1651_-_Design_RFI.pdf

PDF 16 KB Posted

Attached to
B1651 Renovate Building Federal contract opportunity
Solicitation number
FA6675-15-R-0004
Issued by
Department of the Air Force Reserve Command

About this file

Clarification

View the file

Other files for this federal contract opportunity

Other files attached to B1651 Renovate Building, newest first.
File Type Posted
1651_-_RFI_No._4_-_Lighting__Electrical.pdf PDF
1651_-_RFI_No._4_-_Lighting_ _Electrical.pdf PDF
RFI_-RFC_FORM_20150420_0004.pdf PDF
FA6675-15-R-0004-0003.doc DOC document
RFI's_1 2 3_FA6675-15-R-0004-signed.pdf PDF
FA6675-15-R-0004-0002.pdf PDF
FA6675-15-R-0004-00001.pdf PDF
Binder1_Specifications_Div_001_DDPM_14-0002.pdf PDF
2015.03.13_Final_Specifications.pdf PDF
2015-03-11_FINAL_DRAWINGS.pdf PDF
RFI_-RFC_FORM_20150420.doc DOC document
FA6675-15-R-0004_B1651_Renovate_Building.pdf PDF
DBA_WD_TX150322_20150306_TX322.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION / CLARIFICATION FORM

RFI NO.:

PROJECT NAME: Renovation of B1651 CONTRACTOR NAME: Gulf Coast Architecture PROJECT NO: DDPM 140002 E-MAIL ADDRESS: charles.tehan@us.af.mil SUBJECT: Mechanical Piping DRAWING REFERENCE/ DETAIL: M-300 & M-402

RFI REQUEST: From 2nd Contractor Site Visit

Will the refrigerant lines be piped underground or over the sidewalk from the main heat pumps located inside of the brick mechanical equipment enclosure?

ISSUED BY: Charles D. Tehan (Base CE) DATE ISSUED: 12 Aug 2015 RESPONSE NEEDED BY: 21 Aug 2015

(__)ATTACHMENT SENT UNDER SEPARATE COVER

RFI RESPONSE / CLARIFICATION:-

Government to complete following sections:

The refrigerant lines running from the main heat pumps located within the brick mechanical equipment enclosure to B1651 shall be run underground to Room 106 through a 6” diameter schedule 40 PVC pipe. Reference drawings M-300 & M-402 for addition information

ISSUED BY:

Charles D. Tehan, GS-11, Engineering Technician

DATE ISSUED:

12 Aug 2015

(__)ATTACHMENT SENT UNDER SEPARATE COVER

The above response clarifies and interprets the Contract Documents and may include minor changes in the work.