This document contains a constructability review checklist for the Incirlik Air Base Multiple Award Construction Contract opportunity. The checklist covers key areas for construction projects such as general considerations, the construction site, architectural and structural elements, mechanical and plumbing systems, electrical systems, environmental factors, fire alarm systems, and requests input from design engineers and inspectors. It includes over 100 questions to evaluate constructability for areas like site access, building occupancy during construction, utility disruptions, hazardous materials, equipment specifications and drawings. The purpose is to conduct thorough reviews at 35%, 65% and 95% design stages to identify potential issues.

The related federal contract opportunity is for the Incirlik Air Base Multiple Award Construction Contract solicitation. The requirement is to provide construction services to Incirlik Air Base in Turkey. The solicitation is in pre-planning with an anticipated posting date of June 14, 2018. The contracting agency is the Department of the Air Force United States Air Forces in Europe - Air Forces Africa. The MAC contract will allow for issuing firm-fixed price task orders for various construction projects.

FA5685-18-R-0003 - Attachment 8 - INC-1108

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Final Constructability Review Checklist Items

*The checklist must be filled out by hand
PROJECT NUMBER & TITLE:Date:
Type: 35%:_______, 65%:_______, 95%:_______
SECTION I: GENERAL
NO:ITEMYESNON/A
1Is there an impact on the user and/or facility occupier?
a. Will the facility be completely turned over to construction?
b. If answer to 1a is NO than is there a phasing plan?
c. If answer to 1b is NO than is the work safe to be conduceted while bldg occupied and in use?
d. Is the user notified of commencement of work?
e. To minimize impact to user(s); is the contract performance period broken down to material ordering and construction time?
2Does the project impact multiple facilities?
a. If YES is there an identified maximum number of facilities that can be worked on at one time?
b. Is it clear when the contractor will be allowed to additional facilities?
c. Is it possible for one inspector to work that many facilities, and maintain several other projects?
d. Is it clear who makes the choice on the order in which facilities are worked?
3Is the work itself or any part of the work in restricted area (loops & within AF red zones)?
a. If answer to above is YES, is this clearly identified in the project documents?
b. Will CE Military Escorts be required?
4Does the project require any full or partial road closures?
a. If answer to above is YES, has duration of road closure, parking, traffic signs & alternate traffic road been considered?
b. If YES, Is coordination time of up to 30 days considered in PoP?
5Does the project require any utility outages?
a. If answer is YES have the durations and number of occurances been identified?
b. If answer is YES, are all affected facilities by the outage identified?
c. If answer is YES is the user notified?
d. If YES, Is coordination time of up to 30 days considered in PoP?
6Are access and haul routes for the contractor considered?
7Does the project have any asbestos related work?
a. If YES, is it clear where it is located?
b. Is it clear how much must be removed?
c. Is the method of removing asbestos clear?
d. Is it indicated whether or not the facility will remain occupied?
e. Have all environmental permits been obtained?
f. Have all testing, certification, and disposal costs together w/ contractor's costs considered?
8Does the AF Form 66 accurately reflect the material submittals called for in the specifications?
9Is the contract construction performance time reasonable? Are the following considered:
a. Long-lead construction or equipment items?
b. Time b/w change of phasing?
c. Local site conditions and restrictions?
d. Utility marking & initial mobilization? (app 21 days)
e. Pre-Final & Final inspection period? (app 21 days)
10Does the project include government furnished equipment (GFE)?
a. If YES, is the equipment clearly identified in the project documents?
b. Is it identified when, and to what location the equipment will be delivered to the contractor?
c. Is there a memorandum for record filed to document GFE providing agencies agreement?
11Is the scope of work clear?
a. Are there any open questions?
12Has the project been reviewed by O&M representative(s)?
13Does the project require fire detectors & suppression system to be disabled (including ones in attic & mezzanine)
14Is the laydown area identified on the project drawings?
15Does the project request extended manufacturer warranties? If yes, is it requested in AF 66?
16Are there any maintenance of equipment requirements, i.e. chillers, generators etc?
a. If yes has it been incorporated and is the duration for maintanence identified?
SECTION II. CONSTRUCTION SITE
NO:ITEMYESNON/A
1Do the plans accurately depict obvious as-built conditions?
2Do the plans accurately depict the locations of utilities, i.e.:
a. Electrical power poles, underground electrical lines, and service to facility?
b. Telephone poles, underground communication lines, and service to facility?
c. Manholes?
d. Water lines and service to facility?
e. Gas and fuel lines and service to facility?
3Will temporary utilities be readily available if the project documents offer them?
4Spot check the elevations. Do the plans seem relatively accurate?
5Does the project require landscaping work?
a. If YES, do the plans indicate seeding, or some means for quick turf establishment in problem areas?
b. If YES, do the plans address turf placement?
6Are there any abandoned underground utility lines to be left in place?
SECTION III. ARCHITECTURAL/STRUCTURAL
NO:ITEMYESNON/A
1Do the plans clearly distinguish the difference in existing and new work?
2Is the room finish schedule included into the drawings?
work?
3 Do the specifications call for all color selections to be submitted at one time?
4 Does the door finish schedule include information on all rooms indicated to receive
applicable work? Does it agree with the specifications?
5 Are all dimensions shown clearly? Do the dimensions shown agree with the indicated
3scale?
a. If YES, does it include all details of required items in all rooms?
b. If YES, does it include the door finish details as well?
c. If YES, are all items in agreement with the specification?
3Does the specification call for all color selections to be submitted at one time?
4Are all dimensions shown clearly?
a. Do the shown dimensions match with the scaling?
b. Do the structural, mechanical, and electrical floor plans agree with the architectural plans?
c. Do all concrete columns and walls on architectural plans agree with the structural plans?
5Do the plans allow adequate space in utility and mechanical rooms for proper installation and maintenance of equipment?
6Is there a complete legend for the project including architectural, structural, mechanical, and electrical symbols?
7If painting exterior, is building number painting included?
8Does the project call for floor leveling before installing carpeting or VCT?
9Is the new fence line interfeering with manholes, downspouts, yards & surrounding areas, is it blocking drainage?
SECTION IV. MECHANICAL/PLUMBING
NO:ITEMYESNON/A
1a.Does the project require temporary HVAC?
b. If yes has it been identified and requested?
2Do the plans show where all new gas, water, sewer lines, etc. connect to existing?
3Do the plumbing fixture locations agree with the architectural plans?
4Do the plumbing fixtures shown on the plans agree with the fixture schedule, and/or the specifications?
5Are all pipe concealment spaces, or chases shown on architectural plans?
6Do the plans allow for adequate ceiling height to install new ductwork at worst case intersection?
7Do the project documents call for structural support of piping, ductwork, plumbing fixtures and all mechanical equipment?
8Are all the sizes indicated for all ductwork and piping?
9a. Is all roof mounted, or externally mounted, mechanical equipment shown on architectural plans?
b. Does the roof mounted equipment require a maintenance catwalk?
10Does all mechanical equipment show connections for piping, power, controls, etc., as necessary?
11Place FCU in the proper locations, i.e. away from walkway path.
12Ensure that thermostats are shown on the drawings & installed inside of all buildings.
13If the drawings refer to a Government Furnished Computer for remote access, is computer availability checked and all computer and control systems have programing keys, dongles & programs?
14Is the route/path of new pipes clear of obstructions?
15Are pipe designators required?
SECTION V. ELECTRICAL
NO:ITEMYESNON/A
1a. Do the electrical plans indicate that all major pieces of equipment receive power?
b. Does all the scheduled mechanical equipment in the mechanical plans receive power?
c. Do the voltages, phases, and frequencies in the mechanical schedules agree with the electrical plans?
2Are the locations for all panel boards shown in the plans and on the electrical riser?
3Do the specifications require that all electrical work be in accordance with the latest edition of the NEC?
4a. If the plans call for removing existing panels and installing new, is temporary power provided for in the project documents?
b. If not, is this acceptable?
5Ensure that KTR use the proper sealant for exterior outdoor PVC high voltage lines.
6Does the facility(s) require a generator(s)?
SECTION VI. ENVIRONMENTAL
NO:ITEMYESNON/A
1Are there any environmental contaminants that may be present in existing equipment or on site? (i.e. - asbestos, lead paint, Hazardous Air Pollutants (HAPs), contaminated soil, Ozone Depleting Substances (ODC’s), etc.).
2Are there any environmental materials that can be recycled or recovered? (i.e. - Ozone Depleting Substances (ODS’s), Halon, Petroleum, Oil and Lubricants (POLs), etc.)
3Has the project been reviewed by a base environmental representative?
4Have SDSs for hazardous materials been requested for ENV review, and is a note inserted for KTR to keep them on site.
SECTION VII. FIRE ALARM SYSTEMS
NO:ITEMYESNON/A
1Are exit signs in the proper egress, access locations?
2Are notification appliances outside of buildings at the proper height?
3Are recessed fire extinguisher cabinets shown in the req'd locations inside of the building?
4Is this project major renovation and/or construction?
a. Did a Qualified Fire Protection Engineer (QFPE) involve in every aspect of the construction and

testing/commissioning as it relates to fire protection and life safety?

5Does this project include foam type fire suppression system?
a. Did you incorporate AFCEC review and approval for the shop drawings submittal of the foam type fire protection system?
Design Engineer's Name & Signature:
Inspector's Name & Signature:

FA5685-18-R-003 - Attach 8 - INC-1108

&"Arial,Bold"Form INC-1108 Constructability Review Checklist (Rev 1, September 2017)