JA-1_T4_Specifications.pdf

PDF 2 MB Posted

Attached to
Turbine-Generator #4 Federal contract opportunity
Solicitation number
FA5004-14-R-C008
Issued by
Department of the Air Force Pacific Air Forces

About this file

Attachment JA-1

View the file

Other files for this federal contract opportunity

Other files attached to Turbine-Generator #4, newest first.
File Type Posted
FA5004-14-R-C008-0005.pdf PDF
JA-19_Question_and_Answer__3.pdf PDF
FA5004-14-R-C008-0004.pdf PDF
FA5004-14-R-C008-0003.pdf PDF
JA-18_Question_and_Answer__2.pdf PDF
JA-16_Question_and_Answer__1.pdf PDF
FA5004-14-R-C008-0002.pdf PDF
JA-17_Example_LRR.pdf PDF
FA5004-14-R-C008-0001.pdf PDF
JA-12_T4_AF_Form_66.pdf PDF
JA-11_Wage_Determination_AK20130001.pdf PDF
JA-15_AF_Form_3065.pdf PDF
JA-14_AF_Form_3064.pdf PDF
JA-4_T4_Appx_3 _Existing_Panel _final.pdf PDF
JA-6_T4_Appx_5 _O M_Manual.pdf PDF
JA-3_T4_Appx_2 _Photos_w_mark-up.pdf PDF
JA-2_T4_Appx_1 _Inspections.pdf PDF
FA5004-14-R-C008.pdf PDF
JA-13_AF_Form_3000.pdf PDF
JA-9_Past_Performance_Worksheet.docx DOCX document
JA-5_T4_Appx_4 _New_Panel.pdf PDF
JA-10_Financial_Reference_Sheet.docx DOCX document
JA-8_Past_Performance_Questionnaire.docx DOCX document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL PROVISIONS

MAINTAIN

TURBINE-GENERATOR #4

FTQW 15-1001

EIELSON

AIR FORCE BASE,

ALASKA

March 2014

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

SPECIFICATIONS

SOLICITATION FA5004-14-R-C008

MAINTAIN TURBINE-GENERATOR #4 CONTENTS

EIELSON AFB, ALASKA

FTQW 15-1001

Contents 1

DIVISION 1 GENERAL REQUIREMENTS

01010 Description of Work and Coordination 01030 Safety, Environmental Protection, Regulations and Codes 01045 Cutting and Patching

01073 Explanations: Drawings and Specifications 01080 Existing Utilities 01120 Alteration Project Procedures

01300 Submittals 01400 Quality Control 01500 Construction Facilities and Temporary Controls

01600 Material and Equipment 01700 Contract Closeout

DIVISION 15

15699 Turbine-Generator Overhaul

APPENDICES

Appendix 1 Task Inspection list

Appendix 2 Photographs

Appendix 3 Existing Control Panel

Appendix 4 Suggested New Control Panel Layout

Appendix 5 O&M Manual Excerpts

Appendix 6 2010 Turbine 4 Overhaul Report

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

MAINTAIN TURBINE-GENERATOR #4 SECTION 01010

EIELSON AFB, ALASKA DESCRIPTION OF WORK AND COORDINATION

FTQW 15-1001

01010 - 1

PART 1 GENERAL

1.1 SCOPE OF THIS SECTION

A. Synopsis of Contract Work.

B. Government Occupancy.

C. Work by Others

D. Coordination

E. Notification.

F. Security and Access.

G. Existing Features

1.2 SYNOPSIS OF CONTRACT WORK

A. Basic Work Items.

Tear down, inspect, clean and repair turbine-generator #4 and auxiliary equipment at Eielson AFB’s Central Heat and Power Plant (CH&PP) as described in specification section 15699.

Turbine-Generator #4 is a 5 MW Worthington extracting steam turbine – Electric Machinery generator set installed in 1972 (Worthington form TBVXV, Electric Machinery 5MW, 6250 kVA, 7200V synchronous generator). Rebuild the turbine control panel. Prepare technical notes and tear-down/repair reports.

B. The turbine-generator will not be taken out of service until 11 April 2015. Prior to that date, the Contractor is encouraged to order materials and perform work of this contract that does not require the machine to be taken out of service. Within 30 days after the machine has been taken out of service, the Contractor shall have completed teardown and inspection of the machine, it’s components and auxiliary equipment, as described in section 15699, and shall have submitted all Letters of Recommended Repair (refer to section 15699, para 3.6). Within 80 calendar days after the machine has been taken out of service, the Contractor shall have the machine reassembled, he shall have completed all required post-overhaul operational tests, and the unit shall be available to the Government to reliably produce power.

C. Asbestos-containing materials are present in the work area. In addition, turbine-generator parts and ancillary equipment may be coated in lead base paint. The contractor shall take appropriate precautions to avoid disturbing the asbestos, grinding or sanding painted surfaces, or other activities that might create an inhalable hazard.

1.3 GOVERNMENT OCCUPANCY

A. The Government will occupy premises during entire period of construction for the conduct of its normal operations.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

FTQW 15-1001

01010 - 2

B. The Contractor shall perform the work under this contract in such a manner that adjacent Air Force activities may proceed unhindered. Prior to beginning on-site work the Contractor shall meet with the Contracting Officer and technical representatives from Base Civil Engineering to schedule the work of this contract.

C. The Contractor shall not interfere with, nor prevent in any manner, access to or exiting from any room or area without prior approval from the Contracting Officer.

D. Maintain IBC complying access to and through corridors, stairways, and building exits at all times.

E. Cooperate with Government to minimize conflict and to facilitate its operations. In case of conflict accept Contracting Officer's direction as final and adjust use of premises accordingly.

F. Coordinate Work in and use of premises with the Government.

G. The Contractor shall clean and have ready for use all areas of work that will be used by the Government between work periods

1.4 WORK BY OTHERS

A. The Contracting Officer may undertake additional work or award other contracts for additional work for this Project Site and during this Contract Period. The Contractor shall fully cooperate with Government personnel and the other contractors. He shall carefully fit his own work to the additional work as he may be directed by the Contracting Officer.

B. The Contractor shall not commit, nor permit, any act by his personnel which would interfere with the performance of work by any other contractor or by Government employees.

1.5 COORDINATION

A. Coordinate Work of the various Sections of Specifications prior to ordering materials and fabrication to assure efficient and orderly sequence of installation of construction elements, with provisions for accommodating items installed later. Notify Contracting Officer of conflicts between elements prior to installation of any element.

B. Verify characteristics of elements of interrelated operating equipment are compatible; coordinate Work of various Sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements and installation of mechanical and electrical Work, which is indicated diagrammatically on Drawings. Follow routing shown for ducts and conduits as closely as practical. Make piping, duct, and conduit runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas, unless otherwise indicated, conceal pipes, ducts, and wiring in the construction.

Coordinate locations of sprinkler heads, fixtures, and outlets with finish elements.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

FTQW 15-1001

01010 - 3

1.6 NOTIFICATION OF COMMENCEMENT OF WORK

A. Prior to commencing work on-site, the contractor shall coordinate with all of the organizations listed on AF Form 103, Base Civil Engineering Work Clearance Request. The completed form shall be submitted to the Contracting Officer and a copy shall be kept at the work site at all times.

B. The Contractor shall notify the Contracting Officer that work will begin a minimum of seven (7) days prior to commencing work.

1.7 SECURITY AND ACCESS TO CONTROLLED AREAS

A. The Contractor shall comply with all Eielson AFB security and access to controlled area procedures and requirements. Initial procedures and requirements will be provided to the Contractor at the Pre- Construction Conference.

B. All work areas are controlled access areas.

1.8 EXISTING FEATURES

A. Refer to the General Contract Clauses for requirements for protection of existing vegetation, structures, equipment, utilities and improvements.

PART 2 - (NOT USED)

PART 3 - EXECUTION

END OF SECTION

MAINTAIN TURBINE-GENERATOR#4

FTQW 15-1001

ATTACHMENT JA-1

MAINTAIN TURBINE-GENERATOR #4 SECTION 01030

EIELSON AFB, ALASKA SAFETY, ENVIRONMENTAL PROTECTION,

FTQW 15-1001 REGULATIONS, AND CODES

01030 - 1

PART 1 GENERAL

1.1 REQUIREMENTS INCLUDED

A. Reference Standards

B. Licenses and Permits

C. Safety

D. Construction Operation and Safety Plan

E. Accident Prevention Plan

F. Fire Safety

G. Use of Ionizing Radiation

H. Use of Lasers

I. Radioactive Materials

J. Use of Radio Frequency Radiation

K. Use of Ultraviolet Radiation

L. Protection of Nesting Birds

M. Discovery of Historical or Cultural Artifacts

N. Affirmative Procurement Program

O. Environmental Protection

P. Environmental Protection Plan

Q. Hazardous Material Management

R. Hazardous Waste

S. Hazardous Waste Testing

T. Ozone Depleting Substances

U. Lead Base Paint

V. Asbestos Containing Materials

W. Suspected Hazardous Materials

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 2

X. PCBs & Oil-Filled or Impregnated Electrical Components

Y. Cleaning & Debris Control

Z. Spill Reporting / Clean-up

1.2 COMMONLY USED ACRONYMS

ACM Asbestos Containing Material

ADEC Alaska Department of Environmental Conservation

AOO Asbestos Operations Officer

APDES Alaska Pollutant Discharge Elimination System

APO Asbestos Program Officer

CO Contracting Officer

EPA Environmental Protection Agency

EMS Environmental Management System

EPCRA Emergency Planning and Community Right-to-Know Act

EPP Environmental Protection Plan

ESOHTN Environmental, Safety, and Occupational Health Training Network

HAZMAT Hazardous Material

HAZMART Hazardous Material Pharmacy

IRP Installation Restoration Program

LUC Land Use Controls

LUCIP Land Use Control Implementation Plan

MSDS Material Safety Data Sheet

NOI Notice of Intent

NOT Notice of Termination

NTP Notice to Proceed

PCB Polychlorinated Biphenyl

PID Photo Ionization Detector

RCRA Resource Conservation Recovery Act

RSO Radiation Safety Officer

SAP Sampling and Analysis Plan

SWPPP Storm Water Pollution Prevention Plan

TCLP Toxicity Characteristic Leaching Procedure

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 3

1.3 REFERENCE STANDARDS

A. Comply with all applicable laws, building and construction codes and applicable requirements of any governmental agency under whose jurisdiction this Work is being performed.

B. Federal, state and local codes and ordinances take precedence over these specifications and drawings where conflicts occur, unless the drawings or specifications call for more stringent requirements. Notify the Contracting Officer in writing of conflicts.

C. Obtain a copy of standards referenced in the various specification sections. Maintain a copy at the jobsite during execution of portion of the work to which the standard applies.

D. All work shall be governed by the more stringent provisions of these contract document requirements or the latest published edition or statute- adopted edition, of the following applicable codes, regulations and standards:

ADA Americans with Disabilities Act Accessibility Guidelines

AFI Air Force Instructions

AS Alaska Statutes

AAC Alaska Administrative Code

ASTM American Society of Testing and Materials

CFR Code of Federal Regulations

COE U.S. Army Corps of Engineers

COE EM Corps of Engineers Manuals

COE ER Corps of Engineers Regulations

CSC Alaska Department of Labor Construction Safety Code

FAR Federal Acquisition Regulations

FWI Fighter Wing Instructions

NEC National Electrical Code

OSHA Occupational Safety and Health Act - Federal and Alaska Regulations

Other applicable codes and standards as applicable or as referenced by the individual specification Sections.

1.4 SUBMITTALS

A. The following applicable items shall be submitted in accordance with Section 01300 - Submittals (Submit hard copies and a pdf copy for each, where applicable.):

1. Construction Operation and Safety Plan

2. Request for use of Ionizing Radiation (if required)

3. Request for use of Lasers (if required)

4. Request for use of Radioactive Materials (if required)

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 4

5. Request for use of Radio Frequency radiation (if required)

6. Request for use of Ultraviolet Radiation (if required)

7. Environmental Protection Plan

8. Hazardous Materials Inventory (Initial, quarterly & final)

9. Hazardous Waste Accumulation Log (Initial, quarterly & final)

10. Laboratory Test Results (as applicable)

11. NOI for asbestos abatement (if required)

12. Completed Checklist for Quarry Hill C&D Landfill (if applicable)

13. FAA Form 7460-1 Notice of Proposed Construction or Alteration (if applicable)

1.5 LICENSES AND PERMITS

A. The contractor shall obtain and maintain current for the duration of this contract, all required federal, state, and local licenses and permits. All associated fees and taxes shall be paid by the contractor without additional cost to the government.

B. The contractor shall obtain any additional Eielson AFB required permits. Current base permit requirements shall be provided to the contractor at the preconstruction conference.

1.6 SAFETY

A. Comply with all Federal and State regulations concerning safety of personnel and equipment.

Contractors are responsible to provide and ensure personnel have the appropriate personal protective equipment. All Contractor personnel shall wear hard hats and steel toe safety shoes while on the project site. All personnel shall wear hearing protection (ear muffs or ear plugs) when inside the power plant, excluding office areas, rest rooms, break rooms and other “quiet” areas. In addition, comply with the requirements of the U.S. Army Corps of Engineers’ manual, Safety and Health Requirements, EM 385-1-1 and applicable OSHA Standards.

B. Ensure that lock out, tag out procedures are established and used as directed by 29 CFR 1910.145.

Comply with lock-out tag-out procedures in use by CH&PP personnel. Ensure that contractor’s personnel on-site are trained on the government’s procedures.

C. Comply with all safety, traffic and protection requirements in effect on Eielson AFB. The government shall brief the contractor on these requirements at the preconstruction conference.

D. Work areas in this Project may be classified as “permit-required confined spaces” or “non-permit required confined spaces.” The contractor’s certified industrial hygienist shall determine the confined space status of the project areas. Regulations and procedures for entry into “permit-required confined spaces” are contained in 29 CFR 1910.146 and 8 AAC 61.010.14. The contractor is responsible for ensuring the safety of his employees in confined spaces according to these regulations.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 5

E. Confined Space Permit:

1. Provisions for confined space are outlined in 29CFR 1910.146 and ANSI Z117.1 1989 and shall be followed throughout Project.

2. Base Contact for information regarding confined Space issues is Ground Safety (354 FW/SEG, 377-4260). However, the Contractor shall process any permits required for confined space through his own safety Manager and Permit Space Program.

F. Provide safety barriers around open excavations, openings in floors and other hazards created by the contractor’s activities.

G. The Contracting Officer (CO), or the Contracting Officer’s designee may direct the contractor to cease activities which, in their opinion, are unsafe or which jeopardize operations. However, this provision does not relieve contractor of sole responsibility for safety for project activities.

H. The contractor shall protect base residents and the general public from harm in the construction area.

1.7 CONSTRUCTION OPERATION AND SAFETY PLAN

A. Contractor shall provide a Construction Operation and Safety Plan (COSP) for all construction operations.

B. The COSP shall include the following:

1. Detailed construction schedule and work phasing with dates of operation for work elements.

2. Route maps to and from construction sites for workers and equipment and hazardous material transport routes. Route maps shall include FOD fence locations and requirements.

3. Accident Prevention Plan

4. The COSP shall be submitted to the Contracting Officer at least 30 days prior to start of construction.

1.8 ACCIDENT PREVENTION PLAN

A. Submit a comprehensive Accident Prevention Plan (APP). The APP shall be similar to the example given in Appendix A of the Corps of Engineers Safety and Health Requirements Manual, EM 385- 1-1.

B. The APP shall be job specific and should include work to be performed by subcontractors. The APP shall address measures to be taken to control hazards associated with all operations, materials, services or equipment associated with the Work.

C. The Plan shall include the following sections, as applicable:

1. Name of plan preparer and approving company officer

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 6

2. Contractor, contract name & number

3. Copy of current company safety and health policy

4. Responsibilities and lines of authority. Explain who is responsible for site safety and for each specific operation, whether performed by the prime or a subcontractor. Discuss frequency of inspections and documentation.

5. List subcontractors and means of coordinating safety activities.

6. Describe initial new employee training, and periodic safety training. Any specific training required for particular categories of employees. And specific training or meetings occurring prior to specific hazardous activities. Identify who leads the training or meetings.

7. Describe personal protective equipment (PPE) required for each hazardous work activity.

8. Accident reporting procedures

9. Plans programs and procedures:. Address all applicable occupational risks and compliance plans. Plans may include, but are not limited to, the following:

a. Spill plan

b. Fire response plan

c. Posting of emergency phone numbers

d. Medical support – on-site and off-site medical support

e. Site sanitation

f. Respiratory protection plan

g. Health hazard control

h. Hazard communication program

i. Lead abatement plan

j. Asbestos abatement plan

k. Radiation safety

l. Abrasive blasting

m. Fire prevention plan

n. Hazardous energy control plan

o. Critical lift plan

p. Site-specific fall protection and prevention plan

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 7

q. Demolition plan

r. Excavation and trenching plan

s. Compressed air plan

t. Formwork and shoring erection and removal plans

u. Precast concrete plan

v. Steel erection plan

w. Confined space plan

10. Risk management for specific project related activities. Provide an Activity Hazard Analysis (AHA) for project specific hazards and controls that are not covered or are not sufficiently covered by the plans and programs described above.

D. Before beginning each work activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform the work, the Contractors performing the work activity shall prepare an Activity Hazard Analysis (AHA).

E. Each AHA shall define the activities being performed, the work sequence, specific anticipated hazards and control measures to be implemented to eliminate or reduce each hazard to an acceptable level.

F. Work shall not begin until the AHA has been discussed with all engaged in the activity

G. AHAs shall be modified as necessary to address changing site conditions.

1.9 FIRE SAFETY

A. Comply with all fire safety and protection requirements in effect on Eielson AFB. The government shall brief the contractor on these requirements at the preconstruction conference.

B. Prior to beginning any welding, use of open flame device, or any activity that produces sparks, obtain a “hot work permit” (AF Form 592, USAF Welding, Cutting, and Brazing Permit) from base Fire Department. The permit shall be renewed each day welding or open flame devices shall be used.

1. If the contract work requires numerous days of hot work, the contractor may elect to have one of his on-site personnel designated as a Permit Authorizing Individual (PAI). The contractor’s PAI may issue hot work permits at the work site, thus avoiding the requirement for daily permits issued by the Fire Department.

2. The contractor’s PAI shall be the on-site superintendent, a foreman, the contractor’s safety manager, or other individual with sufficient knowledge and experience to recognize unsafe work practices or conditions and having authority to stop work immediately if such unsafe practices or conditions are observed. To be designated as a PAI, a person must schedule and successfully complete PAI certification training offered by the base Fire Department. The PAI certification training is estimated to last 60 to 90 minutes and will be valid for the duration of the contract.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 8

3. Fire Department personnel may periodically visit the site to ensure the contractor is complying with fire safety requirements. A PAIs certification may be revoked if the PAI has failed to issue permits on days when hot work is performed, or if unsafe practices or conditions are observed.

4. Questions concerning these requirements may be directed to Fire Prevention Office, 354 CES/CEFT, Eielson AFB, 377-1293.

C. The contractor shall notify the Fire Department at 377-4156 and Fire Prevention Section at 377-1293 a minimum of 72 hours before, and again immediately prior to, temporarily closing any street or building access, interrupting water service to any fire hydrant or interrupting the operation of any fire detection, alarm or suppression system. The fire department shall be immediately notified upon reopening closed areas, restoration of water service to any fire hydrant, or reactivation of any detection, alarm or suppression system. Additionally any out of service hydrants will be covered and secured with a black bag to easily identify it is “out of service”. This notification requirement is in addition to other contract requirements.

D. Provide a 10 lb, ABC fire extinguisher at all work areas.

1.10 USE OF IONIZING RADIATION (IR)

A. Submit a written request for approval at least 30 calendar days before commencement of activities which require the use of IR generating devices.

B. Submit request to the Base Radiation Safety Officer (RSO) at the Bioenvironmental Engineering Office (354 MDOS/SGOJ, Phone: 377-6687) with a courtesy copy to the Contracting Officer.

Request shall include:

1. Description/Characteristics:

a. X-ray unit manufacturer.

b. Model number.

c. Serial number.

d. Maximum kVp, mA, Sec.

e. Ionizing radiation source/emitter (electron tube).

2. The part of the Air Force contract describing work to be done at the base and the inclusive dates of such work.

3. An acknowledgment that the RSO may make initial and periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel.

1.11 USE OF LASERS

A. Submit a written request for approval at least 30 calendar days before commencement of activities which require the use of a laser.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 9

B. Submit request to the RSO with a courtesy copy to the Contracting Officer. Request shall include:

1. Description/Characteristics:

a. Manufacturer.

b. Model.

c. Number of same units.

d. Serial number(s).

e. Laser medium.

f. Mode of operation (i.e. continuous wave (CW), single pulse, multiple pulse).

g. Maximum exposure time (train length).

h. Time (sec) & wavelength.

i. Energy/pulse (J) or CW power (W).

j. Pulse repetition frequency.

k. Pulse width.

l. Beam diameter (at 1/e point).

m. Beam divergence (at 1/e point).

2. The part of the Air Force contract describing work to be done and the inclusive dates of such work.

3. An acknowledgment that the RSO may make initial and periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel.

1.12 RADIOACTIVE MATERIALS (RAM):

A. Prior to bringing RAM onto Eielson AFB property, the contractor shall obtain permission from the RSO. To obtain approval, forward an application to the RSO and a courtesy copy to the Contracting Officer at least 30 calendar days before the planned date for commencement of activities on the installation. Requests shall include:

1. A description of the proposed activities on NRC Form 241, Report of Proposed Activities in Non-Agreement States, (the 180-day limitation on the form does not apply to organizations holding an NRC license). Contractors possessing Agreement State Licenses shall also submit an NRC Form 241 to NRC in compliance with 10 CFR 150.21. Contractors requiring more than 180 days of operation per calendar year on the installation shall possess an NRC license.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 10

2. The procedures established to ensure radiological health and safety of Air Force personnel and the public while on Air Force installations on site and the name of the responsible contractor representative.

3. A current copy of the applicable NRC, or Agreement State license. Expired licenses are unacceptable. To be valid at the installation, the license must either specifically state the installation by name on the license or state approval for work at temporary job sites anywhere in the United States where the NRC or Agreement State maintains jurisdiction. DoE or DoE prime contractors must provide, in lieu of a license, written certification of their exemption from NRC licensing requirements and cite the applicable exemption of 10 CFR.

4. The part of the Air Force contract describing work to be done and the inclusive dates of such work.

5. An acknowledgment that the base RSO may make periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel and prevent potential contamination of government property.

1.13 USE OF RADIO FREQUENCY (RF) RADIATION

A. Prior to using equipment generating RF radiation in excess of seven watts peak power and a frequency of 1000 MHz or greater on Eielson AFB, the contractor shall submit a written request for approval at least 30 calendar days before commencement of activities, which require the use of the RF generating device.

B. Submit request to the RSO, with a courtesy copy to the Contracting Officer. Submittal shall include:

1. Description.

2. Nomenclature.

3. Location of emitters.

4. Quantity.

5. Frequency (MHz).

6. Pulse width (microsecond.).

7. Pulse repetition freq. (pps).

8. Peak power (kW).

9. Antenna size (feet--horizontal/vertical).

10. Antenna bandwidth (degrees-- horizontal/vertical).

11. Antenna gain (dB).

12. Scan rate (rpm).

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 11

13. The part of the Air Force contract describing work to be done at the base and the inclusive dates of such work.

14. An acknowledgment that the RSO may make initial and periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel.

1.14 USE OF ULTRAVIOLET (UV) RADIATION

A. Submit a written request for approval at least 30 calendar days before commencement of activities which require the use of UV generating devices on Eielson AFB.

B. Submit request to the RSO, with a courtesy copy to the Contracting Officer. Request shall include:

1. The part of the Air Force contract describing work to be done at the base and the inclusive dates of such work.

2. An acknowledgment that the RSO may make initial and periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel.

1.15 PROTECTION OF NESTING BIRDS

A. Federal law prohibits disturbing bird nests containing eggs or birds too young to fly. Harassment of birds to force them to abandon an occupied nest is also illegal. If the contractor removes nests or harasses birds in violation of federal and state law, the contractor is responsible for any charges filed by US Fish and Wildlife Service or State of Alaska Department of Public Safety and is the liable party.

B. If an occupied bird nest is discovered, the contractor shall cease activities in the vicinity of the bird nest until the young birds are able to fly and leave the nest under their own power.

C. Cliff swallow nests are usually the greatest threat to construction projects. As a general rule, cliff swallows can begin nest construction any time between 10 May and 21 July.

D. The contractor shall be responsible for control of new nest construction after issuance of Notice to Proceed (NTP). The contractor shall survey the work area daily for new nest construction. To avoid project delays, the contractor shall remove all nests discovered before the nests have been completed and occupied.

E. The contractor shall be responsible for any increased cost or delay resulting from a nest constructed and occupied in the work area after NTP has been issued.

1.16 DISCOVERY OF HISTORICAL OR CULTURAL ARTIFACTS

A. Should any historical artifacts or cultural resources be unearthed, stop excavating and immediately notify the Contracting Officer.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 12

1.17 AFFIRMATIVE PROCUREMENT PROGRAM

A. The contractor is encouraged to recycle materials that shall be discarded as waste. Items that can be recycled in this community are asphalt, metals (including, but not limited to aluminum, copper, and steel), antifreeze, batteries, paper/cardboard, plastics, and used oil. This list is not all inclusive.

B. These standards apply to all new construction, demolition, rehabilitation, alteration, modification, repair, and maintenance of existing facilities.

1. In an effort to comply with the affirmative procurement requirements of Section 6002 of the Resource Conservation Recovery Act (RCRA) and Executive Order 13101, the government strongly promotes the use of the recycled and recovered materials and products identified in the Environmental Protection Agency’s Comprehensive Procurement Guidelines.

2. Recycled and recovered materials and products shall be considered first before any other materials and products shall be accepted. Recycled and recovered materials and products shall be used throughout the project unless they either do not meet the requirements of this specification, delay the progress of the work, or are cost prohibitive

3. Examples of these materials and products are detailed below. These are recommended quantities and represent minimum compliance. The actual requirement is to use the maximum amount of recycled material possible, while meeting the performance specifications.

Type Material Recycled Material %

Insulation Rock wool Slag 75 Fiberglass Glass cullet 20-25 Loose fill & spray on (cellulose)

Postconsumer paper 75

Perlite composition board Postconsumer paper 23 Plastic rigid foam Recovered material 9 Foam-in place Recovered material 5 Glass fiber reinforced Recovered material 6 Phenolic rigid foam Recovered material 5

Wall Board Structural fiberboard 80-100 Laminated paperboard Postconsumer paper 100

Carpet Polyester carpet face fiber Excludes severe wear applications

25-100

Playground surfaces Rubber or plastic 90-100 Running tracks Rubber or plastic 90-100

Cement/Concrete Concrete & cement Coal fly ash 15-35 Concrete & cement Ground granulated blast furnace (GGBF) 25-50

Flooring/Patio Patio blocks Plastic or plastic blends 90-100 Patio blocks Rubber or rubber blends 90-100 Floor tiles Rubber 90-100 Floor tiles Plastic 90-100

Recreational Surface Playground surface Rubber or plastic 90-100 Running track Rubber or plastic 90-100

Landscaping Paper based hydraulic mulch Postconsumer paper 100

Wood based hydraulic mulch Recoverd wood and/or paper 100

Compost 100

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 13

1.18 ENVIRONMENTAL PROTECTION

A. The Contractor shall comply with all applicable federal, state, and local laws and regulations covering environmental pollution control and abatement, and the specific requirements stated elsewhere in the contract specifications. In addition, the contractor shall comply with any applicable base instructions and plans. If requirements differ between any of the regulatory agencies, the most stringent requirement applies.

B. All general construction wastes, other than those specifically allowed, or required to be disposed of on-base shall be legally disposed at an off-base sanitary landfill. Handling and disposal of hazardous materials and hazardous wastes is described later in this Section.

C. Before disposal of concrete in either Flight Line pond or concrete or other C&D materials at Quarry Hill, the contractor shall complete the C&D form at the end of this Section. To retain concrete disposal privileges the contractor will provide reports weekly to CEIEC. These reports may be faxed to CEIEC at 377-3367.

D. Comply with the requirements of the “Eielson AFB Waste Disposal\Borrow Pit Worksheet”.

E. Part II, Eielson AFB Waste Disposal / Borrow Pit Worksheet.

1. If hazardous waste is generated due to the project scope (i.e. disposal of LBP chips), the contractor shall dispose of this material through the Eielson Hazardous Waste Facility in properly marked containers with sample analysis provided at the time of delivery. If waste is to be disposed of at designated base disposal sites, the following applies:

a. Concrete – Concrete must be screened for asbestos, POLs, LBP and glycols prior to disposal. All painted concrete must be screened for LBP using XRF. If results are greater the 1 mg/cm2, then a Toxic Characteristic Leaching Procedure (TCLP) test must be performed prior to disposal. At no time can the concrete contain free flowing liquids. Submit the completed C&D form prior to disposal.

b. Asbestos Containing Material: All disposal must be coordinated through the 354 CES/CEIEA. If Eielson’s asbestos landfill is used for disposal, contact the base Insulation Shop (354 CES/CEOII). Waste must be properly contained.

F. Comply with the Spill Reporting Procedures for both contractor caused spills and suspected contaminated soils or water found during excavation, new or not as described in the Appendix.

Retain signed copies at the contractor’s on-site office throughout construction.

G. Post the spill reporting placard (Example located at the end of this Section) at the on-site office in a conspicuous location. Ensure employees and subcontractor employees are aware of the location of the placard and of proper reporting procedures.

H. Comply with the Eielson AFB Fugitive Dust Emission Plan. Fugitive dust emissions (airborne dust generated by vehicles operating on unpaved surfaces, transfer or transport of dust producing materials, soil stockpiling, etc.) shall be controlled at the construction site, along haul routes and at staging areas. Water spraying shall be conducted as necessary, determined by contracting officer, to minimize fugitive dust generation. Limit traffic speeds on all unpaved road surfaces to 15 mph.

Any uncontaminated dirt or mud, which is tracked onto paved roadways shall be cleaned away that day. Depending on conditions, the roadway will be watered before cleaning or if a street sweeper is used, it will have a water system that controls dust around the sweeper during operation.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 14

1.19 ENVIRONMENTAL PROTECTION PLAN

A. The contractor shall prepare, submit, and comply with the approved provisions of an Environmental Protection Plan.

B. Two weeks prior to commencing construction activities or delivery of materials to the site, the contractor shall submit an Environmental Protection Plan for review and approval by the Contracting Officer and the 354 CES/CEIEC. The purpose of the Environmental Protection Plan is to present a comprehensive overview of known or potential environmental issues which the contractor must address during construction. The contractor shall address each topic at a level of detail commensurate with the environmental issue and required construction task(s). The contractor shall include environmental issues associated with the specific project. After submittal and review of the Environmental Protection Plan, the contractor shall meet with the Contracting Officer and the 354 CES/CEIEC for the purpose of discussing the implementation of the Environmental Protection Plan; possible subsequent additions and revisions to the plan including any reporting requirements; and methods for administration of the contractor's environmental plans.

The Environmental Protection Plan shall be current and maintained onsite by the contractor.

C. The ENVIRONMENTAL PROTECTION PLAN (EPP) shall include, but is not limited to, the following listed items. Respond to all listed items. If an item is not applicable to project work, then give a short explanation of why it is not. Include discussions of any other environmental issues germane to the work, even if a particular topic may not appear in the following list.

1. Name(s) and contact information of person(s) within the Contractor's organization who is (are) responsible for ensuring adherence to the Environmental Protection Plan.

2. Name(s) and qualifications of person(s) responsible for manifesting hazardous waste, and asbestos and lead-based paint (LBP) to be removed from the site, if applicable.

3. An erosion and sediment control plan.

a. If applicable, include clarification and justification why the project does not require a NPDES Construction General Permit (CGP).

b. Include measures to minimize the amount of mud transported onto paved public roads by vehicles and methods to control runoff and to contain materials on the site.

c. If a SWPPP is prepared it may be substituted for this plan, but not vice versa. The SWPPP must be prepared as a separate stand-alone document. NOTE: A SWPP is not required unless the project, including office trailer, staging area, parking, etc., will disturb an area equal to at least one acre.

4. Drawings showing locations of proposed temporary material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials including methods to control runoff and to contain materials on the site.

a. Soil shall not be stockpiled in areas classified as wetlands. If soils are contaminated they must be handled as described in the sampling and analysis plan provided by the contractor which shall meet all state environmental and OSHA requirements.

5. Spill Control Procedures: The EPP shall include spill response procedures, cleanup supplies onsite, instructions, and reports to be used in the event of an unforeseen spill of a substance regulated by 40 CFR 68, 40 CFR 302, 40 CFR 355, and/or regulated under State or Local laws

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 15 and regulations. The 354 CES/CEIEC shall complete any necessary agency reporting requirements associated with a spill. The plan shall include as a minimum:

a. The name and contact information of the individual who shall report any spills or hazardous substance releases. This individual shall immediately notify 377-SPIL (7745) and the Contracting Officer. The spill phone is manned 24 hours a day. If 377-SPIL is unavailable, the contractor shall call the Facility Fire Department and request they contact the 354 CES/CEIEC. The plan shall contain a list of the required reporting channels and telephone numbers.

b. The name and qualifications of the individual who shall be responsible for implementing and supervising the containment and cleanup.

c. Location of temporary fueling facilities and associated spill control measures. Secondary containment provisions shall be required for any container or group of containers co-located holding 55 gallons or more of petroleum products or hazardous materials.

6. Air Emissions: An air pollution control measures plan, detailing provisions to assure that dust, debris, materials, trash, etc., do not become air borne and travel off the project site, shall be provided.

7. Contaminant prevention procedures that identify potentially hazardous substances to be used on the job site, intended actions to prevent introduction of such materials into the air, water, or ground; and details provisions for compliance with Federal, State, and local laws and regulations for storage and handling of these materials.

8. Identify removal or installation of electrical equipment containing oil. This includes any analysis required to identify PCB contamination.

9. Waste Water (other than storm water) Management Plan. Identify the methods for management and/or discharge of waste waters which are directly derived from construction activities, such as concrete curing water, clean-up water, dewatering of ground water, disinfection water, hydrostatic test water, and water used in flushing of lines, etc.

a. If a settling/retention pond is required, the plan shall include the design of the pond including drawings, removal plan, and testing requirements for possible pollutants.

b. If disposal is to a sanitary sewer, the plan shall include documentation that the Waste Water Treatment Plant Operator has approved the flow rate, volume, and type of discharge.

c. If there will be dewatering, surface discharge or discharge from a container, that meet the state requirements for a permit, the contractor is responsible for obtaining the required permitting. If the contractor determines that no permit is required for these actions, clarify that within the plan. Permit applications must be submitted and approved 354 CES/CEIEC prior to submittal to the state. A copy of each permit shall be included in the plan.

d. If land application will be the method of disposal for the wastewater, the plan shall include a sketch showing the location for land application along with a description of the pretreatment methods to be implemented and erosion mitigation.

e. If discharge is from a container (i.e. discharge after hydrostatically testing a new tank), the contractor is responsible for obtaining the required permitting. Permits must be reviewed by 354 CES/CEIEC prior to submittal to the state.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 16

10. Copies of all required permits and notices to proceed, notices of intent and regulatory agency plans.

11. Waste Disposal Plan:

a. List each type of waste which the Contractor anticipates will be generated and the proposed disposal sites.

b. Identify any subcontractors responsible for the transportation and disposal of solid waste.

Submit copies of licenses or permits for solid waste disposal sites that are not commercial operating facilities.

c. Submit weight tickets to 354 CES/CEIE Solid Waste Program for all materials disposed off-site, including, but not limited to landfill or recycling facilities. Weight tickets shall be submitted to the CO by the end of the month in which they were generated.

12. Hazardous Waste Plan: Provide a Hazardous Waste Plan that includes, at a minimum, the following:

a. Types of waste that will be generated.

b. Methods of Hazardous Waste Storage.

c. Initial Hazardous Waste Accumulation Log

1.20 HAZARDOUS MATERIALS MANAGEMENT

A. Submit an inventory of all hazardous materials listed in OSHA Hazard Communications Standard 29 CFR 1910.1200, Class I and II ozone depleting substances and all items, including medical supplies, covered under Emergency Planning and Community Right-to-Know Act (EPCRA) tracking requirements which shall be brought on site. The inventory shall include a table identifying the material, initial quantity, quantity used, unit of issue, manufacturer, and product code. This table must be updated and submitted quarterly during the project, unless additional quantities/materials are added, at which time the Contractor has seven days to provide the additional information and material safety data sheet (MSDS). At project completion, submit an updated inventory indicating quantities used, and disposed. See the attached Hazardous and Regulated Material Identification Form.

1. Any hazardous materials transported on site shall have an MSDS and a copy must be delivered to the Contracting Officer and the HAZMART (Bldg 3446).

2. All hazardous material shall be removed from the site by the contractor at project completion unless other provisions within the contract direct otherwise.

B. HAZMAT Usage and Reporting: Report the usage of all hazardous materials to the government for all work performed on Eielson AFB. Provide the Contracting Office with a list of proposed HAZMAT that is planned for use on the installation during the performance of the contract. Obtain Air Force authorization prior to using HAZMAT on Eielson, and report usage data to the Hazardous Material Pharmacy (HAZMART).

1. A hazardous material is any substance defined by OSHA as a hazardous substance requiring a MSDS. Hazardous materials that need to be reported include but are not limited to chemicals, MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 17 paints, thinners, sealing compounds, strippers, glues, solvents, all petroleum products including oils, hydraulic fluids, and fuels stored on-site (fuels in vehicles are exempt), pesticides, adhesives, acids, flammables, corrosives, oxidizers, compressed gases (such as but not limited to oxygen, acetylene, propane, flammable and non-flammable gases), all aerosols, and all materials containing hazardous substances.

2. The contractor shall request the proposed usage of all hazardous materials by completing the Hazardous and Regulated Material Identification Form, Appendix C, for each hazardous material and shall submit a copy of the MSDS for each item to the Contracting Officer (CO) prior to bringing the items on the installation. The Contractor shall submit to the CO the information for each item not less than fourteen calendar days prior to bringing the items on the installation. An electronic version of the Hazardous and Regulated Material Identification Form can be obtained through the project manager or 354 CES/CEIEC.

C. Hazardous Materials Management Process (HMMP): The Eielson AFB HMMP team will review the Hazardous and Regulated Material Identification Form and MSDSs to ensure there are no concerns with the chemicals being used and/or stored on the installation. If there are concerns about any chemicals to be used on Eielson AFB, the HMMP team will notify the project manager and the Contracting Officer (CO) who will in-turn notify the contractor of Eielson AFB’s concern.

The contractor shall not bring any chemicals on Eielson AFB that the HMMP team determines cannot be used on Eielson.

1. If the contractor requires additional hazardous materials not previously submitted for approval, they shall submit the request as stated above seven days prior to bringing the item on the base.

2. If it is determined at any time that hazardous materials are on site that were not reported in advance, the CO may issue a stop work notice until the materials are either submitted as stated above or removed from the base.

D. Hazardous Material Storage: Hazardous materials shall be managed properly at all times while on Eielson AFB. Containers shall be in good condition and shall be properly labeled with the contents and hazard class (flammable, corrosive, oxidizer, etc) at all times. Containers shall be closed at all times when not in use, hazardous materials shall be kept under cover to protect them from the elements and to prevent storm water runoff contamination. Tanks and 55-gallon liquid drums shall have secondary containment. Gas cylinders shall be maintained in the upright position with caps on and shall be secured with chains to prevent them from falling over. Gas storage areas shall have signs indicating what type gases are stored in the area (i.e. flammable, oxidizer, non-flammable, etc). NO SMOKING signs shall be posted in all hazardous materials storage areas. In addition, all hazardous materials shall be segregated in storage according to compatibility (i.e. flammables shall not be stored with corrosives, corrosives shall not be stored with oxidizers, flammable gases shall not be stored with flammable liquids, etc). Eielson AFB is subject to inspections at any time from outside agencies (EPA, ADEC, and OSHA). Any violations by the contractor and associated penalties and fines shall be the responsibility of the contractor.

1.21 HAZARDOUS WASTE

A. All hazardous wastes as defined in 40 CFR, Part 261, shall be collected and disposed of in accordance with 40 CFR, Parts 260-268, and FWI 32-7005, Hazardous Materials Management.

The contractor is responsible for properly storing, marking, labeling, securing and transporting hazardous wastes. All hazardous wastes shall be collected in contractor furnished Department of Transportation (DOT) / United Nations (UN) approved containers. The contractor shall not store hazardous waste on base for more than 30 days.

MAINTAIN TURBINE-GENERATOR#4

EIELSON AFB, ALASKA

FTQW 15-1001

ATTACHMENT JA-1

01030 - 18

B. Hazardous Waste Storage: Secondary containment is required for storage of 55 gallons or more of liquids.

C. Maintain a Hazardous Waste Accumulation Log (See example located at the end of this Section) at the work site. Ensure containers are labeled with the start date when the hazardous waste was first put in the containers and are updated when adding waste to the container. The start date begins when the initial deposit of hazardous waste is placed in the container.

D. Provide laboratory analysis reports and/or MSDSs with waste for disposal.

E. Contractor shall arrange for disposal of all hazardous waste through the Hazardous Waste Facility, building 4388. Call 377-2574 to coordinate delivery of hazardous waste a minimum of 48 hours prior to transporting the waste to the Hazardous Waste Facility.

F. Examples of waste to be disposed of at the Hazardous Waste Facility include but are not limited to:

1. Used Oil, Paint Thinner, Contaminated Rags, Spill Clean- Up Materials, waste generated from a project etc.

2. Mercury Thermostats.

3. Smoke detectors.

4. All bulbs, fluorescent, high sodium, u-shaped.

5. Batteries (not alkaline they go in solid waste).

6. Transformers.

7. Light Ballasts (PCB contaminated).

G. Questions regarding disposal of hazardous waste should be directed to 354 CES/CEIEC, 377-1659.

1.22 HAZARDOUS WASTE TESTING

A. The Contractor shall subject a representative sample of each type of hazardous waste, or potentially hazardous waste, generated to TCLP (Toxic Characteristic Leaching Procedure) testing.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .