01 73 00 closeout procedures.pdf

PDF 72 KB Posted

Attached to
Replace Emergency Generator, B213 Project JLSS 21-0002 Federal contract opportunity
Solicitation number
FA671221B0003
Issued by
Department of the Air Force Reserve Command

View the file

Other files for this federal contract opportunity

Other files attached to Replace Emergency Generator, B213 Project JLSS 21-0002, newest first.
File Type Posted
sam B213 OF 1419 abstract of offers construction.pdf PDF
Solicitation Amendment FA671221B00030004 SF 30 add b213 Ampere Readings.pdf PDF
B213 Ampere readings.pdf PDF
Gen2.JPG JPG image
Gen4.JPG JPG image
SW3.JPG JPG image
TS1.JPG JPG image
TS3.JPG JPG image
JLSS 11-0013_Sheet 56 of 61_E011_Schedules.pdf PDF
JLSS 11-0013_Sheet 57 of 61_E012_Schedules.pdf PDF
Gen7.JPG JPG image
SW1.JPG JPG image
SW2.JPG JPG image
JLSS 11-0013_Sheet 50 of 61_E006A_Alt Basement Power Plan.pdf PDF
Pgh generator requirements.docx DOCX document
Gen1.JPG JPG image
Gen3.JPG JPG image
Gen5.JPG JPG image
Sw4.JPG JPG image
contracting Only Questions And Answers Responses to Contractors Questions B213.pdf PDF
G-11 Base Composite Utilities 11 X 17 Bldg 213.pdf PDF
JLSS 11-0013_Sheet 58 of 61_FSE1_Schedules of Equipment and Details.pdf PDF
Solicitation Amendment FA671221B00030003 SF 30date extension and pics to 08272021.pdf PDF
Gen6.JPG JPG image
SW5.JPG JPG image
Bid CE RFI responses for B213 Generator.pdf PDF
JLSS 11-0013_Sheet 49 of 61_E006_Basement Power Plan.pdf PDF
JLSS 11-0013_Sheet 51 of 61_E007_First Floor Power Plan.pdf PDF
DavisBacon Act WD PA20210001 mod 8 as of 08062021.txt TXT text file
JB1.JPG JPG image
TS2.JPG JPG image
Solicitation Amendment FA671221B00030002 SF 30 date extension 1.pdf PDF
Solicitation Amendment FA671221B00030001 SF 30.pdf PDF
01 34 00 submittal procedures.pdf PDF
014100 Env Spec Section (Rev 2019 AUG 14).pdf PDF
01 14 00 work restrictions.pdf PDF
01 40 00 quality requirements.pdf PDF
01 73 89 cutting and patching.pdf PDF
02 41 19 selective demolition.pdf PDF
Solicitation - FA671221B0003.pdf PDF
D-B SOW B213 Generator June 2021.pdf PDF
01 32 00 Construction Progress Documentation.pdf PDF
01 50 00 temporary facilities and controls.pdf PDF
01 59 50 safety requirements.pdf PDF
Attachment to SOW - GENERATOR DESIGN REQUEST.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Bid Set

911th Airlift Wing Close Out Procedures 01 73 00 - 1

SECTION 01 73 00

CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Inspection procedures.

2. Project record documents.

3. Operation and maintenance manuals.

4. Warranties.

5. Instruction of Government's personnel.

6. Final cleaning.

1.02 PRELIMINARY FINAL INSPECTION

A. A meeting shall be held with the Contractor, Contracting Officer, and other designated representatives as deemed necessary by the Contracting Officer to discuss deficiencies, establish standards for quality of acceptance and to establish a beneficial occupancy date. This meeting will be held when the Contractor’s work is substantially complete.

1.03 PRE-FINAL INSPECTION

A. Contractor Preliminary Procedures: Complete the following before requesting pre-final inspection.

1. Complete startup testing of systems.

2. Complete final cleaning requirements, including touchup painting.

3. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

4. Conduct own inspection, identifying items to be corrected. Submit this list to the Contracting Officer along with time frame when the items needing corrected shall be completed.

B. Inspection: On receipt of request, Contracting Officer will either proceed with inspection or notify Contractor of unfulfilled requirements. If upon inspection by the Contracting Officer more than five deficiencies are identified, then the inspection shall immediately terminate and be rescheduled when the contractor corrects all deficiencies and then notifies the Contracting Officer in writing that all deficiencies are corrected.

01 73 00 - 2

1. Reinspection: The Contractor shall request reinspection when the Work identified in the pre-final inspection as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final Completion.

1.04 FINAL INSPECTION

A. Inspection: The Contractor shall submit a written request for final inspection for acceptance.

On receipt of request, Contracting Officer will either proceed with inspection or notify Contractor of unfulfilled requirements. Contracting Officer will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in the final inspection is incomplete is completed or corrected.

1.05 WARRANTIES

A. Provide one (1) bound copies of all warranty documents, organized into an orderly sequence based on the table of contents of the Project Manual.

1. Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

B. Provide copy of each warranty in an electronic format as a closeout submittal.

1.06 OPERATION AND MAINTENANCE MANUALS (O&M)

A. Provide one (1) bound copies of all Operation and Maintenance (O&M) Manuals, organized into an orderly sequence based on the table of contents of the Project Manual.

1. Bind manuals in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate manual. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "O & M MANUAL," Project name, and name of Contractor.

01 73 00 - 3

B. Provide copy of operation and maintenance manuals in an electronic format as a closeout submittal.

PART 2 PRODUCTS (NOT USED)

PART 3 PART 3 - EXECUTION

3.01 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

1. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean all surfaces affected by construction activities, including hallways, rooms, and conference areas. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program.

2. Sweep concrete floors broom clean in unoccupied spaces.

3. Vacuum carpet and similar soft surfaces, removing debris and excess nap; shampoo if visible soil or stains remain.

4. Remove labels that are not permanent.

5. Wipe surfaces of mechanical and electrical equipment, elevator equipment, and similar equipment.

6. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

7. Replace parts subject to unusual operating conditions.

8. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.

9. Subparagraph below is a major work item that may be disruptive to closeout procedures.

10. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. Replace burned-out bulbs, and those noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

11. Leave Project clean and ready for occupancy.

12. Remove all debris, sweep exterior concrete and other paved surfaces to a broom-clean condition.

B. Comply with safety standards for cleaning.

01 73 00 - 4

C. Remove waste materials from Project site and dispose of lawfully.

1. Do not burn waste materials.

2. Do not bury debris or excess materials on Government’s property.

D. Do not discharge volatile, harmful, or dangerous materials into drainage systems.

END OF SECTION