QUESTIONS &ANSWERS RFQ: FA527017Q0007

QUESTIONS (Q) AND ANSWERS (A) 27 Jul 17

For

Solicitation Number: FA527017Q0007

Uninterruptable Power Supply Procurement and Installation at Fort Buckner, Okinawa Japan

Q1. Attachment 1 titled SOW dated 14 JUL 2017, released on 16 JUL 2017, calls for the following in sec 7

(Submittals), sub section 7.3:

7.3 Submit coordination study for UPS prepared in accordance with IEEE Std 242 Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems; demonstrate fully selective coordination with immediate upstream and downstream over current protective devices

In reviewing this requirement, to fully complete this, we would need knowledge of power upstream of the UPS and at the building level. The building design or any part of the electrical distribution is outside of the SOW for this RFQ so we are wondering if this should be accounted for in our package or fall outside of the scope of the RFQ.

A1: Drawing E004 provides answer to question #1, it shows how power is coming into the Panels feeding the input for both the 500 KVA and the 225 KVA UPS. The voltage coming in is 480 volts.

Q2. Attachment 2 titled All Drawings, released on 30 JUN 2017, lists drawing E005 as the new equipment layout.

Attachment 2 titled Missing Drawings (E006-E007), released on 11 JUL 2017, lists drawing E006-E007 as cable and conduit schedule –power. Both of these packages have issue dates listed on the drawings as 30 JUL 2004 and the titles on the drawings do not match to the package being called for in the SOW, the most recent rev titled

Attachment 1SOW dated 14 JUL 2017, released on 16 JUL 2017. Could you please clarify which drawings are in support of the existing equipment and which drawings are in support of the new equipment.

A1: E003 shows the way the room looked before the electrical upgrade of 2005. E005 shows the current configuration of the equipment and room.

Q3. There were two 225KVA and two 500KVA UPS at the site. How many of these need to be removed?

A3: Two (2) of the 225 and two (2) of the 500 shall to be remove along with the cabinets that contain the batteries

IAW Attachment 1 SOW dated 14 Jul 2017 .

Q4. How many new UPS need to be installed?

A4: Two (2) of the new system that are parallel redundant shall be install along with their battery cabinets IAW

Attachment 1 SOW dated 14 Jul 2017.

Q5. Drawing E005: The picture of SWBD "G" on Drawing E004 was removed in the modified Drawing #E005. Do we need to provide the SWBD as well as new UPS?

A5: No, the SWBD is not required. Configuration shall be IAW updated Drawing of E005.

Q6. Is there anything else we need to replace besides UPS in this project?

A6: All item required to be replace shall be IAW Attachment 1 SOW dated 14 Jul 2017.