JPATS T-6A ADS-B (Out) Draft Past Performance Evaluation Matrix
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope and Magnitude
| Scope and Magnitude | |||
| Offeror - Contract Number | |||
| Recency | Yes/No | Start | End |
| Did contract performance end before ??? |
| Very Relevant | Relevant | Somewhat Relevant | Not Relevant | Rationale | |
| Scope (general requirments) | |||||
| Aircraft | |||||
| Design, develop, production, STC cert, retrofit | |||||
| Simulators | |||||
| Design, develop, production, retrofit | |||||
| Magnitude | |||||
| Quantity of Aircraft retrofitted | |||||
| Quantity of Simulators retrofitted | |||||
| Contract types and values | |||||
| Contract type and value (development) | EX. FFP; 2M | ||||
| Contract type and value (retrofit) | Ex. CPFF; 30M | ||||
| Total Contract Value $$$ | Ex. 32 M |
Complexity Matrix
| Complexity Matrix | ||||||
| Offeror - Contract Number | ||||||
| Subfactors | SOW Para | Very Relevant | Relevant | Somewhat Relevant | Not Relevant | Rationale |
| Subfactor 1: System Engineering | ||||||
| Criteria 1--Has delivered an Interface Control Document containing established flow-down requirements |
Criteria 2--Has developed Specification Requirements Verification Matrix
Criteria 3--Has developed System Engineering Management Plan (SEMP)
| 3.2; 3.2.1 | 3 out of 3 | 2 out of 3 | 1 out of 3 | 0 out of 3 | To support the ratings, information pulled directly from contract narrative will be documented here. |
| Subfactor 2: FAA Airworthiness Approval | |||||
| Criteria 1--Has experience obtaining a Supplemental Type Certificate (STC) directly from FAA |
Criteria 2--Has created and delivered Airworthiness Directives, Service Bulletins, and Advisory Data
| 3.2.2.1 | 2 out of 2 | 1 out of 2 | N/A | 0 out of 2 |
| Subfactor 3: Military Airworthiness | ||||
| Criteria 1--Developed, implemented, and maintained an airworthiness program and plan that resulted in Military Airworthiness certification |
| Criteria 2--Updated and maintained a Modified Airworthiness Certification Criteria document | 3.2.2.2 | 2 out of 2 | 1 out of 2 | N/A | 0 out of 2 |
| Subfactor 4: Aircraft Integration | |||||
| Criteria 1--Successfully installed avionics retrofit kit |
Criteria 2--Created and maintained an Integrated Master Schedule for avionics production and retrofit program
| 2 out of 2 | 1 out of 2 | N/A | 0 out of 2 | |
| Subfactor 5: Simulators Integration | ||||
| Criteria 1--Successfully installed simulator retrofit kit |
Criteria 2--Created and maintained an Integrated Master Schedule for simulator program 2 out of 2 1 out of 2 N/A 0 out of 2
NA--Past Performance Quality
| Offeror - Contract Number | ||||||||
| Subfactors | SOW Para | Exceptional | Very Good | Satisfactory | Marginal | Unsatisfactory | Not Applicable | Rationale |
| Subfactor 1: System Engineering | ||||||||
| Criteria 1 |
Criteria 2 Criteria 3
| etc | Insert Corresponding SOW paragraph | To support the ratings, information pulled directly from PPQs, Telephone Interviews, CPARS will be documented here. |
| Subfactor 2: FAA Airworthiness Approval | ||
| Criteria 1 |
Criteria 2 Criteria 3 etc Overview:
Positives:
Performance Observations:
| Subfactor 3: Military Airworthiness |
| Criteria 1 |
Criteria 2 Criteria 3 etc Overview:
Positives:
Performance Observations:
| Subfactor 4: Aircraft Integration |
| Criteria 1 |
Criteria 2 Criteria 3 etc Overview:
Positives:
Performance Observations:
| Subfactor 5: Simulators Integration |
| Criteria 1 |
Criteria 2 Criteria 3 etc Overview:
Positives:
Performance Observations:
Subfactor: Price - Evidence that contractor performed for cost proposed i.e. Cost Control Overview:
Positives:
Performance Observations: