JA-12_T4_AF_Form_66.pdf
PDF 500 KB Posted
- Attached to
- Turbine-Generator #4 Federal contract opportunity
- Solicitation number
- FA5004-14-R-C008
About this file
Attachment JA-12
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA5004-14-R-C008-0005.pdf | ||
| JA-19_Question_and_Answer__3.pdf | ||
| FA5004-14-R-C008-0004.pdf | ||
| FA5004-14-R-C008-0003.pdf | ||
| JA-18_Question_and_Answer__2.pdf | ||
| FA5004-14-R-C008-0002.pdf | ||
| JA-17_Example_LRR.pdf | ||
| JA-16_Question_and_Answer__1.pdf | ||
| FA5004-14-R-C008-0001.pdf | ||
| JA-11_Wage_Determination_AK20130001.pdf | ||
| JA-13_AF_Form_3000.pdf | ||
| JA-9_Past_Performance_Worksheet.docx | DOCX document | |
| JA-5_T4_Appx_4 _New_Panel.pdf | ||
| JA-10_Financial_Reference_Sheet.docx | DOCX document | |
| JA-1_T4_Specifications.pdf | ||
| JA-8_Past_Performance_Questionnaire.docx | DOCX document | |
| JA-15_AF_Form_3065.pdf | ||
| JA-14_AF_Form_3064.pdf | ||
| JA-4_T4_Appx_3 _Existing_Panel _final.pdf | ||
| JA-6_T4_Appx_5 _O M_Manual.pdf | ||
| JA-3_T4_Appx_2 _Photos_w_mark-up.pdf | ||
| JA-2_T4_Appx_1 _Inspections.pdf | ||
| FA5004-14-R-C008.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. GPO 1987-188-148
PROJECT NUMBER PROJECT TITLE MAINTAIN TURBINE- SOLICITATION/CONTRACT NO.
SCHEDULE OF MATERIAL SUBMITTALS FTQW 15-1001 GENERATOR #4
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
SH
O
P D
R A
W
IN
G S
SA
M
PL
ES
C O
LO
R
S
EL
EC
TI
O N
C A
TA
LO
G D
A
TA
O
PE
R A
TI
N
G
IN
ST
R
U C
TI
O
N S
O
TH
ER
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL
APPROVAL REMARKS
APPROVED
DIS-
APPROVED
1 01010-1.6.A. Work Clearnace Request, AF Form 103 4 5 days after
NTP For Information Only
2 01030-1.6. Construction Operation & Safety Plan 4 4 wks prior to work start
3 01030-1.10, Ionizing Radiation Permit Request 4 4 weeks prior to need For Information Only.
Submit only if applicable
4 01030-1.11, Laser Permit Request 4 4 weeks prior to need For Information Only.
Submit only if applicable
5 01030 - 1.12, Radioactive Material Permit Request 4 4 weeks prior to need For Information Only.
Submit only if applicable
6 01030-1.13, Radio Frequency Radiation Permit Request 4 4 weeks prior to need For Information Only.
Submit only if applicable
7 01030-1.14, Ultraviolet Radiation Permit Request 4 4 weeks prior to need For Information Only.
Submit only if applicable
8 01030-1.19, Environmental Protection Plan 5 4 wks prior to work start
9 01030-1.20.A, Initial Hazardous Material Inventory 4 2 wks prior to work start
01030-1.20.A, Final Hazardous Material Inventory 4
1 wk after completion of on-site work
01030-1.21.C, Hazardous Waste Accumulation Log 4
1 wk after completion of on-site work
SE
R
VI
C
E / S
IZ
E
/ A
PP
LI
C
A
TI
O N
S C
H
ED
U
LE
M A
N U
FA
C
TU
R
ER
'S
R
EC
O M
M
EN
D A
TI
O
N S
M A
N U
FA
C
TU
R
ER
'S
W A
R R
A N
TY
C
ER
TI
FI
C A
TI
O
N O
F C
O M
PL
IA
N C
E
AF Form 66, Sep 86
MAINTAIN TURBINE-GENERATOR#4
EIELSON AFB, ALASKA
FTQW 15-1001
ATTACHMENT JA-12
T4 AF FORM 66
SOLICITATION FA5004-14-R-C008
SCHEDULE OF MATERIAL SUBMITTALS FTQW 15-1001 GENERATOR #4
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
SH
O
P D
R A
W
IN
G S
SA
M
PL
ES
C O
LO
R
S
EL
EC
TI
O N
C A
TA
LO
G D
A
TA
O
PE
R A
TI
N
G
IN
ST
R
U C
TI
O
N S
O
TH
ER
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL
APPROVAL REMARKS
APPROVED
DIS-
APPROVEDSE
R
VI
C
E / S
IZ
E
/ A
PP
LI
C
A
TI
O N
S C
H
ED
U
LE
M A
N U
FA
C
TU
R
ER
'S
R
EC
O M
M
EN
D A
TI
O
N S
M A
N U
FA
C
TU
R
ER
'S
W A
R R
A N
TY
C
ER
TI
FI
C A
TI
O
N O
F C
O M
PL
IA
N C
E
2 01030-1.22, TCLP Test Results 4
Prior to disposing
Haz Waste
01400-1.3, Testing Lab Qualifications 4 4 wks prior to testing
01400-1.7, Construction Photographs 2 Submit w/ each
Progress Report
15699-1.2.A & 3.1, Tech Rep Qualifications 4 4 wks prior to work start
15699-1.2.B & 3.2, Governor Tech Qualifications 4 4 wks prior to work start
15699-1.2.C. & 3.4.AAA, NDI
Test Lab & Worker Qualifications
4 2 wks prior to work start
15699-1.2.D & 3.5.D, Pre- Overhaul Vibration Report 4 5 days after testing
15699-1.2.E.1 & 3.5.I, Extraction Isolation Valve Actuator (initial)
4 4 4 wks prior to ordering
15699-1.2.E.2 & 3.5.I, Extraction Isolation Valve Actuator (final)
4 4 4 4 4 2 wks prior to request for final payment
15699-1.2.F & 3.5.V, Runout at proximitor targets 4 24 hrs after measuring
AF Form 66, Sep 86
MAINTAIN TURBINE-GENERATOR#4
EIELSON AFB, ALASKA
FTQW 15-1001
ATTACHMENT JA-12
SCHEDULE OF MATERIAL SUBMITTALS FTQW 15-1001 GENERATOR #4
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
SH
O
P D
R A
W
IN
G S
SA
M
PL
ES
C O
LO
R
S
EL
EC
TI
O N
C A
TA
LO
G D
A
TA
O
PE
R A
TI
N
G
IN
ST
R
U C
TI
O
N S
O
TH
ER
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL
APPROVAL REMARKS
APPROVED
DIS-
APPROVEDSE
R
VI
C
E / S
IZ
E
/ A
PP
LI
C
A
TI
O N
S C
H
ED
U
LE
M A
N U
FA
C
TU
R
ER
'S
R
EC
O M
M
EN
D A
TI
O
N S
M A
N U
FA
C
TU
R
ER
'S
W A
R R
A N
TY
C
ER
TI
FI
C A
TI
O
N O
F C
O M
PL
IA
N C
E
15699-1.2.G.1 & 3.5.JJ, Oil Cooler Diverter Valve (initial) 4 4 wks prior to ordering
15699-1.2.G.2 & 3.5.JJ, Oil Cooler Diverter Valve (final) 4 4 4 4
2 wks prior to request for final payment
15699-1.2.H.1 & 3.5.II, Oil Accumulator (initial) 4 4 4 4 wks prior to ordering
15699-1.2.H.2 & 3.5.II, Oil Accumulator (final) 4 4 4 4
2 wks prior to request for final payment
15699-1.2.I.1 & 3.5.NN,
Condenser Cooling Water Meter & Valve (initial)
4 4 4 wks prior to ordering
15699-1.2.I.2 & 3.5.NN,
Condenser Cooling Water Meter & Valve (final)
4 4 4 4 4 2 wks prior to request for final payment
15699-1.2.J, 3.5.MM & 3.5.RR,
Equipment & Procedures for High Pressure Cleaning
4 4 wks prior to start of cleaning
15699-1.2.K.1 & 3.5.SS,
Alternate Cooling Water Supply (initial)
4 4 4 4 wks prior to ordering mat'l
15699-1.2.K.2 & 3.5.SS,
Alternate Cooling Water Supply (final)
2 wks prior to request for final payment
15699-1.2.L.1 & 3.8, Turbine Control Panel (initial) 4 4 4 4 wks prior to ordering mat'l
15699-1.2.L.2 & 3.8, Turbine Control Panel (final) 4 4 4 4
2 wks prior to request for final payment AF Form 66, Sep 86
MAINTAIN TURBINE-GENERATOR#4
EIELSON AFB, ALASKA
FTQW 15-1001
ATTACHMENT JA-12
SCHEDULE OF MATERIAL SUBMITTALS FTQW 15-1001 GENERATOR #4
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
SH
O
P D
R A
W
IN
G S
SA
M
PL
ES
C O
LO
R
S
EL
EC
TI
O N
C A
TA
LO
G D
A
TA
O
PE
R A
TI
N
G
IN
ST
R
U C
TI
O
N S
O
TH
ER
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL
APPROVAL REMARKS
APPROVED
DIS-
APPROVEDSE
R
VI
C
E / S
IZ
E
/ A
PP
LI
C
A
TI
O N
S C
H
ED
U
LE
M A
N U
FA
C
TU
R
ER
'S
R
EC
O M
M
EN
D A
TI
O
N S
M A
N U
FA
C
TU
R
ER
'S
W A
R R
A N
TY
C
ER
TI
FI
C A
TI
O
N O
F C
O M
PL
IA
N C
E
15699-1.2.M & 3.6, Letters of Recommended Repairs 4 5 days after inspection Submit as necessary
15699-1.2.N & 3.7.F, Start-up Plan 4 2 wks prior to start-up
15699-1.2.O & 3.10, Post Overhaul Report 4 14 days after final acceptance test
15699-1.2.P & 3.5.C, Completed Task Inspection List 4 2 days after final acceptance test
15699-1.2.Q, Proposed Deviations 4 4 4 4 4 4
When deviations are requested
Submit only if applicable
AF Form 66, Sep 86
MAINTAIN TURBINE-GENERATOR#4
EIELSON AFB, ALASKA
FTQW 15-1001
ATTACHMENT JA-12