ATTACHMENT JA-6 APPENDIX 5 PAGE 2
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAINTAIN TURBINE-GENERATOR #5
FTQW 12-1015
NOTE REGARDING FLOOR STRUCTURE DRAWINGS
The turbine room floor has been extended several times during the life of the Central Heat & Power Plant. When originally constructed, the turbine room housed only turbines #1 and #2. Two years later, the turbine room was expanded to house turbine #3. In the 1960s, the room was again extended to accommodate turbine #4. Finally, in the 1980s, the room was extended to house turbine #5.
The drawings provided show the various extensions of the floor over the years.
Bidders are strongly encouraged to visit the site before bidding to see what equipment is currently mounted to the floor and what areas are available for laydown of parts and equipment.