Phase_II_Q&A_-_Part_2.pdf
PDF 218 KB Posted
- Attached to
- Repair Hangar Fire Suppression System Federal contract opportunity
- Solicitation number
- FA4855-17-R-0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Phase_II_Q&A.pdf | ||
| Atch_15-Past_Performance_Questionnaire.pdf | ||
| FP-2_Demo_FP_Zone_1.PDF | ||
| FP-3_Demo_FP_Spray_Booth_Hanger_1.PDF | ||
| Questions_and_Answers.pdf | ||
| FP-1_Demo_FP_Zones_2_&_3.PDF | ||
| FP-4_Demo_FP_Hangers_2_&_3.PDF | ||
| Atch_11_-_AEC_CAD_Standard_TR-12-X_R-6.pdf | ||
| Atch_9-CAFB_DDC_Requirements_Guide_-_Sep_2014.pdf | ||
| Atch_12-As-Built_Submittal_Guidelines.pdf | ||
| FA4855-17-R-0003.pdf | ||
| Atch_7-CANNONAFBI32_201_Fire_Protection.pdf | ||
| Atch_10-CAFB_Labeling_Standards__2009_Rev1.pptx | PPTX presentation | |
| Atch_2-SOMS.pdf | ||
| Atch_14-Entry_Authorization_List.pdf | ||
| Atch_8-CAFB_Hardware_Specifications_Guideline-_2011.pdf | ||
| Atch_13-CAFB_Environment_Guide_2015.pdf | ||
| Atch_6-CAFB_Architec_Compat_Guide-2013.pdf | ||
| Atch_4-CAFB_Electrical_Standards-2016.pdf | ||
| Atch_5-Contractor_Base_Briefing_Pamphlet_(March_2016).pdf | ||
| Atch_1-SOO.pdf | ||
| Atch_3-WDNM23.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4855-17-R-0003 H199 Phase II Questions Part 2
1. While there is no mention of Mass Notification System upgrades or new work in the body of the SOO, based on the last Q&A, and reference documents which relate to a Mass Notification System (MNS), it might be inferred that there is a requirement with respect to MNS. Is there any requirement to install a new MNS or modify or upgrade the existing MNS capabilities in H199?
Answer: This is a design build contract. Reference Documents section of the SOO require the designer to review UFC 4-021-01 Design and O&M: Mass Notifications Systems, with change 1, January 2010 and other applicable sections. The supplemental information provide in the Q&A was provide if the Designer of Record,( DOR) for this project determines it is a requirement. The SOW and/or the Design Analysis will explain all applicable requirements for this contract followed by subsequent drawings and specifications.
2. If so, are the office areas are to be included in the mass notification requirement?
Answer: This is a DOR responsibility of a MSN is determined to be required. Refer to applicable sections of the Reference Documents section to confirm the requirements. The SOW and/or the Design Analysis will explain all applicable requirements for this contract followed by subsequent drawings and specifications.
3. Also if so, In addition, is voice messaging and live voice capability from the fire department a requirement?
Answer: No
4. On the SF1442 where we have to acknowledge the Amendments. How many were there? And what dates would I put? I see there were answers and questions answered but do not see that they are Amendments
Answer: There are no amendments, to date, for the subject solicitation.