Section_M_Sample_TEP_Calc.xlsx
XLSX spreadsheet 25 KB Posted
- Solicitation number
- FA8509-21-R-0003
About this file
This document contains a sample technical evaluation plan (TEP) and related federal contract opportunity notice for the Variable Speed Drogue (VSD) full rate production effort. The government requires production and delivery of VSD units, initial spare parts, support equipment, and data for installation on its MC-130J aircraft fleet. The acquisition will utilize the Delivery Protection Program to award an initial mission essential quantity to a proven source while an unproven source manufactures a first article for testing and qualification prior to receiving the option for the remaining requirement. The five-year contract will include one base year and four option periods. The TEP outlines sample pricing for a proven and unproven source under different award scenarios. The government seeks a vendor with expertise in the MC-130J and Sargent Fletcher Air Refueling Pod, as these customized parts are unavailable commercially.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Method of Manufacturing Sheet.pdf | ||
| PD439030.pdf | ||
| VSD_Drawings.pdf | ||
| SOW_8Apr2021.pdf | ||
| FA8509-21-R-0003.pdf | ||
| Exhibit_B_CDRL_B001.pdf | ||
| Exhibit_A_CDRLs_A001_A008.pdf | ||
| Exhibit_D_Initial_Spare_Parts_Kit_B.xlsx | XLSX spreadsheet | |
| DDForm1653_Transportation Requirements.pdf | ||
| Exhibit_C_Initial_Spare_Parts_Kit_A.xlsx | XLSX spreadsheet | |
| AFMC158_Packaging _Requirements.pdf | ||
| Attachment 01 of Section M -Sample TEP Calculation for VSD.xlsx | XLSX spreadsheet | |
| Section L - Instructions_Conditions and Notices to Offerors.pdf | ||
| Section M - Evaluation Factors for Award.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Section M, Attachment 1 - Sample TEP Calculations | Alternative 2, if proven source is not lowest offeror in Alternative 1: | ||||||||||||||||
| Alternative 1 Scenario: | Proven Source | Unproven Source | Proven Source: | Unproven Source: | |||||||||||||
| CLIN | Title | Pricing | Quantity | U/I | Unit Price | Price | Unit Price | Price | CLIN | Title | Pricing | Quantity | U/I | Unit Price | Price | Unit Price | Price |
| Bid A: (Unproven Source) (Alt 1) | Bid C: (Unproven Source) (Alt 2) | ||||||||||||||||
| 0001 | VSD First Article | FFP | 1 | EA | $ 110,000.00 | $ 110,000.00 | 0010 | VSD First Article | FFP | 1 | EA | $ 110,000.00 | $ 110,000.00 | ||||
| 0002 | VSD Production Units (Option) | FFP | 62 | EA | $ 110,000.00 | $ 6,820,000.00 | 0011 | VSD Production Units (Option) | FFP | 48 | EA | $ 110,000.00 | $ 5,280,000.00 | ||||
| 0003 | DATA (Exhibit B) | NSP | 1 | LO | 0012 | DATA (Exhibit B) | NSP | 1 | LO | ||||||||
| 0020 | DATA (Exhibit A) | NSP | 1 | LO | 0020 | DATA (Exhibit A) | NSP | 1 | LO | ||||||||
| First Article –Evaluation Factor (Govt Cost)* | $ 27,000.00 |
| Bid B: (Proven Source) (Alt 1) | Bid D: (Proven Source) (Alt 2) | ||||||||||||||
| 0004 | VSD Production Units | FFP | 62 | EA | $ 110,000.00 | $ 6,820,000.00 | 0013 | MEQ - VSD Production Units | FFP | 14 | EA | $ 100,000.00 | $ 1,400,000.00 | ||
| 0020 | DATA (Ehhibit A) | NSP | 1 | LO | 0014 | MEQ - VSD Production Units (Option) | FFP | 1 - 48 | EA | $ 100,000.00 | $ 4,800,000.00 | ||||
| 0020 | DATA (Ehhibit A) | NSP | 1 | LO | |||||||||||
| Bid B-1: (Proven Source) Alt 1 | Proven IDIQ Award: | $ 6,200,000.00 | Unproven IDIQ Award: | $ 5,390,000.00 | |||||||||||
| 0005 | Travel | CRNF | 1 | EA | $ 8,000.00 | $ 8,000.00 | |||||||||
| 0006 | Training | FFP | 1 | EA | $ 53,000.00 | $ 53,000.00 | Bid D-1 (Proven Source) - Other MEQ Requirements | ||||||||
| 0007 | VSD Support Equipment | FFP | 5 | EA | $ 20,000.00 | $ 100,000.00 | 0015 | MEQ - Travel | CR NF | 1 | EA | $ 8,000.00 | $ 8,000.00 | ||
| 0008 | VSD Initial Spre Parts (Kit A) | FFP | 1 | EA | $ 300,000.00 | $ 300,000.00 | 0016 | MEQ - Training | FFP | 1 | EA | $ 53,000.00 | $ 53,000.00 | ||
| 0009 | VSD Initial Spre Parts (Kit b) | FFP | 4 | EA | $ 100,000.00 | $ 400,000.00 | 0017 | MEQ - VSD Support Equipment | FFP | 5 | EA | $ 20,000.00 | $ 100,000.00 | ||
| Total | $ 861,000.00 | 0018 | MEQ - VSD Spare Parts Kit (Kit A) | FFP | 1 | EA | $ 300,000.00 | $ 300,000.00 | |||||||
| 0019 | MEQ - VSD Spare Parts Kit (Kit B) | FFP | 4 | EA | $ 100,000.00 | $ 400,000.00 | |||||||||
| Proven IDIQ Award: | $ 861,000.00 |
| NOTE: See Section M for different scenarios regarding options. | |||||||||||||||||
| Option 1 (FY 24) | |||||||||||||||||
| 1001 | VSD Production Units | FFP | 44 | EA | $ 120,000.00 | $ 5,280,000.00 | $ 120,000.00 | $ 5,280,000.00 | Option 1 (FY 24) | ||||||||
| 1020 | Data | NSP | 1 | EA | 1001 | VSD Production Units | FFP | 44 | EA | $ 120,000.00 | $ 5,280,000.00 | $ 120,000.00 | $ 5,280,000.00 | ||||
| 1020 | Data | NSP | 1 LO | ||||||||||||||
| Option 2 (FY 25) | LO | ||||||||||||||||
| 2001 | VSD Production Units | FFP | 18 | EA | $ 130,000.00 | $ 2,340,000.00 | $ 130,000.00 | $ 2,340,000.00 | Option 2 (FY 25) | ||||||||
| 2020 | Data | NSP | 1 | LO | 2001 | VSD Production Units | FFP | 18 | EA | $ 130,000.00 | $ 2,340,000.00 | $ 130,000.00 | $ 2,340,000.00 | ||||
| 2020 | Data | NSP | 1 LO | LO | |||||||||||||
| Option 3 (FY 26) | |||||||||||||||||
| 3001 | VSD Production Units | FFP | 8 | EA | $ 140,000.00 | $ 1,120,000.00 | $ 140,000.00 | $ 1,120,000.00 | Option 3 (FY 26) | ||||||||
| 3020 | Data | NSP | 1 | LO | 3001 | VSD Production Units | FFP | 8 | EA | $ 140,000.00 | $ 1,120,000.00 | $ 140,000.00 | $ 1,120,000.00 | ||||
| PROVEN TEP: | $ 16,421,000.00 | UNPROVEN TEP: | $ 15,670,000.00 | 3020 | Data | NSP | 1 LO | LO | |||||||||
| PROVEN TEP: | $ 15,801,000.00 | UNPROVEN TEP: | $ 14,130,000.00 | ||||||||||||||
| *NOTE: First Article –Evaluation Factor (Govt Cost) is a firm amount in accordance with FAR 9.306(i) Evaluation Cost Factor for First Article |
File details come from the government source that posted it. Updated .