Attachment_L-6_CLIN_MPS_IMS_Guidance_Template_and_SubCLIN_Structure_revised_121312.doc

DOC document 434 KB Posted

Attached to
Vandenberg Air Force Base (AFB) Performance-Based Remediation (PBR) Federal contract opportunity
Solicitation number
FA8903-12-R-0033
Issued by
Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency

About this file

Attachment L-6 CLIN/IMS/MPS Guidance with SubCLIN Structure - Revised

View the file

Other files for this federal contract opportunity

Other files attached to Vandenberg Air Force Base (AFB) Performance-Based Remediation (PBR), newest first.
File Type Posted
Vandenberg_Section_L_-_28_May_2013.pdf PDF
SF33_Amend_005_24_May_13.pdf PDF
Vandenberg_Section_M-21_May_2013.pdf PDF
Vandenberg_Section_L_-_21_May_2013.pdf PDF
VAFB_Questions_and_Answers_Spreadsheet__2_Final_RFP_RQ_revision.xlsx XLSX spreadsheet
VAFB_Questions_and_Answers_Spreadsheet__1_Final_RFP_RQ_revision.xlsx XLSX spreadsheet
6)_Enclosure_2__Key_Documents_revised_050913.xlsx XLSX spreadsheet
QA_Spreadsheet__2_-_VAFB_PBR__Final.xlsx XLSX spreadsheet
Vandenberg_PBR_Solicitation-28_March_2013.pdf PDF
VAFB_Question_and_Answers_Spreadsheet_Final_RFP__2.xlsx XLSX spreadsheet
Vandenberg_Section_L_-_28_Mar_13.pdf PDF
Attachment_L-6__CLIN_Milestone_Schedule_Guidance_27_Mar_13-Revised.pdf PDF
VAFB_Question_and_Answers_Spreadsheet_Final_RFP.xlsx XLSX spreadsheet
Attachment_L-4_Subcontractor_Consent_Letter_Sample_22_Feb_13.pdf PDF
Attachment_L-5_Client_Authorization_Letter_Sample_22_Feb_13.pdf PDF
Attachment_L-1_MilestonePaymentSchedule_without_price_22_Feb_13.pdf PDF
Attachment_3_-_General_Decision_Number_CA23__8_Mar_13.pdf PDF
Attachment_L-6_CLIN_Milestone_Schedule_Guidance_22_Feb_13.pdf PDF
Vandenberg_Section_L_-_FINAL_22_Feb_13.pdf PDF
Vandenberg_Section_M_-_FINAL_22_Feb_13.pdf PDF
Vandenberg_PBR_FA8903-12-R-0033_8_March_2013.pdf PDF
Attachment_L-3_Past_Performance_Questionnaire_22_Feb_13.pdf PDF
Attachment_L-2_MilestonePaymentSchedule_with_price_22_Feb_13.pdf PDF
DRAFT_RFP_QA_-_REV_1_to_FINAL_22_Feb_13.xls XLS spreadsheet
DRAFT_RFP_QA_-_FINAL_20_Feb_13.xls XLS spreadsheet
DRAFT_VAFB_PBR_SOO_022013.docx DOCX document
DRAFT_Enclosure_2__Key_Documents.xlsx XLSX spreadsheet
Attachment_L-3_Past_Performance_Questionnaire_5_Dec_12.docx DOCX document
Vandenberg-draftSection_M_-__11_Dec_12.doc DOC document
Attachment_L-1_MilestonePaymentSchedule_without_price_11_Dec_12.xlsx XLSX spreadsheet
Attachment_L-5_Client_Authorization_Letter_Sample.docx DOCX document
Attachment_L-4_Subcontractor_Consent_Letter_Sample.docx DOCX document
Attachment_L-6_CLIN_MPS_IMS_Guidance_Template_and_SubCLIN_Structure.doc DOC document
Attachment_L-2_MilestonePaymentSchedule_with_price_11_Dec_12.xlsx XLSX spreadsheet
DRAFT_FA8903-12-R-0033.pdf PDF
Vandenberg_draft_Section_L_-_11_Dec_12.docx DOCX document
Vandenberg_PBR_Contracting_Slides.pptx PPTX presentation
Site_Visit_Attendee_Sign-In_Redacted.pdf PDF
Vandenberg_PBR_SubCLIN_Overview_11Oct12.pptx PPTX presentation
PBR_Pitfalls_and_Best_Practices_VAFB_Site_Visit_15Oct12.pptx PPTX presentation
DRAFT SOO Enclosure 1 Site List_070612.xlsx XLSX spreadsheet
Attachment - Bonding Stream.pptx PPTX presentation
DRAFT SOO Enclosure 2 Key Documents List_083112.xlsx XLSX spreadsheet
DRAFT SOO Enclosure 5 - Acronyms and Definitions.doc DOC document
DRAFT SOO - Vandenberg PBR 083112.docx DOCX document
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8903-12-R-0033

Attachment L-6

Supplemental Instructions to Offerors for the Development of Contract Line Item Number (CLIN) Structures/

Milestone Payment Schedules (MPS)/Integrated Master Schedules (IMS) This guidance is being provided to communicate Air Force expectations for the development of CLIN/Sub-CLIN Structures and the correlation with the subsequent development of the MPS and the IMS. This guidance is not intended to remove Contractor flexibility. The examples provided are for illustration purposes only and are not intended to be inclusive of all acceptable approaches.

When annual Congressional appropriations provide the basis for sourcing these contracts, special consideration must be given to ensure compliance with funding rules concerning period of availability, bona fide need and purpose as they relate to each year of funding applied. This will ensure milestones are developed that support fiscally responsible use of funds. To ensure compliance when establishing milestones, any contingent events that affect the beginning date of any milestone must be considered. Key to proper use of funds in this context is non-severability. A non-severable deliverable is defined as a deliverable item that represents a single end product or undertaking, entire in its nature, that cannot be feasibly subdivided into discrete elements or phases without losing its identity. Milestones must have a clear delineation of final deliverables, as distinct non-severable options to be fully funded in the fiscal year in which the award of the Sub-CLIN is made, even though the performance may extend into future fiscal years. There is no administrative reservation of funds whatsoever until a determination is made to exercise a separate and non-severable Sub-CLIN. Each non-severable Sub-CLIN will be funded in its entirety with funds current at the time the Sub-CLIN is exercised, and any need for prior year funds in the future will be clearly tied back to the specific non-severable Sub-CLIN and associated well defined requirement(s) and associated deliverable(s).

CLIN AND SUB-CLIN STRUCTURE:

CLINs are identified in the contract. A CLIN should be done for each site and one for the Program Management Plan. Sub-CLINs provide a means for funding economically or programmatically viable stages by identifying the items or activities to be acquired as non-severable contract deliverables (performance objectives). The performance period for the Sub-CLIN may be for more than one, but not more than five fiscal years. Sub-CLINs shall provide a firm fixed price for separately identifiable contract deliverables (performance objectives). Each Sub-CLIN shall have its own performance objective expressly stated. Sub-CLINs should identify remediation objectives or activities that relate directly to, and are an integral part of, the CLIN. For example:

· Achieve [performance objective] for [site number]

Sub-CLIN prices and completion dates must not exceed the value or completion date of the CLIN. Sub-CLINs cannot be partially exercised and must be fully funded when exercised in order to avoid violations of the Anti-Deficiency Act. The use of Sub-CLINs provides the Air Force with the flexibility to match options to be exercised with available funding as the amount of available program funding is sometimes unpredictable. The Air Force may restructure the Sub-CLINs with the Apparent Successful Offeror based upon the submitted MPS.

Sub-CLINs shall consist of numeric digits and alpha characters. Once a Sub-CLIN number has been assigned, it shall not be assigned to another Sub-CLIN in the same task order. Under the contract the numeric digits for the CLIN on Performance-Based Remediation (PBR) task orders shall begin with 0001and so forth. Only 24 alpha characters shall be used in the second position before selecting a different alpha character for the first position. Alpha characters I and O should be avoided due to the potential for confusion with numeric digits 1 or 0. The Sub-CLINs must use AA, AB, AC, through AZ before beginning BA, BB, and BC. For example, if the CLIN number is 0001, the first three Sub-CLIN items would be 0001AA, 0001AB, and 0001AC. Each Site should have its own CLIN. For example:

· 0001AA Performance Management Plan

· 0002AA Achieve [performance objective] for [site A]

· 0002AB Achieve [performance objective] for [site A]

· 0003AA Achieve [performance objective] for [site B]

· 0003AB Achieve [performance objective] for [site B]

MILESTONE PAYMENT SCHEDULE:

The Contractor shall propose milestone payments as part of the MPS in its proposal. The Air Force intends to use the Contractor’s proposed MPS to restructure Sub-CLINs, if necessary, to align with projected available funding prior to award. The MPS shall also be included as part of the Project Management Plan (PMP). The MPS is not included in the task order and is not considered final with award of the task order. Changes made to the MPS prior to award are used to finalize the Sub-CLINs, therefore, award of the task order does not equate to final acceptance of the MPS. The MPS will be negotiated during development of the PMP and may require additional changes.

Milestone payments shall be based on the completion of a definable and measurable step considered integral and necessary to the achievement of the performance objective/Sub-CLIN. Completion of milestones shall demonstrate payment is appropriate. Milestone payments shall include the approval requirements in accordance with the performance standards in Table 1 of the Statement of Objectives (SOO) and the requirements of the regulatory structure. Terms of acceptance of milestone payments will be negotiated during development of the PMP.

A consolidation of completed milestone payments is to be submitted monthly, however milestone payments shall not represent a “progress” payment or a “monthly” payment for level of effort expended. In addition, milestone payments shall not include management or overhead type costs (program/project management, monthly reporting, mobilization/demobilization, etc.) that do not provide measurable project advancement. For any performance objective, a milestone payment shall be for completion of a definable and measurable point considered integral and necessary to completion of the performance objective. For example, if the performance objective is to achieve Remedy-in-Place (RIP) and the work required to achieve RIP includes Feasibility Study (FS), Proposed Plan (PP), Record of Decision (ROD), Remedial Design (RD), and Remedial Action (RA), then potential interim milestone payments could be:

· Air Force approval of Draft FS;

· Air Force and Regulator approval of Final FS;

· Air Force approval of Draft PP;

· Air Force and Regulator approval of Final PP;

· Air Force approval of Draft ROD;

· Air Force and Regulator approval of Final ROD;

· Air Force approval of Draft Remedial Action Work Plan (RAWP)/RD;

· Air Force and Regulator approval of Final RAWP/RD;

· Air Force approval of Remedial Action Completion Report (RACR);

· Air Force and Regulator approval of Final RACR signifying achievement of RIP.

Contractor proposed milestone payments for Air Force approval of draft documents require sufficient funds to remain associated with the final document to ensure completion of the performance objective. Milestone payments shall not exceed 80% of the total payment for that Sub-CLIN prior to achievement of the final deliverable (performance objective). The Sub-CLIN’s final deliverable may include the combination of the draft and final versions. The final Sub-CLIN milestone for each site must be a minimum of 20% of the total Sub-CLIN cost. Air Force acceptance of Contractor proposed draft milestones, or the proposed percentage of the milestone payment as compared to the total payment for that Sub-CLIN, is discretionary and negotiated on a case-by-case basis between the Air Force and selected Offeror. These negotiations may occur prior to award and/or during development of the PMP.

The Air Force will use performance indicators and performance models in addition to the PMP to establish and execute a Surveillance Plan. The Surveillance Plan will highlight key quality control activities or events. The Contracting Officer’s Representative (COR) will use the Surveillance Plan to determine when Air Force (COR and/or Contracting Officer (CO)) surveillance activities can be conducted to assess progress toward and/or completion of milestone payments.

INTEGRATED MASTER SCHEDULE:

The Contractor shall prepare and submit an activity-based IMS that is consistent with the MPS. The Contractor must include and identify all performance milestones at the appropriate level of detail and logically sequenced to support and manage achievement of the proposed performance objectives. The IMS shall identify completion of the performance objectives in the time designated and shall include identification of any critical path items. The IMS shall include incorporation of Air Force and Regulatory review periods for deliverables while meeting or exceeding any applicable agreements or regulatory schedule requirements.

Sites associated with each milestone/task must be noted in the schedules using the Site IDs and referencing all site aliases noted in Table 1 of the SOO. The schedule shall be provided in hardcopy and electronic format consistent/compatible with Air Force software, currently Microsoft( Project, Microsoft( Excel, and in Adobe Acrobat portable document file (.pdf). Updated and revised schedules shall be submitted with monthly status reports with changes clearly identified by the Contractor.

An example illustrating the progression of CLIN/Sub-CLIN Structure to MPS and IMS follows:

EXAMPLE CLIN/SUB-CLIN STRUCTURE

(Air Force approval required prior to Contract Award)

CLIN/SUB-CLIN
CLIN/SUB-CLIN/MILESTONE PAYMENT DESCRIPTION
CLIN/SUB-CLIN AMOUNT
PROJECTED EXERCISE DATE OR RATIONALE
0001
Program Management Plan
$0
0001AA
Preliminary Project Management Plan (PMP)
$25,000
At Award
0001AB
Final Project Management Plan (PMP)
$25,000
Approx 4.5 years from 0001AA or upon CO determination of bona fide need
0002
CG025 Management Unit
0002AA
CG025 Management Unit: Achieve RIP
$200,000
At Award
Total
$250,000

EXAMPLE MILESTONE PAYMENT SCHEDULE

(Negotiated between the Air Force and the selected Offeror and approved by the Air Force)

CLIN/SUB-CLIN
CLIN/SUB-CLIN/MILESTONE PAYMENT DESCRIPTION
CLIN/SUB-CLIN AMOUNT
MILESTONE PAYMENT AMOUNT
MILESTONE PERCENT
0001
Program Management Plan
$0
0001AA
Preliminary Project Management Plan (PMP)
$25,000
$25,000
0001AB
Final Project Management Plan (PMP)
$25,000
$25,000
0002
CG025 Management Unit
0002AA
CG025 Management Unit: Achieve RC
$200,000

Air Force Approval of Draft FS

$30,000
15%

Air Force and Regulatory Approval of Final FS

$20,000
25%

Air Force Approval of Draft ROD

$6,000
28%

Air Force and Regulatory Approval of Final ROD

$4,000
30%

Air Force Approval of Draft Remedial Action Work Plan/Remedial Design

$62,000
61%

Air Force and Regulatory Approval of Final Remedial Action Work Plan/Remedial Design

$38,000
80%

Air Force Approval of Draft RACR

$30,000
95%

Air Force and Regulatory Approval of Final RACR signifying achievement of RIP

$10,000
100%
Total
$250,000
$250,000

Note: Payment milestone shall not exceed 80% of the total payment for the CLIN/Sub-CLIN prior to achievement of the final deliverable. In the example above, 80% of $200,000 = $160,000; therefore, RACR (draft + final) = $40,000 or 20% of the Sub-CLIN 0002AA. Air Force approval of the "Draft" is defined as Contractor resolution of Air Force comments on the Draft deliverable.

EXAMPLE Integrated Master Schedule (Air Force approval required as part of the PMP)

Activity ID#
ACTIVITY DESCRIPTION
DURATION
START
FINISH
0001
Contract Award
1 day
1 OCT 10
1 OCT 10
0001AA0001
Kick Off Meeting
1 day
15 OCT 10
15 OCT 10
0001AA0002
Prepare Preliminary PMP
30 days
1 OCT 10
31 OCT 10
0001AA0003QA
Air Force Review of Draft Preliminary PMP
30 days
1 NOV 10
1 DEC 10
0001AA0004PM
Air Force Approval of Final Preliminary PMP
1 day
1 DEC 10
1 DEC 10

Note: Air Force surveillance activities precede all milestone payments.

*CLIN/ SUB-CLIN
CLIN/SUB-CLIN DESCRIPTION
**PROJECTED DATE OF EXERCISE
CLIN/SUB-CLIN AMOUNT
0001
Project Management Plan

$0

0001AA
Preliminary Project Management Plan in accordance with Table 1 of the SOO
At Award
0001AB
Final Project Management Plan in accordance with Table 1 of the SOO
Approx 4.5 years from 0001AA or upon CO determination of bona fide need
0002
SS333 - Bldg 13852

$0

0002AA
SS333 - Bldg 13852: Achieve SC within 1 year from NTP.
At Award
0003
TA549 - Bldg 11777

$0

0003AA
TA549 - Bldg 11777: Achieve SC within 1 year from NTP.
At Award
0004
TU561 - Bldg 13017

$0

0004AA
TU561 - Bldg 13017: Achieve SC within 1 year from NTP.
At Award
0005
TU580 - Bldg 106008

$0

0005AA
TU580 - Bldg 106008: Achieve SC within 1 year from NTP.
At Award
0005
TU580 - Bldg 106008

$0

0006AA
TU582 - Demo Bldg 06335: Achieve SC within 1 year from NTP.
At Award
0007
TU587 - Bldg 07015

$0

0007AA
TU587 - Bldg 07015: Achieve SC within 1 year from NTP.
At Award
0008
CD124 - CE Maintenance

$0

0008AA
CD124 - CE Maintenance: Achieve SC within 1 year from NTP.
At Award
0009
TU329 - Bldg 7312

$0

0009AA
TU329 - Bldg 7312: Achieve SC within 2 years from NTP.
At Award
0010
OW512 - O/W Separator at Bldg 10711B

$0

0010AA
OW512 - O/W Separator at Bldg 10711B: Achieve SC within 2 years from NTP.
At Award
0011
OW264 - O/W Separator at Bldg 6437

$0

0011AA
OW264 - O/W Separator at Bldg 6437: Achieve SC within 2 years from NTP.
At Award
0012
OW519 - O/W Separator at Bldg 1740

$0

0012AA
OW519 - O/W Separator at Bldg 1740: Achieve SC within 2 years from NTP.
At Award
0013
OW231 - O/W Separator at Bldg 11559

$0

0013AA
OW231 - O/W Separator at Bldg 11559: Achieve SC within 2 years from NTP.
At Award
0014
OW262 - O/W Separator at Bldg 10660

$0

0014AA
OW262 - O/W Separator at Bldg 10660: Achieve SC within 2 years from NTP.
At Award
0015
CB024 - Anderson Peak

$0

0015AA
CB024 - Anderson Peak: Achieve SC within 2 years from NTP.
At Award
0016
SA283 - Bldg 06817

$0

0016AA
SA283 - Bldg 06817: Achieve SC within 3 years from NTP.
At Award
0017
TU197 - Bldgs 510 and 511
0017AA
TU197 - Bldgs 510 and 511: Achieve SC within 5 years from NTP.
At Award
0018
ST042 - Component Decotamination Facility: Achieve RC within 2 years from NTP.

$0

0018AA
ST042 - Component Decotamination Facility: Achieve RC within 2 years from NTP.
At Award
0019
SA320 - Bldg 07304

$0

0019AA
SA320 - Bldg 07304: Achieve RC within 2 years from NTP.
At Award
0020
AB139 - Bldg 3340, Former Camp Cooke Waste Incinerator

$0

0020AA
AB139 - Bldg 3340, Former Camp Cooke Waste Incinerator: Achieve RC within 2 years from NTP.
At Award
0021
TU346 - Former Airmen Dining Hall, Bldg 21180

$0

0021AA
TU346 - Former Airmen Dining Hall, Bldg 21180: Achieve RC within 2 years from NTP.
At Award
0022
MY240 - Former Bldg 9310

$0

0022AA
MY240 - Former Bldg 9310: Achieve RIP within 2 years from NTP.
At Award
0023
TU670 - Bldg 11670

$0

0023AA
TU670 - Bldg 11670: Achieve RIP within 2 years from NTP.
At Award
0024
TU077 - Bldg 7425

$0

0024AA
TU077 - Bldg 7425: Achieve RIP within 3 years from NTP.
At Award
0025
CG147- Bldg 8401

$0

0025AA
CG147 - Bldg 8401: Achieve RIP within 3 years from NTP.
At Award
0026
TU174 - Bldg 9340

$0

0026AA
TU174 - Bldg 9340: Achieve RIP within 3 years from NTP.
At Award
0027
SA228 - Bldg 07426

$0

0027AA
SA228 - Bldg 07426: Achieve RIP within 3 years from NTP.
At Award
0028
MY247 - Former Bldg 6441 and 6451

$0

0028AA
MY247 - Former Bldg 6441 and 6451: Achieve RIP within 3 years from NTP.
At Award
0029
MY248 - Former Bldg 6442 and 6452

$0

0029AA
MY248 - Former Bldg 6442 and 6452: Achieve RIP within 3 years from NTP.
At Award
0030
MY249 - Former Bldg 6443 and 6453

$0

0030AA
MY249 - Former Bldg 6443 and 6453: Achieve RIP within 3 years from NTP.
At Award
0031
MY250 - Former Bldg 7306 and 7315

$0

0031AA
MY250 - Former Bldg 7306 and 7315: Achieve RIP within 3 years from NTP.
At Award
0032
MY251 - Former Bldg 7307 and 7316

$0

0032AA
MY251 - Former Bldg 7307 and 7316: Achieve RIP within 3 years from NTP.
At Award
0033
MY240 - Former Bldg 9310

$0

0033AA
MY240 - Former Bldg 9310: Achieve RIP within 2 years from NTP.
At Award
0034
SA251 - Bldg 06436

$0

0034AA
SA251 - Bldg 06436: Achieve RIP within 3 years from NTP.
At Award
0035
SA280 - Bldg 6605 Former (CAP)

$0

0035AA
SA280 - Bldg 6605 Former (CAP): Achieve RIP within 3 years from NTP.
At Award
0036
SA228 - Bldg 07437

$0

0036AA
SA288 - Bldg 07437: Achieve RIP within 3 years from NTP.
At Award
0037
SS004 - Laundry Site

$0

0037AA
SS004 - Laundry Site: Achieve RIP within 4 years from NTP.
At Award
0038
SD015 - Abres-B Launch Complex

$0

0038AA
SD015 - Abres-B Launch Complex: Achieve RIP within 4 years from NTP.
At Award
0039
SD024 - Entomology Wash Rack

$0

0039AA
SD024 - Entomology Wash Rack: Achieve RIP within 4 years from NTP.
At Award
0040
SS003 - Old Railroad Pumping Station

$0

0040AA
SS003 - Old Railroad Pumping Station: Achieve RIP within 5 years from NTP.
At Award
0041
WP005 - Space Launch Complex (SLC) - 3E

$0

0041AA
WP005 - Space Launch Complex (SLC) - 3E: Achieve RIP within 5 years from NTP.
At Award
0042
ST171 - Bldg 1110 - 1113: Achieve RIP within 5 years from NTP.

$0

0042AA
ST171 - Bldg 1110 - 1113: Achieve RIP within 5 years from NTP.
At Award
0043
PL351 - Camp Cooke Fuel Distribution Lines

$0

0043AA
PL351 - Camp Cooke Fuel Distribution Lines: Achieve Remedial Investigation within 2 years from NTP.
At Award
0044
TU003 - Bldg 5003

$0

0044AA
TU003 - Bldg 5003: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0044
TU003 - Bldg 5003

$0

0045AA
TU004 - Bldg 5004: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0046
TU008 - Bldg 5008D

$0

0046AA
TU008 - Bldg 5008D: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0047
ZZ025 - TT-10-Area 7

$0

0047AA
ZZ025 - TT-10-Area 7: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0048
TU044 - Bldg 1971 -2

$0

0048AA
TU044 - Bldg 1971 -2: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0049
TU055 - Bldg 1987

$0

0049AA
TU055 - Bldg 1987: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0050
TU067 - CC-34-9 and 26

$0

0050AA
TU067 - CC-34-9 and 26: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0051
TU100 - Bldgs 13320, 13322

$0

0051AA
TU100 - Bldgs 13320, 13322: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0052
TU101 - Bldg 10103

$0

0052AA
TU101 - Bldg 10103: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0053
TU103 - Bldg 13323

$0

0053AA
TU103 - Bldg 13323: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0054
TU105 - Bldg 4105

$0

0054AA
TU105 - Bldg 4105: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0055
TU107 - Former Bldgs 660, 665, and 668

$0

0055AA
TU107 - Former Bldgs 660, 665, and 668: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0056
TU114 - Former Bldg 475

$0

0056AA
TU114 - Former Bldg 475: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0057
TU115 - Former Bldg 490

$0

0057AA
TU115 - Former Bldg 490: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0058
TU129 - Bldg 6512

$0

0058AA
TU129 - Bldg 6512: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0059
TU130 - Bldg 13850

$0

0059AA
TU130 - Bldg 13850: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0060
TU133 - Bldg 7133

$0

0060AA
TU133 - Bldg 7133: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0061
TU136 - Bldg 4136

$0

0061AA
TU136 - Bldg 4136: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0062
TU187 - Former Bldg 10122

$0

0062AA
TU187 - Former Bldg 10122: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0063
TU196 - Bldg 3196

$0

0063AA
TU196 - Bldg 3196: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0064
TU205 - Bldg 1974

$0

0064AA
TU205 - Bldg 1974: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0065
TU206 - Bldg 2206

$0

0065AA
TU206 - Bldg 2206: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0066
TU216 - Bldg 1731

$0

0066AA
TU216 - Bldg 1731: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0067
TU221 - Bldg 1756

$0

0067AA
TU221 - Bldg 1756: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0068
SA323 - SS-C323 Bldg 6811

$0

0068AA
SA323 - SS-C323 Bldg 6811: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0069
TU328 - Bldg 13512

$0

0069AA
TU328 - Bldg 13512: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0070
TU347 - Former Camp Cook Dormitory

$0

0070AA
TU347 - Former Camp Cook Dormitory: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0071
TU358 - UST at Facility 23205

$0

0071AA
TU358 - UST at Facility 23205: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0072
TU416 - Data Collection Reporting Station

$0

0072AA
TU416 - Data Collection Reporting Station: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0073
TU424 - NASA Administration Bldg

$0

0073AA
TU424 - NASA Administration Bldg: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0074
TU446 Elevan Fuel Oil USTs

$0

0074AA
TU446 Elevan Fuel Oil USTs: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0075
TU448 - Bldg 4448

$0

0075AA
TU448 - Bldg 4448: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0076
TU459 - Camp Cooke Blocks(CC 37-4000, 4100, 4200, 4300)

$0

0076AA
TU459 - Camp Cooke Blocks(CC 37-4000, 4100, 4200, 4300): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0077
TU472 - Bldg 2472

$0

0077AA
TU472 - Bldg 2472: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0078
TU476 - Bldg 725

$0

0078AA
TU476 - Bldg 725: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0079
TU494 - Bldg 302

$0

0079AA
TU494 - Bldg 302: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0080
TU526 - Bldg 2526

$0

0080AA
TU526 - Bldg 2526: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0081
TU537 - Former Bldg 11168 and 11173: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.

$0

0081AA
TU537 - Former Bldg 11168 and 11173: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0082
TU544 - Correctional Facility

$0

0082AA
TU544 - Correctional Facility: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0083
TU574 - Bldgs 13122 and 13123

$0

0083AA
TU574 - Bldgs 13122 and 13123: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0084
TU578 - Bldg 13330

$0

0084AA
TU578 - Bldg 13330: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0085
TU605 - Bldg 10103

$0

0085AA
TU605 - Bldg 10103: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0086
TU606 - Camp Cooke Bldgs (Airmen Dormitories)

$0

0086AA
TU606 - Camp Cooke Bldgs (Airmen Dormitories): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0087
TU608 - Camp Cook Bldgs (i)

$0

0087AA
TU608 - Camp Cook Bldgs (i): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0088
TU649 - Camp Cook Bldgs (II)

$0

0088AA
TU649 - Camp Cook Bldgs (II): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0089
TU713 - Bldg 1713

$0

0089AA
TU713 - Bldg 1713: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP.
3QFY15
0090
TU788 - Bldg 1788

$0

0090AA
TU788 - Bldg 1788: Achieve Preliminary Assessment/Site Inspection within 1 year from NTP.
3QFY15
0091
ST001 - BX Service Station

$0

0091AA
ST001 - BX Service Station: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0091AB
ST001 - BX Service Station: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 00091AA or upon CO determination of bona fide need
0091AC
ST001 - BX Service Station: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0091AB or upon CO determination of bona fide need
0091AD
ST001 - BX Service Station: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0091AC or upon CO determination of bona fide need
0091AE
ST001 - BX Service Station: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 00091AD or upon CO determination of bona fide need
0092
SS002 - Old Service Station

$0

0092AA
SS002 - Old Service Station: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0092AB
SS002 - Old Service Station: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0092AA or upon CO determination of bona fide need
0092AC
SS002 - Old Service Station: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 00092AB or upon CO determination of bona fide need
0092AD
SS002 - Old Service Station: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0092AC or upon CO determination of bona fide need
0092AE
SS002 - Old Service Station: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0092AD or upon CO determination of bona fide need
0093
WP008 - Site 8 Cluster

$0

0093AA
WP008 - SITE 8 Cluster: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0093AB
WP008 - SITE 8 Cluster: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0093AA or upon CO determination of bona fide need
0093AC
WP008 - SITE 8 Cluster: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0093AB or upon CO determination of bona fide need
0093AD
WP008 - SITE 8 Cluster: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0093AC or upon CO determination of bona fide need
0093AE
WP008 - SITE 8 Cluster: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0093AD or upon CO determination of bona fide need
0094
WP013 - Abres A Launch Complex

$0

0094AA
WP013 - Abres A Launch Complex: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0094AB
WP013 - Abres A Launch Complex: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0094AA or upon CO determination of bona fide need
0094AC
WP013 - Abres A Launch Complex: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0094AB or upon CO determination of bona fide need
0094AD
WP013 - Abres A Launch Complex: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 3 years from 0094AC or upon CO determination of bona fide need
0094AE
WP013 - Abres A Launch Complex: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0094AD or upon CO determination of bona fide need
0095
LF018 - Landfill Nos 3 & 4

$0

0095AA
LF018 - Landfill Nos 3 & 4: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0095AB
LF018 - Landfill Nos 3 & 4: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0095AA or upon CO determination of bona fide need
0095AC
LF018 - Landfill Nos 3 & 4: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0095AB or upon CO determination of bona fide need
0095AD
LF018 - Landfill Nos 3 & 4: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0095AC or upon CO determination of bona fide need
0095AE
LF018 - Landfill Nos 3 & 4: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0095AD or upon CO determination of bona fide need
0096
SD019 - Bldg 836

$0

0096AA
SD019 - Bldg 836: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0096AB
SD019 - Bldg 836: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0096AA or upon CO determination of bona fide need
0096AC
SD019 - Bldg 836: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0094AB or upon CO determination of bona fide need
0096AD
SD019 - Bldg 836: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0096AC or upon CO determination of bona fide need
0096AE
SD019 - Bldg 836: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0096AD or upon CO determination of bona fide need
0097
LF020 - Landfill No 1/Drum Disposal Site UST

$0

0097AA
LF020 - Landfill No 1/Drum Disposal Site UST: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0097AB
LF020 - Landfill No 1/Drum Disposal Site UST: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0097AA or upon CO determination of bona fide need
0097AC
LF020 - Landfill No 1/Drum Disposal Site UST: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0097AB or upon CO determination of bona fide need
0097AD
LF020 - Landfill No 1/Drum Disposal Site UST: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0097AC or upon CO determination of bona fide need
0097AE
LF020 - Landfill No 1/Drum Disposal Site UST: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0097AD or upon CO determination of bona fide need
0098
FT021 - Fire Training Area No 1

$0

0098AA
FT021 - Fire Training Area No 1: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0098AB
FT021 - Fire Training Area No 1: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0098AA or upon CO determination of bona fide need
0098AC
FT021 - Fire Training Area No 1: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0098AB or upon CO determination of bona fide need
0098AD
FT021 - Fire Training Area No 1: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0098AC or upon CO determination of bona fide need
0098AE
FT021 - Fire Training Area No 1: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0098AD or upon CO determination of bona fide need
0099
LF022 - Landfill No 11

$0

0099AA
LF022 - Landfill No 11: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0099AB
LF022 - Landfill No 11: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0099AA or upon CO determination of bona fide need
0099AC
LF022 - Landfill No 11: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0099AB or upon CO determination of bona fide need
0099AD
LF022 - Landfill No 11: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0099AC or upon CO determination of bona fide need
0099AE
LF022 - Landfill No 11: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0099AD or upon CO determination of bona fide need
0100
LF023 - Landfill No 5

$0

0100AA
LF023 - Landfill No 5: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0100AB
LF023 - Landfill No 5: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0100AA or upon CO determination of bona fide need
0100AC
LF023 - Landfill No 5: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0100AB or upon CO determination of bona fide need
0100AD
LF023 - Landfill No 5: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0100AC or upon CO determination of bona fide need
0100AE
LF023 - Landfill No 5: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0100AD or upon CO determination of bona fide need
0101
SD025 - SLC-2E

$0

0101AA
SD025 - SLC-2E: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0101AB
SD025 - SLC-2E: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0101AA or upon CO determination of bona fide need
0101AC
SD025 - SLC-2E: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0101AB or upon CO determination of bona fide need
0101AD
SD025-SLC-2E: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0101AC or upon CO determination of bona fide need
0101AE
SD025 - SLC-2E: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0101AD or upon CO determination of bona fide need
0102
SS027 - Exploded Missile Silo

$0

0102AA
SS027 - Exploded Missile Silo: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0102AB
SS027 - Exploded Missile Silo: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0102AA or upon CO determination of bona fide need
0102AC
SS027 - Exploded Missile Silo: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0102AB or upon CO determination of bona fide need
0102AD
SS027 - Exploded Missile Silo: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0102AC or upon CO determination of bona fide need
0102AE
SS027 - Exploded Missile Silo: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0102AD or upon CO determination of bona fide need
0103
SD031 - Missile Silo 576-C

$0

0103AA
SD031 - Missile Silo 576-C: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0103AB
SD031 - Missile Silo 576-C: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0103AA or upon CO determination of bona fide need
0103AC
SD031 - Missile Silo 576-C: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0103AB or upon CO determination of bona fide need
0103AD
SD031 - Missile Silo 576-C: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0103AC or upon CO determination of bona fide need
0103AE
SD031 - Missile Silo 576-C: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0103AD or upon CO determination of bona fide need
0104
SD032 - Missile Silo 576-D

$0

0104AA
SD032 - Missile Silo 576-D: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0104AB
SD032 - Missile Silo 576-D: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0104AA or upon CO determination of bona fide need
0104AC
SD032 - Missile Silo 576-D: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0104AB or upon CO determination of bona fide need
0104AD
SD032 - Missile Silo 576-D: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0104AC or upon CO determination of bona fide need
0104AE
SD032 - Missile Silo 576-D: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0104AD or upon CO determination of bona fide need
0105
SD033 - Missile Silo 576-E

$0

0105AA
SD033 - Missile Silo 576-E: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0105AB
SD033 - Missile Silo 576-E: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0105AA or upon CO determination of bona fide need
0105AC
SD033 - Missile Silo 576-E: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0105AB or upon CO determination of bona fide need
0105AD
SD033 - Missile Silo 576-E: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0105AC or upon CO determination of bona fide need
0105AE
SD033 - Missile Silo 576-E: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0105AD or upon CO determination of bona fide need
0105
SS050 - Bionetics Bldg

$0

0106AA
SS050 - Bionetics Bldg: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0106AB
SS050 - Bionetics Bldg: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0106AA or upon CO determination of bona fide need
0106AC
SS050 - Bionetics Bldg: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0106AB or upon CO determination of bona fide need
0106AD
SS050 - Bionetics Bldg: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0106AC or upon CO determination of bona fide need
0106AE
SS050 - Bionetics Bldg: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0106AD or upon CO determination of bona fide need
0107
ST060 - GSA Service Station

$0

0107AA
ST060 - GSA Service Station: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0107AB
ST060 - GSA Service Station: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0107AA or upon CO determination of bona fide need
0107AC
ST060 - GSA Service Station: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0107AB or upon CO determination of bona fide need
0107AD
ST060 - GSA Service Station: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0107AC or upon CO determination of bona fide need
0107AE
ST060 - GSA Service Station: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0107AD or upon CO determination of bona fide need
0108
DC142 - CE Maintenance Facility

$0

0108AA
DC142 - CE Maintenance Facility, Bldgs 837 and 839: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0108AB
DC142 - CE Maintenance Facility, Bldgs 837 and 839: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0108AA or upon CO determination of bona fide need
0108AC
DC142 - CE Maintenance Facility, Bldgs 837 and 839: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP.
Approx. 2 years from 0108AB or upon CO determination of bona fide need
0108AD
DC142 - CE Maintenance Facility, Bldgs 837 and 839: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0108AC or upon CO determination of bona fide need
0108AE
DC142 - CE Maintenance Facility, Bldgs 837 and 839: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0108AD or upon CO determination of bona fide need

[additional Sub-CLINs beyond minimum performance objectives to be proposed consistent with the contractor's approach]

*NOTE: If additional Sub-CLINs are created prior to award pursuant to Sub-CLIN restructuring, some or all could be re-numbered to be sequential

**Projected Dates of Exercise are the anticipated award dates for the Sub-CLINs, but will be subject to the availability of funding and to the bona fide needs rule. Note that prior to task order award, the Government may restructure the Sub-CLINS based on the Offeror's proposal.

File details come from the government source that posted it. Updated .