FILLS
A leveling course of variable thickness shall be placed and compacted prior to placing the surface course at locations designated on the Plans. The leveling course is intended to correct pavement irregularities such as rutting, variable cross slope, or variable longitudinal slope.
Where two overlays of different thickness meet at a longitudinal joint, the Contractor shall adjust the thinner section to match the thicker lift, ensuring a smooth transition and uniform cross-fall.
The City Project Manager/Inspector may require cold planing of ridges or other surface irregularities prior to paving. The exact limits and thickness of leveling courses, asphalt concrete fills, and transitions will be determined by the City Inspector.
Areas designated for asphalt fill, as shown on the plans or directed by the City Project
Manager/Inspector, shall be completed prior to performing leveling course work.
PAYMENT
Payment for “Asphalt Levelling Course” shall be made at the contract unit prices bid for this bid item. Such payment shall constitute full compensation for furnishing all labor, materials, tools, equipment, and incidentals necessary to comply with the requirements of the project plans, Cold Mill Header Cut & Transitions
SP 24
The existing pavement adjacent to gutters, cross gutters, at the ends of rehabilitation areas, and at equipment crossings shall be cold planed as specified herein and as shown on the Plans.
The limits of cold planing shall be as shown on the Plans or as determined by the City Project
Manager/Inspector prior to construction. The required depths, widths, and dimensions of cold planing shall be as indicated on the Plans and Standard Details.
Cold planing shall be used to remove existing pavement on roadways designated for cold planing and for the installation of asphalt concrete, and may also be used in areas requiring dig-outs as directed by the City Project Manager/Inspector.
The Contractor shall schedule cold planing operations so that the pavement leveling (base) course can be placed immediately after milling and completion of dig-outs, to minimize exposure of the underlying pavement structure and to maintain traffic safety.
EQUIPMENT
The cold planing machine shall be designed specifically for cold milling of bituminous pavement without the application of heat and shall have demonstrated satisfactory performance on similar work. The machine shall also be capable of planing portland cement concrete (PCC) patches within asphalt pavement and PCC pavement surfaces.
The planing machine shall meet the following minimum requirements:
• Equipped with a cutting drum not less than 30 inches wide.
• Fitted with carbide-tipped cutting teeth arranged in a variable lacing pattern to produce a uniform surface texture.
• Capable of operating at forward speeds ranging from 0 to 40 feet per minute.
• Self-propelled and equipped with a water spray system at the cutting drum to minimize dust.
• Capable of removing material adjacent to gutters and curbs.
• Designed so the operator can observe the planing operation at all times without leaving the controls.
• Adjustable for slope and depth to conform to the required surface profile.
The Contractor’s attention is directed to Subsection 3-12.2, “Air Pollution Control,” of the
Standard Specifications.
CONSTRUCTION
The Contractor shall maintain any temporary asphaltic fill material placed over planed areas, utility adjustments, or keycuts until the final pavement surface is installed.
Material shall be removed as shown in the keycut details included in the project plans.
Remaining material around utility covers, gutter lips, and other fixed features shall be removed
SP 25
to the depth of the adjacent milled surface after completion of cold planing. Where the planing machine cannot remove material at these locations, the Contractor shall use approved alternate methods to achieve the required grade and profile.
REMOVAL AND DISPOSAL OF MATERIAL
During planing operations, the Contractor shall continuously sweep the pavement with mechanical equipment and remove all loosened material from the project site until the removal work is complete. All necessary measures shall be taken to prevent the dispersion of dust.
The Contractor shall notify the City Inspector and obtain approval of the swept surface prior to application of tack coat.
All removed material shall be disposed of in accordance with the City of Pasadena Construction and Demolition Materials Management requirements, project specifications and contract documents.
PAYMENT
Payment for “Cold Mill Header Cut and Cold Mill Transition” shall be made at the contract unit price bid for each bid item and shall constitute full compensation for furnishing all labor, materials, tools, equipment, traffic control, disposal, and incidentals necessary to comply with project plans, Digout or Remove and Replace 4" AC
The work consists of removing existing asphalt concrete and base, if necessary, to the specified depth by cold planing and replacing the void with asphalt concrete. Dig-outs shall be constructed as indicated on the plans and immediately after cold planing operations so that the asphalt concrete levelling (base course) can be placed on the milled surface in the same shift.
MATERIALS
Asphalt concrete for dig-outs or remove & replace shall be C2 and conform to these Special
Provisions. The asphalt concrete binder shall be C2 PG 64-10 (dense medium coarse) per Table
203-6.4.4 of the Standard Specifications, unless otherwise specified on the plans or approved by the City Project Manager.
CONSTRUCTION
• The City Inspector shall mark the locations of dig-outs and base repair areas based on the plans and observations following full-width milling operations. The Contractor shall accompany the City Inspector during marking. The areas marked, measured, and agreed
SP 26
upon shall constitute the final pay quantity.
• The Contractor shall notify the City Inspector at least two working days prior to performing work.
• After milling, asphalt concrete within the marked dig-out/base repair areas shall be removed to the uniform depth specified. The edges of the removal shall be saw-cut or vertically ground. All removed material shall be hauled from the site.
• If base rock is exposed, it shall be compacted and proof-rolled in the presence of the City
Project Manager or designated representative.
• Pavement shall be placed and compacted as specified in Subsection 302-5 of the
Standard Specifications.
• In areas where the underlying material appears wet, soft, or deflects under wheel loads, excavation and grading techniques shall be employed that do not worsen subgrade conditions.
• Prior to placing asphalt concrete, the area shall be proof-rolled using a loaded construction vehicle, preferably a 10-cubic-yard dump truck or equivalent. The compacted surface shall not visibly yield or deflect. Soft, unstable, or unsuitable areas shall be removed and replaced with base rock or asphalt concrete.
• Any subgrade deficiencies caused or significantly worsened by the Contractor’s operations shall be corrected at the Contractor’s expense.
• If underlying material is soft, yielding, unstable, or unsuitable, it shall be excavated to 6 inches below the original dig-out/base repair depth, as directed by the City Project
Manager/Inspector, and filled with a single lift of asphalt concrete, compacted per Section
302-5 of the Standard Specifications. Payment for this work shall be made under the Bid
Item “Over-Excavation”. For bidding purposes, it is assumed that 10% of dig-out/base repair areas may require over-excavation and shall be included in the contract unit price for bid item “Digout or Remove and Replace”.
a. Unsuitable material is defined as material that the City determines to be:
• incapable of being compacted to specified density using ordinary methods at optimum moisture content, or
• too wet to be properly compacted and in-place drying is not feasible, or
• otherwise unsuitable for the planned use.
• Remove only as much material as can be replaced within the same work period.
• For streets requiring an ARHM surface course, the Contractor shall coordinate the
SP 27
schedule and timing of placement. All AC base and intermediate courses shall be placed within the same work period.
PAYMENT
Payment for “Dig-outs or Remove & Replace 4” AC,” complete in place, shall be made at the contract unit price bid for this bid item. Such payment shall be considered full compensation for furnishing all labor, materials, tools, and equipment required to complete the work, including the removal and proper disposal of excavated material, in accordance with the project plans, specifications, special provisions and contract documents. No additional compensation shall be
Portland Concrete Cement (PCC) Curb and Gutter
The work consists of removing existing curb and gutter, or curb or gutter alone, and constructing new curb and gutter using Class 560-C-3250 concrete, including depressed curbs for driveways per the project plans and specifications, special provisions, and contract documents. All new curbs shall be painted within 48 hours of installation.
PAYMENT
Payment for “PCC Curb, PCC Gutter and PCC Curb & Gutter” shall be made at the contract unit price bid for each bid item and shall constitute full compensation for furnishing all labor, materials, tools and equipment for complying with the requirements of the project plans, specifications, special provisions and contract documents. No additional compensation will be allowed therefor.
PCC Access Ramp, Sidewalk, Driveway Apron and Cross Gutter
The work consists of constructing Class 520-C-2500 or 560-C-3250 minor concrete infrastructure per Pasadena standard…