Attachment JA-13 SECTION 01010-1
SECTION 01010
GENERAL REQUIREMENTS
5/01
PART 1 GENERAL
1.1 PROJECT INFORMATION
1.1.1 Contract Drawings and Specifications
1.2. SUBMITTALS
Submittals shall be submitted in accordance with Section 01300, SUBMITTALS.
1.2.1. Administrative or Close-out Submittals
a. Construction Phasing Sequence Plan
b. As-built drawings
c. Quality Control Plan
1.3. GENERAL DESCRIPTION
1.3.1. Location
The project is located at Dobbins Air Reserve Base, Georgia.
1.3.2. Project Description
Provide all labor, tools, equipment, materials, services and supervision necessary to renovate building 904 as specified in the Statement of Work; to include but not limited to: interior and exterior painting; floor coverings; standing seam metal roof; electric system and energy efficient lighting; HVAC repair and connect all systems to Base EMCS; fire protection system; new plumbing fixtures, accessories, toilet partitions and exterior covered storage area.
The contractor shall conform to Dobbins ARB operating procedures defined in paragraph 3.4. Operating procedures will be briefed at the Pre-Construction Meeting.
1.4. GOVERNMENT INSPECTOR
The Base Civil Engineer, or his authorized representative, is designated as the representative of the Contracting Officer for the purpose of technical surveillance of workmanship and inspection of materials for work being performed under this contract. This clause does not authorize anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract.
Attachment JA-13 SECTION 01010-2
1.5. ORAL STATEMENTS
No oral statement by any government official shall in any manner or degree modify or otherwise affect the terms of this contract.
1.6. NO GOVERNMENT WAIVER
The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred will not be construed as a waiver or relinquishment to any extent of the right to assert or rely upon such terms or option on any future occasion.
1.7. AS-BUILT RECORDS
1.7.1. AS-BUILT DRAWINGS
Maintain at the jobsite 2 sets of full-size contract drawings. Any deviations from the contract drawings shall be marked legibly and accurately with a red pen. These drawings shall be available for review by the Contracting Officer at all times. Submit one marked set of prints to the Contracting Officer no later than 30 calendar days after work is deemed substantially performed or beneficial occupancy is taken.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1. BASE REGULATIONS
The Contractor and his employees and subcontractor shall become familiar with and obey all base regulations, including fire, traffic, airfield, safety, environmental, and security regulations. Regulations are available upon request. All personnel employed on subject contract shall keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless previously cleared for such entry.
The Contractor's equipment shall by conspicuously marked for identification.
3.2. WORK SCHEDULE
The Contractor shall schedule his work to cause the least amount of interference with base operations. Work schedules shall be subject to the approval of the Contracting Officer. Under no circumstances shall fire water system be out of service for more than 5 calendar days. Permission to interrupt any base roads and/or utility service shall be requested in writing a minimum of 10 calendar days prior to the desired date of interruption. Interruption shall not take place without specific approval from the Contracting Officer.
3.2.1. Not Used
3.3 WORK HOURS
The normal hours of work for the performance of this contract will be from 7 a.m. to 4 p.m., except as otherwise expressly provided in this contract.
The workdays will by Monday through Friday, with Federal holidays excluded. Alternate work hours require written permission of the
Attachment JA-13 SECTION 01010-3
Contracting Officer. The contractor must submit a written request for permission to work to the Contracting Officer at least 2 working days in advance of the date when the contractor desires to deviate from the normal hours and days. Permission to deviate will be predicated on complete justification for the request after due consideration to a larger work force and more equipment during normal hours, and providing the contractor defrays the additional costs to the Government including, but not limited to, inspection computed in accordance with existing Government regulations. If permission is granted by the Contracting Officer, written authority will be furnished to the contractor prior to the date the contractor desires to deviate from the normal hours or days. The Contracting Officer may also direct performance as authorized by the General Provisions by reference clause entitled “Schedule for Construction Contract.” The contractor shall be responsible for government inspection costs associated with after hours work.
3.4 OPERATIONS ON THE AIRFIELD
All access to or through airfield areas shall be coordinated with the Contracting Officer and with the Chief of Airfield Management. The Contractor shall, at all times that he is on the airfield, be in verbal and visual contact with the control tower. The control tower and the Chief of Airfield Management shall be verbally informed when the work is complete and all equipment, labor, and materials have been removed from the airfield by the Contractor. The Chief of Airfield Management shall conduct a visual runway check to ensure that all contractor tools, equipment, employees and debris have been removed before opening the runway to aircraft traffic.
Attachment JA-13 SECTION 01010-4
3.4.1 Aircraft Traffic Interruption
The operation of equipment and the performance of work upon and in the vicinity of airfields shall be coordinated with the Contracting Officer and with the Flight Operations Officer. Neither equipment nor personnel shall use any portion of an airfield without permission of these officers unless the runway is closed. The airfield is active and work interrup-tions may occur for emergency or special mission purposes.
3.4.2 Clean-up
The Contractor shall clean debris from the runway surface as he proceeds with the work. The “clean as you go concept” is necessary to ensure a clean surface is available if there is an aircraft emergency.
3.5. EXISTING WORK
The removal or altering in any way of existing work shall be carried on in such a manner as to prevent personal injury or damage to any portions of the existing work that remains.
3.6. SANITATION
Adequate sanitary conveniences of a type approved for use by persons employed on the work shall be provided. Sanitary conveniences shall be properly secluded from public observation, and maintained by the Contractor in such a manner as required or approved by the Contracting Officer. Maintain these conveniences at all times without nuisance. Upon completion of the work, the contractor shall remove the conveniences from the premises, leaving the premises clean and free from nuisance.
3.7. UTILITIES
All reasonable quantities of government provided utilities shall be made available to the contractor without charge. Any temporary telephone service shall be requested by the contractor from the local Telephone Company providing service to Dobbins ARB. The contractor shall not tamper with, connect or access any Government communication facility, equipment or cable without express written consent from the Contracting Officer.
Any temporary connections or lines that may be required shall be installed, maintained, and removed by the Contractor at his expense and in a manner satisfactory to the Contracting Officer. Contractor shall remove all temporary connections and lines prior to final acceptance of the construction.
3.8. UTILITY SERVICE INTERRUPTION
The Government shall not be held responsible for interruptions of utility services and shall not be liable for Contractor delays, damages, or increased costs occasioned by any such interruption of services.
3.9. OPTIONAL REQUIREMENTS
Where a choice of materials or methods, or both, is permitted in this contract, the Contractor will be given the right to exercise the option unless otherwise required by the specification.
Attachment JA-13 SECTION 01010-5
3.10. MATERIAL APPROVAL SUBMITTAL PREPARATION
"Material and Workmanship" shall be accomplished on and in accordance with the instructions to AF Form 3000, Material Approval Submittal. Material Approval Submittals shall contain complete information for the product proposed. The information shall be in enough detail to allow the Government to determine acceptability. Information to be provided includes, but is not limited to: a description of all salient features of the product, descriptive literature and manufacturer's cut sheet (if available), plus an explanation as to precisely why and how the material or item submitted meets or exceeds all required functions, performance and quality specifications.
3.11. MATERIAL DISPOSITION
3.11.1. Material/Equipment Title
Title to materials and equipment to be demolished, except Government salvage and historical items, is vested in the Contractor upon receipt of notice to proceed. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed.
3.11.2. Contractor Salvage
Contractor shall salvage items and materials to the maximum extent possible. Material salvaged for the Contractor shall be stored as approved by the Contracting Officer and removed from Government property before completion of the contract. The contractor shall not sell salvaged material on the site.
3.12. CLEAN-UP
Remove and transport debris in a manner that prevents spillage on streets or adjacent areas. Local regulations regarding hauling and disposal shall apply. The contractor shall maintain a clean and orderly work site.
3.13. SAFETY REQUIREMENTS
The contractor shall initiate and maintain programs that comply with the provisions of 29 CFR parts 1926 and 1910 of the Occupational Safety and Health Standards. These programs shall include the education and training of employees and subcontractors’ personnel in the recognition, avoidance, and prevention of unsafe conditions and practices.
3.14. FIRE PROTECTION
The contractor shall be responsible for furnishing adequate and proper fire protection during all phases of work on site. Contact the base Fire Department in the event of emergency.
3.15. FACILITIES AND SERVICES
The contractor is responsible for storage of all materials. Storage areas shall be shown on the site plan and approved by the Contracting Officer.
Attachment JA-13 SECTION 01010-6
3.16. RESTRICTIONS
3.16.1. Radio Transmitter Restrictions
The contractor shall conform to the restrictions and procedures for the use of radio transmitting equipment, as directed. Transmitters are to be provided by the contractor and should be able to tune in on a frequency of
165.1125. Do not use transmitters without prior approval.
3.16.2. Materials Burning
Burning of trash, timber and any other debris on government property is not permitted.
3.17. REQUIRED CONTRACTOR ACTIONS
3.17.1. BASE PERMITS
Obtain these pursuant to paragraph 3.1 of this specification. Permits are required for, but are not necessarily limited to, welding, and digging.
3.17.1.1. Government Digging Permits
The requirement for digging or excavation permits (AF Form 103) shall be applicable for Government-owned utilities such as water, gas, electrical, sewer, fiber optics, telephone cable and communication cables for radar, weather and navigational aids cable.
3.17.1.1.1. Procedures for Government Digging Permits
a) Contractor shall not dig anywhere on Dobbins ARB without a valid digging permit.
b) Contractor shall notify the Contracting Officer in writing to request a digging permit.
c) Contractor shall stake the area on site where digging is to occur.
This shall be done the same day the dig permit is requested.
d) Government has 14 days to issue an initial digging permit, and the government digging permit is valid for 30 days.
e) Contractor shall notify the Contracting Officer in writing to request a renewal of a digging permit. A request will not be accepted more than 10 days prior to expiration. The Government has 7 days to issue a renewal to a digging permit.
f) If the digging permit is more than 60 days old, a renewal will not be issued and the contractor must request a new digging permit.
g) Once a digging permit is issued, the contractor must hand dig and locate all marked utilities within 5 feet of the area to be worked on.
Contractor shall fill all holes prior to project completion.
h) If, during the life of the digging permit, utility markings are removed by the contractor or his subcontractor the contractor shall be responsible for replacing all markings.
Attachment JA-13 SECTION 01010-7
3.17.1.2. UPC Digging Permits
The procedures set forth for Government-owned utilities shall not apply to utilities which are governed by the Utilities Protection Center (UPC) under the auspices of the State of Georgia. UPC utilities on Dobbins ARB include television cable, telephone cables, data cables, etc..
Procedures for utilities governed by the UPC shall be followed in accordance with Georgia House Bill No. 1651, dated April 4, 1990. The contractor is required to obtain a UPC digging permit prior to digging on Dobbins ARB. The government is not responsible for issuing or monitoring UPC digging permits.
3.17.1.3. Utility Damage
The Contractor must immediately notify the Government technical representative and UPC in the event that utility damage occurs. If damage to utilities is due to contractor non-compliance with permit instructions or contract requirements, repairs required shall be at the contractor’s expense. Fiber optic cables, which cannot be repaired to meet the minimum allowable decibels, will be replaced at the contractor’s expense.
3.17.1.4 Welding Permits
Obtain welding permits on a daily basis from the Base Fire Department.
3.17.2. Severe Weather Protection
In the event of severe weather, the contractor shall take precautions to minimize any danger to persons, and protect the work and any nearby Government property. Precautions shall include, but are not limited to, closing openings; removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work.
3.17.3. Clean Tire Policy
Dobbins ARB has a clean tire policy at work sites. The purpose of this policy is to reduce or eliminate the transport of mud from the work area onto public rights-of-way by motor vehicles leaving the site or by runoff from the site. Clean and remove mud from the wheels of vehicles prior to entrance to public rights-of-way. The site exit shall be maintained in order to prevent tracking or flow of mud onto public rights-of-way.
Immediately remove all materials spilled, dropped, washed or tracked from any vehicle or site onto any roadway or into any storm drain. Compliance with the clean tire policy, by Contractor and Sub-contractor personnel, shall be the sole responsibility of the Contractor.
3.17.4. Erosion and Sediment Control
Take positive steps to minimize siltation and erosion during the work.
Comply with the requirements of Section 01560, drawings and all other related specification sections.
3.17.5. Environmental Requirements
The Contractor and all work to be performed on Dobbins ARB shall comply with the requirements of Section 01560.
Attachment JA-13 SECTION 01010-8
3.17.6. Quality Control Plan
The contractor shall be required to institute a comprehensive Quality Control Program in order to assure himself and the Government that all materials and workmanship are in strict accordance with the provisions of the specifications. Within 10 calendar days after receipt of Notice to Proceed, the contractor shall submit his Quality Control Program Plan to the Contracting Officer for review and approval. The plan shall contain, at a minimum, identification of procedures for quality control, the type and model of major pieces of equipment to be used on-the-job, ordering procedures for materials, and procedures to ensure adequate progress.
3.17.7. Hazardous Spill Reporting
The contractor shall report any spill of oil or hazardous substances to the Fire Department service desk at Ext. 117 from a government phone, or
(770) 919-4840 from a commercial phone (24 hours per day, 7 days per week). The contractor shall take every reasonable precaution to prevent the spillage of oil or other hazardous substances.
--- END OF SECTION ---
| SECTION 01010 |
| GENERAL REQUIREMENTS |
| 5/01 |
| PART 1 GENERAL |
| 1.1 PROJECT INFORMATION |
| 1.1.1 Contract Drawings and Specifications |
1.2. SUBMITTALS
| Submittals shall be submitted in accordance with Section 01300, SUBMITTALS. |
| 1.2.1. Administrative or Close-out Submittals |
| 1.3. GENERAL DESCRIPTION |
| 1.3.1. Location |
| 1.3.2. Project Description |
| 1.4. GOVERNMENT INSPECTOR |
| 1.5. ORAL STATEMENTS |
| 1.6. NO GOVERNMENT WAIVER |
| 1.7. AS-BUILT RECORDS |
| 1.7.1. As-Built Drawings |
| PART 2 PRODUCTS (Not Applicable) |
| PART 3 EXECUTION |
| 3.1. BASE REGULATIONS |
| 3.2. WORK SCHEDULE |
| 3.3 WORK HOURS |
| 3.4 OPERATIONS ON THE AIRFIELD |
| 3.4.1 Aircraft Traffic Interruption |
| 3.4.2 Clean-up |
| 3.5. EXISTING WORK |
| 3.6. SANITATION |
| 3.7. UTILITIES |
| 3.8. UTILITY SERVICE INTERRUPTION |
| 3.9. OPTIONAL REQUIREMENTS |
| 3.10. MATERIAL APPROVAL SUBMITTAL PREPARATION |
| 3.11. MATERIAL DISPOSITION |
| 3.11.1. Material/Equipment Title |
| 3.11.2. Contractor Salvage |
| 3.12. CLEAN-UP |
| 3.13. SAFETY REQUIREMENTS |
| 3.14. FIRE PROTECTION |
| 3.15. FACILITIES AND SERVICES |
| 3.16. RESTRICTIONS |
| 3.16.1. Radio Transmitter Restrictions |
| 3.16.2. Materials Burning |
| Burning of trash, timber and any other debris on government property is not permitted. |
| 3.17. REQUIRED CONTRACTOR ACTIONS |
| 3.17.1. Base Permits |
| 3.17.1.1. Government Digging Permits |
| 3.17.1.1.1. Procedures for Government Digging Permits |
| 3.17.1.2. UPC Digging Permits |
| 3.17.1.3. Utility Damage |
| 3.17.1.4 Welding Permits |
| Obtain welding permits on a daily basis from the Base Fire Department. |
| 3.17.2. Severe Weather Protection |
| 3.17.3. Clean Tire Policy |
| 3.17.4. Erosion and Sediment Control |
| 3.17.5. Environmental Requirements |
| 3.17.6. Quality Control Plan |
| 3.17.7. Hazardous Spill Reporting |