FA8903-12-R-0033
Attachment L-6
Supplemental Instructions to Offerors for the Development of Contract Line Item Number (CLIN) Structures/
Milestone Payment Schedules (MPS)/Integrated Master Schedules (IMS) This guidance is being provided to communicate Air Force expectations for the development of CLIN/Sub-CLIN Structures and the correlation with the subsequent development of the MPS and the IMS. This guidance is not intended to remove Contractor flexibility. The examples provided are for illustration purposes only and are not intended to be inclusive of all acceptable approaches.
When annual Congressional appropriations provide the basis for sourcing these contracts, special consideration must be given to ensure compliance with funding rules concerning period of availability, bona fide need and purpose as they relate to each year of funding applied. This will ensure milestones are developed that support fiscally responsible use of funds. To ensure compliance when establishing milestones, any contingent events that affect the beginning date of any milestone must be considered. Key to proper use of funds in this context is non-severability. A non-severable deliverable is defined as a deliverable item that represents a single end product or undertaking, entire in its nature, that cannot be feasibly subdivided into discrete elements or phases without losing its identity. Milestones must have a clear delineation of final deliverables, as distinct non-severable options to be fully funded in the fiscal year in which the award of the Sub-CLIN is made, even though the performance may extend into future fiscal years. There is no administrative reservation of funds whatsoever until a determination is made to exercise a separate and non-severable Sub-CLIN. Each non-severable Sub-CLIN will be funded in its entirety with funds current at the time the Sub-CLIN is exercised, and any need for prior year funds in the future will be clearly tied back to the specific non-severable Sub-CLIN and associated well defined requirement(s) and associated deliverable(s).
CLIN AND SUB-CLIN STRUCTURE:
CLINs are identified in the contract. A CLIN should be done for each site and one for the Program Management Plan. Sub-CLINs provide a means for funding economically or programmatically viable stages by identifying the items or activities to be acquired as non-severable contract deliverables (performance objectives). The performance period for the Sub-CLIN may be for more than one, but not more than five fiscal years. Sub-CLINs shall provide a firm fixed price for separately identifiable contract deliverables (performance objectives). Each Sub-CLIN shall have its own performance objective expressly stated. Sub-CLINs should identify remediation objectives or activities that relate directly to, and are an integral part of, the CLIN. For example:
· Achieve [performance objective] for [site number]
Sub-CLIN prices and completion dates must not exceed the value or completion date of the CLIN. Sub-CLINs cannot be partially exercised and must be fully funded when exercised in order to avoid violations of the Anti-Deficiency Act. The use of Sub-CLINs provides the Air Force with the flexibility to match options to be exercised with available funding as the amount of available program funding is sometimes unpredictable. The Air Force may restructure the Sub-CLINs with the Apparent Successful Offeror based upon the submitted MPS.
Sub-CLINs shall consist of numeric digits and alpha characters. Once a Sub-CLIN number has been assigned, it shall not be assigned to another Sub-CLIN in the same task order. Under the contract the numeric digits for the CLIN on Performance-Based Remediation (PBR) task orders shall begin with 0001and so forth. Only 24 alpha characters shall be used in the second position before selecting a different alpha character for the first position. Alpha characters I and O should be avoided due to the potential for confusion with numeric digits 1 or 0. The Sub-CLINs must use AA, AB, AC, through AZ before beginning BA, BB, and BC. For example, if the CLIN number is 0001, the first three Sub-CLIN items would be 0001AA, 0001AB, and 0001AC. Each Site should have its own CLIN. For example:
· 0001AA Performance Management Plan
· 0002AA Achieve [performance objective] for [site A]
· 0002AB Achieve [performance objective] for [site A]
· 0003AA Achieve [performance objective] for [site B]
· 0003AB Achieve [performance objective] for [site B]
MILESTONE PAYMENT SCHEDULE:
The Contractor shall propose milestone payments as part of the MPS in its proposal. The Air Force intends to use the Contractor’s proposed MPS to restructure Sub-CLINs, if necessary, to align with projected available funding prior to award. The MPS shall also be included as part of the Project Management Plan (PMP). The MPS is not included in the task order and is not considered final with award of the task order. Changes made to the MPS prior to award are used to finalize the Sub-CLINs, therefore, award of the task order does not equate to final acceptance of the MPS. The MPS will be negotiated during development of the PMP and may require additional changes.
Milestone payments shall be based on the completion of a definable and measurable step considered integral and necessary to the achievement of the performance objective/Sub-CLIN. Completion of milestones shall demonstrate payment is appropriate. Milestone payments shall include the approval requirements in accordance with the performance standards in Table 1 of the Statement of Objectives (SOO) and the requirements of the regulatory structure. Terms of acceptance of milestone payments will be negotiated during development of the PMP.
A consolidation of completed milestone payments is to be submitted monthly, however milestone payments shall not represent a “progress” payment or a “monthly” payment for level of effort expended. In addition, milestone payments shall not include management or overhead type costs (program/project management, monthly reporting, mobilization/demobilization, etc.) that do not provide measurable project advancement. For any performance objective, a milestone payment shall be for completion of a definable and measurable point considered integral and necessary to completion of the performance objective. For example, if the performance objective is to achieve Remedy-in-Place (RIP) and the work required to achieve RIP includes Feasibility Study (FS), Proposed Plan (PP), Record of Decision (ROD), Remedial Design (RD), and Remedial Action (RA), then potential interim milestone payments could be:
· Air Force approval of Draft FS;
· Air Force and Regulator approval of Final FS;
· Air Force approval of Draft PP;
· Air Force and Regulator approval of Final PP;
· Air Force approval of Draft ROD;
· Air Force and Regulator approval of Final ROD;
· Air Force approval of Draft Remedial Action Work Plan (RAWP)/RD;
· Air Force and Regulator approval of Final RAWP/RD;
· Air Force approval of Remedial Action Completion Report (RACR);
· Air Force and Regulator approval of Final RACR signifying achievement of RIP.
Contractor proposed milestone payments for Air Force approval of draft documents require sufficient funds to remain associated with the final document to ensure completion of the performance objective. Milestone payments shall not exceed 80% of the total payment for that Sub-CLIN prior to achievement of the final deliverable (performance objective). The Sub-CLIN’s final deliverable may include the combination of the draft and final versions. The final Sub-CLIN milestone for each site must be a minimum of 20% of the total Sub-CLIN cost. Air Force acceptance of Contractor proposed draft milestones, or the proposed percentage of the milestone payment as compared to the total payment for that Sub-CLIN, is discretionary and negotiated on a case-by-case basis between the Air Force and selected Offeror. These negotiations may occur prior to award and/or during development of the PMP.
The Air Force will use performance indicators and performance models in addition to the PMP to establish and execute a Surveillance Plan. The Surveillance Plan will highlight key quality control activities or events. The Contracting Officer’s Representative (COR) will use the Surveillance Plan to determine when Air Force (COR and/or Contracting Officer (CO)) surveillance activities can be conducted to assess progress toward and/or completion of milestone payments.
INTEGRATED MASTER SCHEDULE:
The Contractor shall prepare and submit an activity-based IMS that is consistent with the MPS. The Contractor must include and identify all performance milestones at the appropriate level of detail and logically sequenced to support and manage achievement of the proposed performance objectives. The IMS shall identify completion of the performance objectives in the time designated and shall include identification of any critical path items. The IMS shall include incorporation of Air Force and Regulatory review periods for deliverables while meeting or exceeding any applicable agreements or regulatory schedule requirements.
Sites associated with each milestone/task must be noted in the schedules using the Site IDs and referencing all site aliases noted in Table 1 of the SOO. The schedule shall be provided in hardcopy and electronic format consistent/compatible with Air Force software, currently Microsoft( Project, Microsoft( Excel, and in Adobe Acrobat portable document file (.pdf). Updated and revised schedules shall be submitted with monthly status reports with changes clearly identified by the Contractor.
An example illustrating the progression of CLIN/Sub-CLIN Structure to MPS and IMS follows:
EXAMPLE CLIN/SUB-CLIN STRUCTURE
(Air Force approval required prior to Contract Award)
| CLIN/SUB-CLIN |
| CLIN/SUB-CLIN/MILESTONE PAYMENT DESCRIPTION |
| CLIN/SUB-CLIN AMOUNT |
| PROJECTED EXERCISE DATE OR RATIONALE |
| 0001 |
| Program Management Plan |
| $0 |
| 0001AA |
| Preliminary Project Management Plan (PMP) |
| $25,000 |
| At Award |
| 0001AB |
| Final Project Management Plan (PMP) |
| $25,000 |
| Approx 4.5 years from 0001AA or upon CO determination of bona fide need |
| 0002 |
| CG025 Management Unit |
| 0002AA |
| CG025 Management Unit: Achieve RIP |
| $200,000 |
| At Award |
EXAMPLE MILESTONE PAYMENT SCHEDULE
(Negotiated between the Air Force and the selected Offeror and approved by the Air Force)
| CLIN/SUB-CLIN |
| CLIN/SUB-CLIN/MILESTONE PAYMENT DESCRIPTION |
| CLIN/SUB-CLIN AMOUNT |
| MILESTONE PAYMENT AMOUNT |
| MILESTONE PERCENT |
| 0001 |
| Program Management Plan |
| $0 |
| 0001AA |
| Preliminary Project Management Plan (PMP) |
| $25,000 |
| $25,000 |
| 0001AB |
| Final Project Management Plan (PMP) |
| $25,000 |
| $25,000 |
| 0002 |
| CG025 Management Unit |
| 0002AA |
| CG025 Management Unit: Achieve RC |
| $200,000 |
Air Force Approval of Draft FS
Air Force and Regulatory Approval of Final FS
Air Force Approval of Draft ROD
Air Force and Regulatory Approval of Final ROD
Air Force Approval of Draft Remedial Action Work Plan/Remedial Design
Air Force and Regulatory Approval of Final Remedial Action Work Plan/Remedial Design
Air Force Approval of Draft RACR
Air Force and Regulatory Approval of Final RACR signifying achievement of RIP
Note: Payment milestone shall not exceed 80% of the total payment for the CLIN/Sub-CLIN prior to achievement of the final deliverable. In the example above, 80% of $200,000 = $160,000; therefore, RACR (draft + final) = $40,000 or 20% of the Sub-CLIN 0002AA. Air Force approval of the "Draft" is defined as Contractor resolution of Air Force comments on the Draft deliverable.
EXAMPLE Integrated Master Schedule (Air Force approval required as part of the PMP)
| Activity ID# |
| ACTIVITY DESCRIPTION |
| DURATION |
| START |
| FINISH |
| 0001 |
| Contract Award |
| 1 day |
| 1 OCT 10 |
| 1 OCT 10 |
| 0001AA0001 |
| Kick Off Meeting |
| 1 day |
| 15 OCT 10 |
| 15 OCT 10 |
| 0001AA0002 |
| Prepare Preliminary PMP |
| 30 days |
| 1 OCT 10 |
| 31 OCT 10 |
| 0001AA0003QA |
| Air Force Review of Draft Preliminary PMP |
| 30 days |
| 1 NOV 10 |
| 1 DEC 10 |
| 0001AA0004PM |
| Air Force Approval of Final Preliminary PMP |
| 1 day |
| 1 DEC 10 |
| 1 DEC 10 |
Note: Air Force surveillance activities precede all milestone payments.
| *CLIN/ SUB-CLIN |
| CLIN/SUB-CLIN DESCRIPTION |
| **PROJECTED DATE OF EXERCISE |
| CLIN/SUB-CLIN AMOUNT |
| 0001 |
| Project Management Plan |
$0
| 0001AA |
| Preliminary Project Management Plan in accordance with Table 1 of the SOO |
| At Award |
| 0001AB |
| Final Project Management Plan in accordance with Table 1 of the SOO |
| Approx 4.5 years from 0001AA or upon CO determination of bona fide need |
$0
| 0002AA |
| SS333 - Bldg 13852: Achieve SC within 1 year from NTP. |
| At Award |
$0
| 0003AA |
| TA549 - Bldg 11777: Achieve SC within 1 year from NTP. |
| At Award |
$0
| 0004AA |
| TU561 - Bldg 13017: Achieve SC within 1 year from NTP. |
| At Award |
$0
| 0005AA |
| TU580 - Bldg 106008: Achieve SC within 1 year from NTP. |
| At Award |
$0
| 0006AA |
| TU582 - Demo Bldg 06335: Achieve SC within 1 year from NTP. |
| At Award |
$0
| 0007AA |
| TU587 - Bldg 07015: Achieve SC within 1 year from NTP. |
| At Award |
| 0008 |
| CD124 - CE Maintenance |
$0
| 0008AA |
| CD124 - CE Maintenance: Achieve SC within 1 year from NTP. |
| At Award |
$0
| 0009AA |
| TU329 - Bldg 7312: Achieve SC within 2 years from NTP. |
| At Award |
| 0010 |
| OW512 - O/W Separator at Bldg 10711B |
$0
| 0010AA |
| OW512 - O/W Separator at Bldg 10711B: Achieve SC within 2 years from NTP. |
| At Award |
| 0011 |
| OW264 - O/W Separator at Bldg 6437 |
$0
| 0011AA |
| OW264 - O/W Separator at Bldg 6437: Achieve SC within 2 years from NTP. |
| At Award |
| 0012 |
| OW519 - O/W Separator at Bldg 1740 |
$0
| 0012AA |
| OW519 - O/W Separator at Bldg 1740: Achieve SC within 2 years from NTP. |
| At Award |
| 0013 |
| OW231 - O/W Separator at Bldg 11559 |
$0
| 0013AA |
| OW231 - O/W Separator at Bldg 11559: Achieve SC within 2 years from NTP. |
| At Award |
| 0014 |
| OW262 - O/W Separator at Bldg 10660 |
$0
| 0014AA |
| OW262 - O/W Separator at Bldg 10660: Achieve SC within 2 years from NTP. |
| At Award |
| 0015 |
| CB024 - Anderson Peak |
$0
| 0015AA |
| CB024 - Anderson Peak: Achieve SC within 2 years from NTP. |
| At Award |
$0
| 0016AA |
| SA283 - Bldg 06817: Achieve SC within 3 years from NTP. |
| At Award |
| 0017 |
| TU197 - Bldgs 510 and 511 |
| 0017AA |
| TU197 - Bldgs 510 and 511: Achieve SC within 5 years from NTP. |
| At Award |
| 0018 |
| ST042 - Component Decotamination Facility: Achieve RC within 2 years from NTP. |
$0
| 0018AA |
| ST042 - Component Decotamination Facility: Achieve RC within 2 years from NTP. |
| At Award |
$0
| 0019AA |
| SA320 - Bldg 07304: Achieve RC within 2 years from NTP. |
| At Award |
| 0020 |
| AB139 - Bldg 3340, Former Camp Cooke Waste Incinerator |
$0
| 0020AA |
| AB139 - Bldg 3340, Former Camp Cooke Waste Incinerator: Achieve RC within 2 years from NTP. |
| At Award |
| 0021 |
| TU346 - Former Airmen Dining Hall, Bldg 21180 |
$0
| 0021AA |
| TU346 - Former Airmen Dining Hall, Bldg 21180: Achieve RC within 2 years from NTP. |
| At Award |
| 0022 |
| MY240 - Former Bldg 9310 |
$0
| 0022AA |
| MY240 - Former Bldg 9310: Achieve RIP within 2 years from NTP. |
| At Award |
$0
| 0023AA |
| TU670 - Bldg 11670: Achieve RIP within 2 years from NTP. |
| At Award |
$0
| 0024AA |
| TU077 - Bldg 7425: Achieve RIP within 3 years from NTP. |
| At Award |
$0
| 0025AA |
| CG147 - Bldg 8401: Achieve RIP within 3 years from NTP. |
| At Award |
$0
| 0026AA |
| TU174 - Bldg 9340: Achieve RIP within 3 years from NTP. |
| At Award |
$0
| 0027AA |
| SA228 - Bldg 07426: Achieve RIP within 3 years from NTP. |
| At Award |
| 0028 |
| MY247 - Former Bldg 6441 and 6451 |
$0
| 0028AA |
| MY247 - Former Bldg 6441 and 6451: Achieve RIP within 3 years from NTP. |
| At Award |
| 0029 |
| MY248 - Former Bldg 6442 and 6452 |
$0
| 0029AA |
| MY248 - Former Bldg 6442 and 6452: Achieve RIP within 3 years from NTP. |
| At Award |
| 0030 |
| MY249 - Former Bldg 6443 and 6453 |
$0
| 0030AA |
| MY249 - Former Bldg 6443 and 6453: Achieve RIP within 3 years from NTP. |
| At Award |
| 0031 |
| MY250 - Former Bldg 7306 and 7315 |
$0
| 0031AA |
| MY250 - Former Bldg 7306 and 7315: Achieve RIP within 3 years from NTP. |
| At Award |
| 0032 |
| MY251 - Former Bldg 7307 and 7316 |
$0
| 0032AA |
| MY251 - Former Bldg 7307 and 7316: Achieve RIP within 3 years from NTP. |
| At Award |
| 0033 |
| MY240 - Former Bldg 9310 |
$0
| 0033AA |
| MY240 - Former Bldg 9310: Achieve RIP within 2 years from NTP. |
| At Award |
$0
| 0034AA |
| SA251 - Bldg 06436: Achieve RIP within 3 years from NTP. |
| At Award |
| 0035 |
| SA280 - Bldg 6605 Former (CAP) |
$0
| 0035AA |
| SA280 - Bldg 6605 Former (CAP): Achieve RIP within 3 years from NTP. |
| At Award |
$0
| 0036AA |
| SA288 - Bldg 07437: Achieve RIP within 3 years from NTP. |
| At Award |
| 0037 |
| SS004 - Laundry Site |
$0
| 0037AA |
| SS004 - Laundry Site: Achieve RIP within 4 years from NTP. |
| At Award |
| 0038 |
| SD015 - Abres-B Launch Complex |
$0
| 0038AA |
| SD015 - Abres-B Launch Complex: Achieve RIP within 4 years from NTP. |
| At Award |
| 0039 |
| SD024 - Entomology Wash Rack |
$0
| 0039AA |
| SD024 - Entomology Wash Rack: Achieve RIP within 4 years from NTP. |
| At Award |
| 0040 |
| SS003 - Old Railroad Pumping Station |
$0
| 0040AA |
| SS003 - Old Railroad Pumping Station: Achieve RIP within 5 years from NTP. |
| At Award |
| 0041 |
| WP005 - Space Launch Complex (SLC) - 3E |
$0
| 0041AA |
| WP005 - Space Launch Complex (SLC) - 3E: Achieve RIP within 5 years from NTP. |
| At Award |
| 0042 |
| ST171 - Bldg 1110 - 1113: Achieve RIP within 5 years from NTP. |
$0
| 0042AA |
| ST171 - Bldg 1110 - 1113: Achieve RIP within 5 years from NTP. |
| At Award |
| 0043 |
| PL351 - Camp Cooke Fuel Distribution Lines |
$0
| 0043AA |
| PL351 - Camp Cooke Fuel Distribution Lines: Achieve Remedial Investigation within 2 years from NTP. |
| At Award |
$0
| 0044AA |
| TU003 - Bldg 5003: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0045AA |
| TU004 - Bldg 5004: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0046AA |
| TU008 - Bldg 5008D: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0047 |
| ZZ025 - TT-10-Area 7 |
$0
| 0047AA |
| ZZ025 - TT-10-Area 7: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0048 |
| TU044 - Bldg 1971 -2 |
$0
| 0048AA |
| TU044 - Bldg 1971 -2: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0049AA |
| TU055 - Bldg 1987: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0050 |
| TU067 - CC-34-9 and 26 |
$0
| 0050AA |
| TU067 - CC-34-9 and 26: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0051 |
| TU100 - Bldgs 13320, 13322 |
$0
| 0051AA |
| TU100 - Bldgs 13320, 13322: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0052AA |
| TU101 - Bldg 10103: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0053AA |
| TU103 - Bldg 13323: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0054AA |
| TU105 - Bldg 4105: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0055 |
| TU107 - Former Bldgs 660, 665, and 668 |
$0
| 0055AA |
| TU107 - Former Bldgs 660, 665, and 668: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0056 |
| TU114 - Former Bldg 475 |
$0
| 0056AA |
| TU114 - Former Bldg 475: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0057 |
| TU115 - Former Bldg 490 |
$0
| 0057AA |
| TU115 - Former Bldg 490: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0058AA |
| TU129 - Bldg 6512: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0059AA |
| TU130 - Bldg 13850: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0060AA |
| TU133 - Bldg 7133: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0061AA |
| TU136 - Bldg 4136: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0062 |
| TU187 - Former Bldg 10122 |
$0
| 0062AA |
| TU187 - Former Bldg 10122: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0063AA |
| TU196 - Bldg 3196: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0064AA |
| TU205 - Bldg 1974: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0065AA |
| TU206 - Bldg 2206: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0066AA |
| TU216 - Bldg 1731: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0067AA |
| TU221 - Bldg 1756: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0068 |
| SA323 - SS-C323 Bldg 6811 |
$0
| 0068AA |
| SA323 - SS-C323 Bldg 6811: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0069AA |
| TU328 - Bldg 13512: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0070 |
| TU347 - Former Camp Cook Dormitory |
$0
| 0070AA |
| TU347 - Former Camp Cook Dormitory: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0071 |
| TU358 - UST at Facility 23205 |
$0
| 0071AA |
| TU358 - UST at Facility 23205: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0072 |
| TU416 - Data Collection Reporting Station |
$0
| 0072AA |
| TU416 - Data Collection Reporting Station: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0073 |
| TU424 - NASA Administration Bldg |
$0
| 0073AA |
| TU424 - NASA Administration Bldg: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0074 |
| TU446 Elevan Fuel Oil USTs |
$0
| 0074AA |
| TU446 Elevan Fuel Oil USTs: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0075AA |
| TU448 - Bldg 4448: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0076 |
| TU459 - Camp Cooke Blocks(CC 37-4000, 4100, 4200, 4300) |
$0
| 0076AA |
| TU459 - Camp Cooke Blocks(CC 37-4000, 4100, 4200, 4300): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0077AA |
| TU472 - Bldg 2472: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0078AA |
| TU476 - Bldg 725: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0079AA |
| TU494 - Bldg 302: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0080AA |
| TU526 - Bldg 2526: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0081 |
| TU537 - Former Bldg 11168 and 11173: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
$0
| 0081AA |
| TU537 - Former Bldg 11168 and 11173: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0082 |
| TU544 - Correctional Facility |
$0
| 0082AA |
| TU544 - Correctional Facility: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0083 |
| TU574 - Bldgs 13122 and 13123 |
$0
| 0083AA |
| TU574 - Bldgs 13122 and 13123: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0084AA |
| TU578 - Bldg 13330: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0085AA |
| TU605 - Bldg 10103: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0086 |
| TU606 - Camp Cooke Bldgs (Airmen Dormitories) |
$0
| 0086AA |
| TU606 - Camp Cooke Bldgs (Airmen Dormitories): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0087 |
| TU608 - Camp Cook Bldgs (i) |
$0
| 0087AA |
| TU608 - Camp Cook Bldgs (i): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
| 0088 |
| TU649 - Camp Cook Bldgs (II) |
$0
| 0088AA |
| TU649 - Camp Cook Bldgs (II): Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0089AA |
| TU713 - Bldg 1713: Achieve Preliminary Assessment/Site Inspection within 2 years from NTP. |
| 3QFY15 |
$0
| 0090AA |
| TU788 - Bldg 1788: Achieve Preliminary Assessment/Site Inspection within 1 year from NTP. |
| 3QFY15 |
| 0091 |
| ST001 - BX Service Station |
$0
| 0091AA |
| ST001 - BX Service Station: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0091AB |
| ST001 - BX Service Station: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 00091AA or upon CO determination of bona fide need |
| 0091AC |
| ST001 - BX Service Station: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0091AB or upon CO determination of bona fide need |
| 0091AD |
| ST001 - BX Service Station: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0091AC or upon CO determination of bona fide need |
| 0091AE |
| ST001 - BX Service Station: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 00091AD or upon CO determination of bona fide need |
| 0092 |
| SS002 - Old Service Station |
$0
| 0092AA |
| SS002 - Old Service Station: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0092AB |
| SS002 - Old Service Station: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0092AA or upon CO determination of bona fide need |
| 0092AC |
| SS002 - Old Service Station: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 00092AB or upon CO determination of bona fide need |
| 0092AD |
| SS002 - Old Service Station: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0092AC or upon CO determination of bona fide need |
| 0092AE |
| SS002 - Old Service Station: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0092AD or upon CO determination of bona fide need |
| 0093 |
| WP008 - Site 8 Cluster |
$0
| 0093AA |
| WP008 - SITE 8 Cluster: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0093AB |
| WP008 - SITE 8 Cluster: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0093AA or upon CO determination of bona fide need |
| 0093AC |
| WP008 - SITE 8 Cluster: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0093AB or upon CO determination of bona fide need |
| 0093AD |
| WP008 - SITE 8 Cluster: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0093AC or upon CO determination of bona fide need |
| 0093AE |
| WP008 - SITE 8 Cluster: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0093AD or upon CO determination of bona fide need |
| 0094 |
| WP013 - Abres A Launch Complex |
$0
| 0094AA |
| WP013 - Abres A Launch Complex: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0094AB |
| WP013 - Abres A Launch Complex: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0094AA or upon CO determination of bona fide need |
| 0094AC |
| WP013 - Abres A Launch Complex: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0094AB or upon CO determination of bona fide need |
| 0094AD |
| WP013 - Abres A Launch Complex: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 3 years from 0094AC or upon CO determination of bona fide need |
| 0094AE |
| WP013 - Abres A Launch Complex: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0094AD or upon CO determination of bona fide need |
| 0095 |
| LF018 - Landfill Nos 3 & 4 |
$0
| 0095AA |
| LF018 - Landfill Nos 3 & 4: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0095AB |
| LF018 - Landfill Nos 3 & 4: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0095AA or upon CO determination of bona fide need |
| 0095AC |
| LF018 - Landfill Nos 3 & 4: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0095AB or upon CO determination of bona fide need |
| 0095AD |
| LF018 - Landfill Nos 3 & 4: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0095AC or upon CO determination of bona fide need |
| 0095AE |
| LF018 - Landfill Nos 3 & 4: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0095AD or upon CO determination of bona fide need |
$0
| 0096AA |
| SD019 - Bldg 836: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0096AB |
| SD019 - Bldg 836: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0096AA or upon CO determination of bona fide need |
| 0096AC |
| SD019 - Bldg 836: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0094AB or upon CO determination of bona fide need |
| 0096AD |
| SD019 - Bldg 836: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0096AC or upon CO determination of bona fide need |
| 0096AE |
| SD019 - Bldg 836: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0096AD or upon CO determination of bona fide need |
| 0097 |
| LF020 - Landfill No 1/Drum Disposal Site UST |
$0
| 0097AA |
| LF020 - Landfill No 1/Drum Disposal Site UST: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0097AB |
| LF020 - Landfill No 1/Drum Disposal Site UST: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0097AA or upon CO determination of bona fide need |
| 0097AC |
| LF020 - Landfill No 1/Drum Disposal Site UST: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0097AB or upon CO determination of bona fide need |
| 0097AD |
| LF020 - Landfill No 1/Drum Disposal Site UST: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0097AC or upon CO determination of bona fide need |
| 0097AE |
| LF020 - Landfill No 1/Drum Disposal Site UST: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0097AD or upon CO determination of bona fide need |
| 0098 |
| FT021 - Fire Training Area No 1 |
$0
| 0098AA |
| FT021 - Fire Training Area No 1: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0098AB |
| FT021 - Fire Training Area No 1: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0098AA or upon CO determination of bona fide need |
| 0098AC |
| FT021 - Fire Training Area No 1: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0098AB or upon CO determination of bona fide need |
| 0098AD |
| FT021 - Fire Training Area No 1: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0098AC or upon CO determination of bona fide need |
| 0098AE |
| FT021 - Fire Training Area No 1: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0098AD or upon CO determination of bona fide need |
| 0099 |
| LF022 - Landfill No 11 |
$0
| 0099AA |
| LF022 - Landfill No 11: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0099AB |
| LF022 - Landfill No 11: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0099AA or upon CO determination of bona fide need |
| 0099AC |
| LF022 - Landfill No 11: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0099AB or upon CO determination of bona fide need |
| 0099AD |
| LF022 - Landfill No 11: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0099AC or upon CO determination of bona fide need |
| 0099AE |
| LF022 - Landfill No 11: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0099AD or upon CO determination of bona fide need |
| 0100 |
| LF023 - Landfill No 5 |
$0
| 0100AA |
| LF023 - Landfill No 5: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0100AB |
| LF023 - Landfill No 5: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0100AA or upon CO determination of bona fide need |
| 0100AC |
| LF023 - Landfill No 5: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0100AB or upon CO determination of bona fide need |
| 0100AD |
| LF023 - Landfill No 5: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0100AC or upon CO determination of bona fide need |
| 0100AE |
| LF023 - Landfill No 5: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0100AD or upon CO determination of bona fide need |
$0
| 0101AA |
| SD025 - SLC-2E: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0101AB |
| SD025 - SLC-2E: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0101AA or upon CO determination of bona fide need |
| 0101AC |
| SD025 - SLC-2E: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0101AB or upon CO determination of bona fide need |
| 0101AD |
| SD025-SLC-2E: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0101AC or upon CO determination of bona fide need |
| 0101AE |
| SD025 - SLC-2E: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0101AD or upon CO determination of bona fide need |
| 0102 |
| SS027 - Exploded Missile Silo |
$0
| 0102AA |
| SS027 - Exploded Missile Silo: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0102AB |
| SS027 - Exploded Missile Silo: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0102AA or upon CO determination of bona fide need |
| 0102AC |
| SS027 - Exploded Missile Silo: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0102AB or upon CO determination of bona fide need |
| 0102AD |
| SS027 - Exploded Missile Silo: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0102AC or upon CO determination of bona fide need |
| 0102AE |
| SS027 - Exploded Missile Silo: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0102AD or upon CO determination of bona fide need |
| 0103 |
| SD031 - Missile Silo 576-C |
$0
| 0103AA |
| SD031 - Missile Silo 576-C: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0103AB |
| SD031 - Missile Silo 576-C: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0103AA or upon CO determination of bona fide need |
| 0103AC |
| SD031 - Missile Silo 576-C: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0103AB or upon CO determination of bona fide need |
| 0103AD |
| SD031 - Missile Silo 576-C: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0103AC or upon CO determination of bona fide need |
| 0103AE |
| SD031 - Missile Silo 576-C: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0103AD or upon CO determination of bona fide need |
| 0104 |
| SD032 - Missile Silo 576-D |
$0
| 0104AA |
| SD032 - Missile Silo 576-D: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0104AB |
| SD032 - Missile Silo 576-D: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0104AA or upon CO determination of bona fide need |
| 0104AC |
| SD032 - Missile Silo 576-D: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0104AB or upon CO determination of bona fide need |
| 0104AD |
| SD032 - Missile Silo 576-D: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0104AC or upon CO determination of bona fide need |
| 0104AE |
| SD032 - Missile Silo 576-D: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0104AD or upon CO determination of bona fide need |
| 0105 |
| SD033 - Missile Silo 576-E |
$0
| 0105AA |
| SD033 - Missile Silo 576-E: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0105AB |
| SD033 - Missile Silo 576-E: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0105AA or upon CO determination of bona fide need |
| 0105AC |
| SD033 - Missile Silo 576-E: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0105AB or upon CO determination of bona fide need |
| 0105AD |
| SD033 - Missile Silo 576-E: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0105AC or upon CO determination of bona fide need |
| 0105AE |
| SD033 - Missile Silo 576-E: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0105AD or upon CO determination of bona fide need |
| 0105 |
| SS050 - Bionetics Bldg |
$0
| 0106AA |
| SS050 - Bionetics Bldg: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0106AB |
| SS050 - Bionetics Bldg: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0106AA or upon CO determination of bona fide need |
| 0106AC |
| SS050 - Bionetics Bldg: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0106AB or upon CO determination of bona fide need |
| 0106AD |
| SS050 - Bionetics Bldg: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0106AC or upon CO determination of bona fide need |
| 0106AE |
| SS050 - Bionetics Bldg: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0106AD or upon CO determination of bona fide need |
| 0107 |
| ST060 - GSA Service Station |
$0
| 0107AA |
| ST060 - GSA Service Station: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0107AB |
| ST060 - GSA Service Station: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0107AA or upon CO determination of bona fide need |
| 0107AC |
| ST060 - GSA Service Station: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0107AB or upon CO determination of bona fide need |
| 0107AD |
| ST060 - GSA Service Station: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0107AC or upon CO determination of bona fide need |
| 0107AE |
| ST060 - GSA Service Station: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0107AD or upon CO determination of bona fide need |
| 0108 |
| DC142 - CE Maintenance Facility |
$0
| 0108AA |
| DC142 - CE Maintenance Facility, Bldgs 837 and 839: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP. |
| At Award |
| 0108AB |
| DC142 - CE Maintenance Facility, Bldgs 837 and 839: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0108AA or upon CO determination of bona fide need |
| 0108AC |
| DC142 - CE Maintenance Facility, Bldgs 837 and 839: Implement the elements of the approved optimized exit strategy in an Interim Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0108AB or upon CO determination of bona fide need |
| 0108AD |
| DC142 - CE Maintenance Facility, Bldgs 837 and 839: Implement the elements of the approved optimized exit strategy in an Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0108AC or upon CO determination of bona fide need |
| 0108AE |
| DC142 - CE Maintenance Facility, Bldgs 837 and 839: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0108AD or upon CO determination of bona fide need |
[additional Sub-CLINs beyond minimum performance objectives to be proposed consistent with the contractor's approach]
*NOTE: If additional Sub-CLINs are created prior to award pursuant to Sub-CLIN restructuring, some or all could be re-numbered to be sequential
**Projected Dates of Exercise are the anticipated award dates for the Sub-CLINs, but will be subject to the availability of funding and to the bona fide needs rule. Note that prior to task order award, the Government may restructure the Sub-CLINS based on the Offeror's proposal.