6. Permit Requirements Memo.pdf

PDF 28 KB Posted

Attached to
Sustain Pad 5, Phase III Federal contract opportunity
Solicitation number
FA9401-12-R-0019
Issued by
Department of the Air Force Global Strike Command

About this file

Attachment 6

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEMORANDUM

DATE: 26 April 2012

SUBJECT: TN 12-015, Project No.: MHMV070054B, Project Title: Sustain Pad 5-Phase III, Kirtland AFB, NM Permit Requirements

FROM: Chugach Management Services JV, Task Order Project Manager

The following permits are required on the subject project:

1. AF Form 103 – Base Civil Engineering Work Clearance Request (blank example attached)

2. Construction SWPPP

3. Fugitive Dust Permit

If changes are made to the project, or new laws/policies enacted by the local agencies, there may be additional permits required for construction. Prior to work starting, it is recommended the government verify current permit requirements are being met at the time of construction.

SUBJECT: TN 12-015, Project No.: MHMV070054B, Project Title: Sustain Pad 5-Phase III, Kirtland AFB, NM Permit Requirements