Pgh generator requirements.docx

DOCX document 25 KB Posted

Attached to
Replace Emergency Generator, B213 Project JLSS 21-0002 Federal contract opportunity
Solicitation number
FA671221B0003
Issued by
Department of the Air Force Reserve Command

View the file

Other files for this federal contract opportunity

Other files attached to Replace Emergency Generator, B213 Project JLSS 21-0002, newest first.
File Type Posted
sam B213 OF 1419 abstract of offers construction.pdf PDF
Solicitation Amendment FA671221B00030004 SF 30 add b213 Ampere Readings.pdf PDF
B213 Ampere readings.pdf PDF
Gen2.JPG JPG image
Gen4.JPG JPG image
SW3.JPG JPG image
TS1.JPG JPG image
TS3.JPG JPG image
JLSS 11-0013_Sheet 56 of 61_E011_Schedules.pdf PDF
JLSS 11-0013_Sheet 57 of 61_E012_Schedules.pdf PDF
Gen1.JPG JPG image
Gen3.JPG JPG image
Gen5.JPG JPG image
Sw4.JPG JPG image
contracting Only Questions And Answers Responses to Contractors Questions B213.pdf PDF
G-11 Base Composite Utilities 11 X 17 Bldg 213.pdf PDF
JLSS 11-0013_Sheet 58 of 61_FSE1_Schedules of Equipment and Details.pdf PDF
Solicitation Amendment FA671221B00030003 SF 30date extension and pics to 08272021.pdf PDF
Gen6.JPG JPG image
SW5.JPG JPG image
Bid CE RFI responses for B213 Generator.pdf PDF
JLSS 11-0013_Sheet 49 of 61_E006_Basement Power Plan.pdf PDF
JLSS 11-0013_Sheet 51 of 61_E007_First Floor Power Plan.pdf PDF
DavisBacon Act WD PA20210001 mod 8 as of 08062021.txt TXT text file
JB1.JPG JPG image
TS2.JPG JPG image
Gen7.JPG JPG image
SW1.JPG JPG image
SW2.JPG JPG image
JLSS 11-0013_Sheet 50 of 61_E006A_Alt Basement Power Plan.pdf PDF
Solicitation Amendment FA671221B00030002 SF 30 date extension 1.pdf PDF
Solicitation Amendment FA671221B00030001 SF 30.pdf PDF
01 34 00 submittal procedures.pdf PDF
014100 Env Spec Section (Rev 2019 AUG 14).pdf PDF
Solicitation - FA671221B0003.pdf PDF
D-B SOW B213 Generator June 2021.pdf PDF
01 32 00 Construction Progress Documentation.pdf PDF
01 50 00 temporary facilities and controls.pdf PDF
01 59 50 safety requirements.pdf PDF
Attachment to SOW - GENERATOR DESIGN REQUEST.pdf PDF
01 14 00 work restrictions.pdf PDF
01 40 00 quality requirements.pdf PDF
01 73 00 closeout procedures.pdf PDF
01 73 89 cutting and patching.pdf PDF
02 41 19 selective demolition.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.0GENERAL REQUIREMENTS
1.1Basis of Design
Cummins/Onan, Caterpillar, Kohler, or equal.
1.2Location Guidelines
Generators are usually located outside the facility with NEMA 3R enclosures.
Clear access of four (4) feet shall be provided and maintained around all four sides of the generator.
Provide a generator disconnect and prime mover shutdown per NEC 445.18.
1.3Size

The Contractor shall provide a submittal of the generator with the vendor’s sizing software. Information for loading the generator will be taken from the one-line. Two items must be addressed: startup inrush current and demand load. Manufacturers of generators incorporate various amounts of copper wiring in the alternator, two different means of control (permanent magnet generators or self-excited DC generators) and other reasons for different sizes to take care of motor inrush current. If the inrush current cannot be controlled, another manufacturer should be chosen. Getting a larger generator than the one approved will require re- approved by AFCEC. This approval process may take four months or more.

2.0ENVIRONMENTAL REQUIREMENTS
2.1Sulfur Content

Each compression ignition internal combustion engine must be optimized to run on diesel fuel containing a maximum of 15 ppm of sulfur content.

2.2 Emission Requirements

The model year of each generator shall be certified by the manufacturer to meet Tier 4 emission standards and the emissions standards contained within 40 CFR 60. 4201 or 40 CFR 60.4202, respectively (40 CFR 60 Subpart IIII - Standards of Performance for Stationary Compression Ignition Internal Combustion Engine [CI ICE]). Provide EPA Certificates of Conformity to EPA requirements for the model year of the engine procured.

3.0COMPONENTS
3.1Main Breaker

Provide a main breaker with the generator. Breaker shall be sized a minimum of 125% of the generator rated capacity and no more than 200% of the rated capacity.

· For 2000 Amps and greater, use large draw-out breakers with solid state tripping units.

· For 1800 Amps to 900 Amps, use insulated-case or molded-case breaker with solid state tripping units.

· Breakers 1000 Amps and above shall have ground fault protection.

· For 800 Amps or less, the breaker shall be a standard molded case breaker.

3.2Control Panel
3.2.1Outputs

Control panel for the generator shall provide the following outputs and provide a single point that personnel can determine the overall operational status of the generator.

· On-off: Provide a means of turning the generator on-off. In the “off” position, it will not auto start. In the “on” position, the generator will respond to the Automatic Transfer Switch (ATS) and crank up and run as the ATS signals it.

· The controller will also allow the generator to be cranked and run without engagement from the ATS for maintenance purposes.

· No controls or software shall be installed to automatically run the generator at specified intervals; any such controls that exist, shall be deactivated.

3.2.2 Gauges

Gauges/readings can be an electronic screen with means to select between the different readings. The following gauges shall be included:

· Oil pressure and water temperature

· Exhaust temperature

· AC metering – Volts, Amps, Hertz

· Phase selector switch (3 phase)

· Hour meter (non-resettable)

3.3 Radiator

Provide a radiator that is integral to the prime mover skid package.

When a generator is to be installed inside or within three (3) feet of fences/structures that block airflow, provide a pass through ventilation system. The exhaust opening shall be the same size or larger than the radiator screen and shall be placed immediately in front of and aligned with the radiator. Provide louvers and bird screen for the opening. Offsets may be provided if ductwork is provided to direct airflow through the opening.

3.4Exhaust Piping
3.4.1Muffler

The generator shall have a muffler designed to limit the noise to the local noise standard requirements.

If the generator is installed inside, the muffler shall be mounted horizontally and shall have heat shielding material installed to keep the temperature rise in the room at a minimum. Under the heat shielding material, calcium silicate shall be installed around the muffler in the same manner as around exhaust piping.

If the generator is installed outside, the muffler may be mounted horizontally or vertically.

If the muffler is outside or on top of or inside a NEMA 3R enclosure insulation is not required.

3.4.2 Piping

Exhaust piping shall be routed from the generator to the muffler to a point outside the facility.

Provide a minimum of 1” of calcium silicate insulation around piping with binders on nine (9)-inch centers. Then place a two (2)-inch calcium silicate insulation around the one (1)-inch insulation just applied with all seams and joints staged so they do not match. Place binders on nine (9)- inch centers.

Include a penetration spacer at the point of wall penetration. Immediately upon exiting a wall, the pipe shall be turned upwards. Install lengths of pipe so that the top of the pipe is at least two

(2) feet above the highest point of roof within 10 feet of the pipe. Provide a brace from the pipe attached to a point just below roof level. Avoid roof penetrations if possible. If roof penetration cannot be avoided, provide design for penetration and roof installation around the pipe.

When exhaust point from muffler is within 10 feet of a facility, route the piping from the muffler upwards to at least two (2) feet above the highest point of roof. Provide a brace from the pipe attached to a point just below roof level. No insulation is required on the piping.

When exhaust point is more than 10 feet from a facility, route the piping from the muffler pointed away from building. If the muffler is less than 10 feet high, route the pipe upwards to a point on the wall at least 10 feet above ground level, then point away from building.

If the generator is installed in a courtyard or alleyway with high roof lines on at least two sides, provide piping to reach a point two (2) feet above the roof height close to the generator.

Do not locate exhaust piping exhaust point within 20 feet radius of any supply/return air vent on adjacent buildings.

Provide spacers so that the exhaust piping is no closer than six (6) inches to structure when it is routed up a wall or other structure.

3.4.3 System

Each exhaust system from the generator shall be topped with a flap. The flap shall be equal or larger diameter than the piping and shall be gravity operated to close. The operating mechanism shall be free enough to allow the flap to open at least to a 45 to 60 degree angle during exhaust flow.

Provide a temperature sensor in the exhaust system with a gauge in the control panel.

4.0ABOVE GROUND FUEL TANKS
4.1Fuel for Stand-By Power Generation

Diesel is the fuel of choice for stand-by power generation at AFRC locations. Use of natural gas (NG), liquid petroleum gas (LPG), or bio-diesel fuels is not permitted. Primary fuel tanks shall be placed above ground, should be integral to the generator enclosure and located no closer than 5 feet from any building or structure. Below ground storage tanks are not permitted.

4.2Fuel Tanks
4.2.1Tank Design

Fuel tanks shall be sized to provide a 24 hour running time for the generation at 100% rated load.

Fuel tanks shall have double steel walls with interstitial concrete filler that complies with the following specifications. Provides secondary containment, leak monitoring, spill containment and overfill protection

· Provides lockable containment for filling operations

· UL 2085 listed – Protected Aboveground Tank for Flammable and Combustible Liquids

· Inner Tank shall be fabricated from minimum 3/16 inch steel and UL-142 listed – Steel Aboveground Tank for Flammable and Combustible Liquids

· Provides a minimum two-hour fire rating

· Fittings and protrusions are stainless steel

4.2.2 Fuel Tank Alarm Panel

A separate alarm panel shall be provided for each fuel tank with the following indicators:

· High Fuel Level red alarm lamp (labeled High)

· Low Fuel Level red alarm lamp (labeled Low)

· Tank Leak red alarm lamp (labeled Leak)

· Push To Test pushbutton

· Push To Reset pushbutton

· Push To Silence Alarm Horn pushbutton

· 90dB audible alarm horn Include an interstitial leak monitoring system to monitor tank leakage from the tank into the secondary compartment.

Fuel tanks shall be equipped with the following safety devices

· A visual indication of fuel level

· Automatic control of low and normal level of fuel into the tank

· A secondary automatic shut off of fuel delivery into tank at the 95% fill level

· Low level alarm in the event of failure of fuel supply system

· Grounding via #4 bare copper wire to the frame of the generator (both tank and fuel cooler)

· Normal vent pipe to outside that reaches a point that is 10 to 14 feet above ground level

· Pressure lifted emergency vent cap

· Anti-siphoning devices to prevent siphoning of fuel back into the tank Pittsburgh generator requirements of

File details come from the government source that posted it. Updated .