About this file

This document includes a statement of work and federal contract opportunity notice for renovations to Building 1334 at Moron Air Base in Spain. The renovation project is identified as QUUG 110-1017 and has a value between $500,000 and $1,000,000. Revisions have been made to delete options for refurbishing an ARMAG container and modifying exterior lighting specifications. A pre-proposal conference will be held on August 13, 2020, with questions due by August 19th. Proposals must be received by August 31, 2020. The work is subject to requirements in the Defense Cooperation Agreement between the US and Spain to use Spanish labor and materials when feasible. Funding is not presently available and no award will be made until funds are allocated.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISION O1 OF PROJECT QUUG 10-1017 Renovate BDOC B1334

Statement of Work

From the previous SoW the line items of OPTION 3 part 2.4.3 refurbishing the portable

ARMAG container, has been deleted

a. Remove interior paneling, timber and insulation in bad condition from walls (approx.

50%), remove paneling and timber from the floor and store the wood plank for subsequent reuse.

b. Scrape exterior paint up to obtain a clean surface of steel envelopment, remove interior paint and rusting from the interior metal skin after demolition.

c. Remove interior light fixture.

d. Apply corrosion inhibitor passivate coating, two component epoxy polyamide primer with zinc phosphate and two coats of two component polyurethane acrylic enamel to all exterior metal envelopment and interior exposed metal surfaces of walls, underfloor and ceiling.

e. Install interior 16 mm wood waterproof plywood, 25 mm thick polystyrene insulation board with aluminum veneer, two 30 mm thick layers of timber and interior finish of

16 mm thick plywood with melamine veneer.

f. Install two 30 mm thick layers of timber, a 16 mm thick waterproof plywood and a 2 mm thick min. of vinyl flooring.

g. Provide electrical service, new lighting fixtures, bonding and Lightning Protection

System (LPS)/Grounding as required.

From the previous, SoW the line items of OPTION 3 part 2.4.6 (Now 2.4.5) Has been modified by including “exterior” regarding the lighting fixtures.

It has been also included in this option in the paragraph 2.4.2 the following works

Remove the curb around the container from original location and disconnect the power incoming.

Pictures 16 to 18 do not apply: Have been deleted