1. Are there as-built drawings that can be provided of the facility? Attached

2. Room 101 calls for Replace/Repair Drywall – is the drywall to be repaired or replaced?. Yes, Replace Drywall

3. Room 107 – Note calls for VCT and base boards to be removed and replaced with new. Existing floor is Tile and Wd. Base boards, is the tile and wood base boards to be removed? No tile and wood baseboard will remain.

4. Rooms 105 and 106 calls for VCT tiles and base boards to be removed. Existing floor is painted concrete. Are we to install new VCT and base or leave as existing? NO, leave as existing.

5. Can a VCT spec be provided so all parties are pricing the same? Attached

6. Room 110 – no ceiling work is mentioned however, there are water damaged ceiling tiles and missing tiles. Is the entire room to receive new tiles? Please refer to SOW 3.1.6.

7. Is there a Mold remediation and Asbestos report available? Yes.

8. If active mold or asbestos is encountered, how will that be handled? Need to notify the contracting officer (CO) as per SOW 2.1.

9. Room 201 calls for drywall to be replaced/repaired along the exterior. Please provide location and extent along with if it is to be replace or repaired. Walls appear to be in good condition.

Replace / Repair is NOT needed.

10. There is an existing wood chair rail on all the walls. Is this to be carefully removed and reinstalled? NO. Replace / Repair is NOT needed.

11. The second floor calls for new carpet, is this to be carpet squares or rolled goods? Please provide a spec as to the material to be installed. Please follow Spec 09 68 00 attached.

12. Can a second site visit be scheduled once these RFIs are responded to and the scope of work is properly identified and quantified? No

13. Is there an asbestos survey available for the building? Yes

14. Will there be a revision to the scope of work to address building envelope issues noted at the site visit? No, do not deviate from SOW and Specs.