Atch_2-SOMS.pdf
PDF 17 KB Posted
- Attached to
- Repair Hangar Fire Suppression System Federal contract opportunity
- Solicitation number
- FA4855-17-R-0003
About this file
Atch 2: SOMS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Phase_II_Q&A_-_Part_2.pdf | ||
| Phase_II_Q&A.pdf | ||
| Atch_15-Past_Performance_Questionnaire.pdf | ||
| FP-1_Demo_FP_Zones_2_&_3.PDF | ||
| FP-4_Demo_FP_Hangers_2_&_3.PDF | ||
| Questions_and_Answers.pdf | ||
| FP-2_Demo_FP_Zone_1.PDF | ||
| FP-3_Demo_FP_Spray_Booth_Hanger_1.PDF | ||
| Atch_14-Entry_Authorization_List.pdf | ||
| Atch_8-CAFB_Hardware_Specifications_Guideline-_2011.pdf | ||
| Atch_13-CAFB_Environment_Guide_2015.pdf | ||
| Atch_6-CAFB_Architec_Compat_Guide-2013.pdf | ||
| Atch_4-CAFB_Electrical_Standards-2016.pdf | ||
| Atch_5-Contractor_Base_Briefing_Pamphlet_(March_2016).pdf | ||
| Atch_1-SOO.pdf | ||
| Atch_3-WDNM23.pdf | ||
| Atch_12-As-Built_Submittal_Guidelines.pdf | ||
| FA4855-17-R-0003.pdf | ||
| Atch_7-CANNONAFBI32_201_Fire_Protection.pdf | ||
| Atch_10-CAFB_Labeling_Standards__2009_Rev1.pptx | PPTX presentation | |
| Atch_11_-_AEC_CAD_Standard_TR-12-X_R-6.pdf | ||
| Atch_9-CAFB_DDC_Requirements_Guide_-_Sep_2014.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
L I N E
N U M B E R
ITEM, DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
O
F C
O M
PL
IA
N C
E
SH
O
P D
R A
W
IN
G S
SA
M
PL
E
S / C
O L
O R
S E
L E
C T
T E
ST
R
E
SU
L T
S
M A
N F'
R R
E C
O M
M E
N D
A T
IO
N
S
M A
N F'
R . W
A R
R A
N T
Y
L
IC
E N
SE
D
A
PP
L
IC
A T
O R
E L
E C
T R
O N
IC
F
IL
E
(E M
A
IL
E D
T
O C
O N
S)
E L
E C
T R
O N
IC
F
IL
E
S( C
D
PR
IN
T E
D C
O
PI
E S
R E
Q U
IR
SU
B M
IS
SI
O N
D A
T E
D A
T E
R E
C E
IV
IN
C O
N T
R A
C T
IN
G
D A
T E
IV
IL
E
N G
IN
E
E R
IN
G
R E
T U
R N
S U
SP
E
N
SE
D A
T E
FO
L
L O
W -U
P
C O
N T
R A
C T
O R
N O
T
IF
IE
A pp ro va l D at e
C O
N T
R A
C T
O R
N O
T
IF
IE
D
D is ap pr ov al D at e
C O
N T
R A
C T
R
-S U
B M
IT
T
A L
FI
N
A L
A
PP
R O
V A
L
R E
M A
R K
S
1 DESIGN PROJECT SCHEDULE- AF3064
AND GANTT CHART (SOO §11.1.) 1 Within 7 calendar days of
NTP
MEETING MINUTES FROM KICK OFF
MEETING/ PRE-DESIGN MEETING
(SOO §7.)
1 Within 7 calendar days of meeting occurrence.
SITE SURVEY OF EXISTING
CONDITIONS MEETING MINUTES
(SOO §11.2.1.)
1 Within 7 calendar days of meeting occurrence.
4 DESIGN QUALITY CONTROL PLAN
(SOO §11.3.) 1 1 Within 7 calendar days of
NTP
35% DESIGN PACKAGE (SOO §11.4.1.)
Statement of Work (SOW), Design Analysis, Schedule of Material Submittals (SOMS) and Drawings are required.
***Government will have 14 calendar days for review and provide comments.
Contractor will then be allotted 14 calendar days to incorporate comment in the next phase of design ***
1 1 21 calendar days after NTP
6 35% DESIGN REVIEW COMMENT
MATRIX RESPONSES (SOO §11.5.) 1
Within 7 calendar days review documents have been returned.
Optional 35% DESIGN PHASE
MEETING MINUTES (SOO §11.6.)
***Only required if meeting occurs****
1 Within 7 calendar days of meeting occurrence.
65% DESIGN PACKAGE (SOO §11.4.2.)
Statement of Work (SOW), Design Analysis, Schedule of Material Submittals (SOMS) and Drawings are required.
***Government will have 14 calendar days for review and provide comments.
Contractor will then be allotted 14 calendar days to incorporate comment in the next phase of design ***
1 1 49 calendar days after NTP
9 65% DESIGN REVIEW COMMENT
MATRIX RESPONSES (SOO §11.5.) 1
Within 7 calendar days review documents have been returned.
NUMBER OF COPIES REQUIRED
AF FORM 66 SCHEDULE OF MATERIALS SUBMITTALS
PROJECT # PROJECT TITLE SOLICITATION/CONTRACT NO.
CZQZ-15-0012 REPAIR FIRE
PROTECTION IN B199
TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
L I N E
N U M B E R
ITEM, DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
O
F C
O M
PL
IA
N C
E
SH
O
P D
R A
W
IN
G S
SA
M
PL
E
S / C
O L
O R
S E
L E
C T
T E
ST
R
E
SU
L T
S
M A
N F'
R R
E C
O M
M E
N D
A T
IO
N
S
M A
N F'
R . W
A R
R A
N T
Y
L
IC
E N
SE
D
A
PP
L
IC
A T
O R
E L
E C
T R
O N
IC
F
IL
E
(E M
A
IL
C
O N
S)
E L
E C
T R
O N
IC
F
IL
E
S( C
D
PR
IN
T E
D C
O
PI
E S
R E
Q U
IR
SU
B M
IS
SI
O N
D A
T E
D A
T E
R E
C E
IV
IN
O
N T
R A
C T
IN
G
D A
T E
IV
IL
E
N G
IN
E
E R
IN
G
R E
T U
R N
S U
SP
E
N
SE
D A
T E
FO
L
L O
W -U
P
C O
N T
R A
C T
O R
N O
T
IF
IE
A pp ro va l D at e
C O
N T
R A
C T
O R
N O
T
IF
IE
D
D is ap pr ov al D at e
C O
N T
R A
C T
-S U
B M
IT
T
A L
FI
N
A L
A
PP
R O
V A
L
R E
M A
R K
S
NUMBER OF COPIES REQUIRED
AF FORM 66 SCHEDULE OF MATERIALS SUBMITTALS
PROJECT # PROJECT TITLE SOLICITATION/CONTRACT NO.
CZQZ-15-0012 REPAIR FIRE
PROTECTION IN B199
TO BE COMPLETED BY PROJECT ENGINEER
Optional 65% DESIGN PHASE
MEETING MINUTES (SOO §11.6.)
***Only required if meeting occurs****
1 Within 7 calendar days of meeting occurrence.
95% DESIGN PACKAGE (SOO §11.4.3.)
Statement of Work (SOW), Design Analysis, Schedule of Material Submittals (SOMS) and Drawings are required.
***Government will have 14 calendar days for review and provide comments.
Contractor will then be allotted 14 calendar days to incorporate comment in the next phase of design ***
1 1 77 calendar days after NTP
12 95% DESIGN REVIEW COMMENT
MATRIX RESPONSES (SOO §11.5.) 1
Within 7 calendar days review documents have been returned.
Optional 95% DESIGN PHASE
MEETING MINUTES (SOO §11.6.)
***Only required if meeting occurs****
1 Within 7 calendar days of meeting occurrence.
100%/FINAL "ISSUE FOR
CONSTRUCTION" PACKAGE (SOO
§11.4.4) Statement of Work (SOW), Design Analysis, Schedule of Material Submittals (SOMS) and Drawings (1 half size and 1 full size) are required.
1 2 105 calendar days after
NTP
CONSTRUCTION PROJECT
SCHEDULE- AF3064 AND GANTT
CHART (SOO §26.1.)
Within 7 calendar days after 100% Design Package Approval
16 CONSTRUCTION QUALITY CONTROL
PLAN (SOO §26.2.) 1 1
Within 7 calendar days after 100% Design Package
Approval