JA-5_AF_Form_66 _Schedule_of_Material_Submittals.pdf
PDF 2 MB Posted
- Attached to
- South Loop Taxiway Mill and Overlay Federal contract opportunity
- Solicitation number
- FA5004-15-B-C002
About this file
JA-5 AF Form 66 Material Submittal Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers_004.pdf | ||
| 26_May_15_FTQW_15-2015_South_Loop_Mill_and_Overlay_SOW_descope.pdf | ||
| Amendment_0003_-_Incorperate_Revised_SOW.pdf | ||
| Questions_and_Answers_003.pdf | ||
| Questions_and_Answers_002.pdf | ||
| Amendment_0002_-_Incorperate_SOW_and_Grounding_Diagram.pdf | ||
| JA-1_SOW_15MAY15.pdf | ||
| JA-7_Grounding_Diagram_15MAY15.pdf | ||
| Questions_and_Answers_001.pdf | ||
| Amendment_0001_-_Site_Visit_Change_(Signed).pdf | ||
| JA-8_Wage_Determination_AK150007_AK7.pdf | ||
| JA-2_Tab_1-_Construction_Area_Map.pdf | ||
| JA-11_AF_Form_3065.pdf | ||
| JA-9_AF_Form_3000.pdf | ||
| JA-6_ETL_04-2_(Change_1).pdf | ||
| JA-12_AF_Form_103.pdf | ||
| FA5004-15-B-C002_Solicitation.doc | DOC document | |
| JA-4_Airfield_Painting_Plan_Maps.pdf | ||
| JA-3_Techincal_Specification.pdf | ||
| JA-1_FTQW_15-2015_South_Loop_Mill_and_Overlay_SOW_(Final).pdf | ||
| JA-10_AF_Form_3064.pdf | ||
| JA-7_South_Loop_Grounding_Diagram.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line
Acti vity
Trans-mittal #
Specification
Section
SD
# Submittal Description Item Submitted Paragraph #
Classificati on: GOVT or A/E
Revwr Submit
Approval
Needed
By
Material
Needed
By
Action
Code
Date Of
Action
Date FWD to APPR /
Auth Date
RCD From
CONTR
Date
FWD To
Other
Revwr
Date
RCD
From
Other
Revwr
Action
Code
Date Of
Action
Mailed To
CONTR/
Date RCD
From
APPR
Authority Remarks
1 01 10 00 1 Preconstruction Submittals AF Form 103 1.8
2 01 30 00 01 Preconstruction Submittals Waste Disposal/ Borrow Pit Plan 1.19
3 01 30 00 01 Preconstruction Submittals Construction Operation and Safety Plan 1.6
4 01 30 00 01 Preconstruction Submittals Safety and Health Program 1.8
5 01 30 00 01 Preconstruction Submittals Work Plan 1.8
6 01 30 00 01 Preconstruction Submittals Environmental Protection Plan 1.20
7 01 30 00 01 Preconstruction Submittals Hazardous Materials Inventory 1.21
8 01 30 00 01 Preconstruction Submittals FAA Form 7460-1 1.41
9 01 33 00 01 Preconstruction Submittals Submittal Register 1.6 G
10 01120 01 Alteratrion Project Procedures Demo and Reomval procedures
11 32 01 11.51 04 Samples Paint Removal 1.9.1
12 32 01 11.51 07 Certificates Schedule of Work 1.7.1 G
13 32 01 11.51 07 Certificates High-Pressure Paint Removal
Equipment 1.8.1
14 32 12 10 03 Product Data Waybills & Delivery Tickets 1.1.3 G
15 32 12 10 03 Product Data Tack Coat 3.2.1 G
16 32 12 10 03 Product Data Temperature Ranges 3.3.2 G
17 32 12 10 06 Test Reports Sampling and Testing 3.7
18 32 12 15.13 02 Shop Drawings Placement Plan 1.4 G
19 32 12 15.13 03 Product Data Mix Design 2.3
20 32 12 15.13 04 Samples Asphalt Cement Binder 2.2
21 32 12 15.13 04 Samples Aggregates 2.1
22 32 12 15.13 06 Test Reports Aggregates 2.1
23 32 12 15.13 07 Certificates Asphalt Cement Binder 2.2
24 32 12 15.13 07 Certificates Testing Laboratory 3.1.2
25 32 17 23.00 20 03 Product Data Reflective media for airfields 2.1.3
26 32 17 23.00 20 03 Product Data Paints for airfields 2.1.1
27 32 17 23.00 20 03 Product Data Equipment 1.5 G
28 32 17 23.00 20 03 Product Data Qualifications 1.8
29 32 17 23.00 20 06 Test Reports Reflective media for airfields 2.1.3
30 32 17 23.00 20 06 Test Reports Paints for airfields 2.1.1
31 32 17 23.00 20 07 Certificates Reflective media for airfields 2.1.3
32 32 17 23.00 20 07 Certificates Paints for airfields 2.1.1
33 32 17 23.00 20 07 Certificates Volatile Organic Compound
34 32 17 23.00 20 07 Certificates Construction equipment list 1.5
35 32 17 23.00 20 08 Manufacturer’s Instructions Paints for airfields 2.1.1
36 32 17 24.00 10 03 Product Data Equipment 1.3 G
37 32 17 24.00 10 03 Product Data Composition Requirements
38 32 17 24.00 10 03 Product Data Qualifications 1.5.1
APPROVING AUTHORITY
(d)
CONTRACTOR SCHEDULE
DATES
CONTRACTOR
ACTION
TITLE: South Loop Mill and Overlay
SUBMITTAL REGISTER
JOB NAME:
LOCATION: Eielson AFB
CONTRACT NO:
CONTRACTOR:
Page 1 of 2ATTACHMENT JA-5
FA5004-15-B-C002
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
APPROVING AUTHORITY
(d)
CONTRACTOR SCHEDULE
DATES
CONTRACTOR
ACTION
TITLE: South Loop Mill and Overlay
SUBMITTAL REGISTER
JOB NAME:
LOCATION: Eielson AFB
CONTRACT NO:
CONTRACTOR:
39 32 17 24.00 10 06 Test Reports Sampling and Testing 2.4
40 32 17 24.00 10 07 Certificates Volatile Organic Compound (VOC)