Questions and Answers 004

South Loop Taxiway Mill and Overlay

FA5004-15-B-C002

Q1. Questions and Answers 003 - Q2 answers a question about bury depth for the 2/0 ground cable running horizontally between ground points while the SOW dated May 26, 2015 is silent on installing new ground points or 2/0 ground cable between new or existing ground points (in the previous statement of work ground point installation was covered in paragraph 3.7).

Please clarify if new ground points and ground cable between them are a part of this project.

A1. Paragraph 3.7 from Statement of Work dated 15 May 2015, which discusses the ground static points, has been removed from this project because it is no longer part of the requirement. This requirement is only for a 2” mill, therefore, it is not possible to reach the 30” depth for the grounding rods without doing a full depth repair across the entire taxiway. The Statement of Work dated 26 May 2015, removes this paragraph.