Lead_Paint_Bldg-850_Bay_G_WO57154.xlsx

XLSX spreadsheet 52 KB Posted

Attached to
Bldg. 850 G Renovate For New Workload Federal contract opportunity
Solicitation number
FA8201-16-B-0002
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Lead Paint Survey Bldg. 850 Bay G

View the file

Other files for this federal contract opportunity

Other files attached to Bldg. 850 G Renovate For New Workload, newest first.
File Type Posted
060316_Specification.pdf PDF
060316_Cleanroom_HVAC_Loads.pdf PDF
Projector_PT-RZ570.pdf PDF
Bldg_850_Amend_04_Solicit.docx DOCX document
062116_Drawings.pdf PDF
Alltec_Screens_Manual_Screen_Info_and_Specifications.pdf PDF
B850_addendum1_QA-22_June_2016.pdf PDF
Bldg_850_Amend_03.docx DOCX document
Answers_to_Contractor_Questions_-_B850_-_3_June_2016.pdf PDF
060316_Cleanroom_HVAC_Loads.pdf PDF
General_Decision_Number_UT160104_22_April_2016_UT_104.pdf PDF
060316_Specification.pdf PDF
Amendment_02_-_FA8201-16-B-0002_-_Bldg_850_-_9_June_2016.pdf PDF
060316_Drawings.pdf PDF
BLD_850_Site_Visit_List.pdf PDF
BLDG_850_AMEND_01.docx DOCX document
General_Decision_Number.docx DOCX document
Asbestos_Report_Bldg-850_Bay_G_WO57154.xlsx XLSX spreadsheet
APPENDIX_C_MASTER_ON_or_OFF_BASE_UPDATED_March_2015.docx DOCX document
_3-3-15_SPECS_Final_Combined.pdf PDF
614162_-_HAFB_B850_Cleanroom.pdf PDF
TAB_K__1_Aug_11.pdf PDF
BLDG_850_bay_G_Solicitation_R3.doc DOC document
BASE_FACILITY_DESIGN_STANDARD.docx DOCX document
_Submittal_Register.pdf PDF
Final_B850_Design_Analysisr1.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Report

DEPARTMENT OF THE AIR FORCE
75TH CIVIL ENGINEERING (CEOHA)
HILL AIR FORCE BASE, UTAH
REQUESTER:Cary HawsDATE:24-March-2016
ORGANIZATION:309 MMXG
FROM:75TH CES/CEOHA
SUBJECT:Lead Based Paint (LBP) Survey,Building850 Bay G
WORK ORDER:57154
SCOPE OF WORK:Remodel South Section Bay G

Inspection Date: 24-February-2016 Inspector: Chase Johnson (Utah Certified Lead Inspector #PB-2125)

Niton used for this inspection: XRF Analyzer XL3t 300 (Serial #96588)

Building850 Bay G
Built in:1967
Limited lead-based paint identification has been completed for,Building850 Bay G

1-The table below summarizes the building components in building Building # that tested positive for LBP. These components should be segregated or abated prior to renovation or demolition, and a composite TCLP taken of the waste before disposal. (See attached results for further detail).

ComponentColorLead ReadingCondition
2" Floor LineYellow6.02Fair
Metal BollardYellow1.8Good
Metal DoorYellow1.15Good

2-The U.S. Department of Housing and Urban Development defines Lead-based paint as any paint, varnish, stain, or other applied coating that has 1mg/cm² as measured by an X-ray Fluorescence (XRF) Analyzer or laboratory analysis or 0.5 percent by weight (5,000µg/g by dry weight) by laboratory analysis, or more of lead. All other components tested were less than 0.80 mg/cm².

3-Any effort to disturb lead paint can create lead dust. Please ensure that appropriate abatement, cleanup, and disposal will be accomplished and that the appropriate safety measures are taken IAW 29 CFR 1926.62. If you have any questions please feel free to call Nickolas King at 586-7094.

Inspector: Chase Johnson (Utah Certified Lead Inspector #PB-2125)

Niton:XRF Analyzer XL3t 300 (Serial #96588)
Note:
Refer to "Readings" tab for all readings.
In order to print the entire LBP report select: "File", "Print", then select "Entire Workbook", "OK".

Readings

Building:850 Bay GInspector & Certification #:Chase Johnson (Utah Certified Lead Inspector #PB-2125)
Date:24-February-2016
Time:1245
Work Order:57154
Pre CalibrationPbL (mg/cm²)Calibration RangeModel#Serial #Post CalibrationPbL (mg/cm²)Calibration Range
XRF Analyzer XL3t 300 (Serial #96588)
2101.01Per 20 Second Reading2270.99Per 20 Second Reading
2110.912280.89
2120.952290.95
Range:.8 to 1.2Range:.8 to 1.2
XL NumberRoomSideStructureConditionSubstrateColorPbL(mg/cm2)NEG/POS
219Bay GSouth2" Floor LineFairConcreteYellow6.02POS
220Bay GSouthBollardGoodMetalYellow1.80POS
221Bay GSouth2" Floor LineGoodConcreteRed0.01NEG
222Bay GEastDoorGoodMetalYellow1.15POS
223Bay GEastWallGoodDrywallWhite0.01NEG
224Bay GSouthDoorGoodMetalBrown0.01NEG
225Bay GSouthDoor JambGoodMetalBrown0.01NEG
226Bay GSouthFloorPoorConcreteBlack0.11NEG
Traver Andreasen (Utah Certified Lead Inspector #PB-2085)
Chase Johnson (Utah Certified Lead Inspector #PB-2125)
Nickolas King (Utah Certified Lead Inspector #PB-1244)
Raudel Arteaga (Utah Certified Lead Inspector #PB-)
XRF Analyzer XL3t 300 (Serial #30660)
XRF Analyzer XL2 600 (Serial #56999)
XRF Analyzer XL3t 300 (Serial #96588)

image1.png image2.emf

File details come from the government source that posted it. Updated .