ChavezATFP_Q As_Part_2.pdf

PDF 200 KB Posted

Attached to
Chavez CDC Post Inspection ATFP Upgrades Federal contract opportunity
Solicitation number
FA4855-16-B-0021
Issued by
Department of the Air Force Special Operations Command

About this file

Chavez ATFP Questions and Answers Part 2

View the file

Other files for this federal contract opportunity

Other files attached to Chavez CDC Post Inspection ATFP Upgrades, newest first.
File Type Posted
FA4855-16-B-0021_SF1409.pdf PDF
SOW_Para_3.7_Picture.jpg JPG image
SOW_-_CZQZ160053_CDC_ATFP_Upgrades_-_1_Sep_16.pdf PDF
Drawings_-_CZQZ16-0053_Chavez_CDC_ATFP_Upgrades.pdf PDF
ChavezAFTP_Questions_and_Answers.pdf PDF
FA4855-16-B-0021-0001_Priority_Changes.pdf PDF
Drawings_-_CZQZ16-0053_Chavez_CDC_ATFP_Upgrades.pdf PDF
Specs_-_CZQZ160053_CDC_ATFP_Upgrades_w_options_30_June_16.pdf PDF
SOMS_-_CZQZ160053__30_June_16.pdf PDF
EAL_Chavez_ATFP.docx DOCX document
WD_NM_23.txt TXT text file
SOW_-_CZQZ160053_CDC_ATFP_Upgrades.pdf PDF
FA4855-16-B-0021 _Chavez_ATFP.pdf PDF
WD_NM_23.txt TXT text file
Drawings_-_CZQZ16-0053_Chavez_CDC_ATFP_Upgrades.pdf PDF
Specs_-_CZQZ160053_CDC_ATFP_Upgrades_w_options_30_June_16.pdf PDF
SOMS_-_CZQZ160053__30_June_16.pdf PDF
SOW_-_CZQZ160053_CDC_ATFP_Upgrades.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4855-16-B-0021 : Chavez ATFP

Site Visit Questions

Reference Question Answer

IFB CLIN 0003 Fence Additive Priority

#1

It was brought up during the site visit that both sides of the Chavez entry control point will have a wall constructed on both sides on the road heading west towards the ECP – in CLIN item 0003 it states 115ln/ft however this footage would be incorrect please clarify.

Fence identified along the both sides of the roadway leading up to the entry control point is identified in SOW 3.8. Option 1 is for the rod iron fencing and gates crossing the roadway. Refer to the revised drawings and SOW for clarification.

SOW §3.10

Is the existing MNS under any warranty currently, will the Government require any specialized certifications of the person or persons relocating the panel? Does the

Government have a wiring schematic of the existing MNS system?

The mass notification system is not under warranty and is required to be tested prior to being moved to verify it is in working condiiton. A wiring schematic is not available for the existing system.

NO REFERENCE GIVEN

How far north does the base property line exceed into the farmers field on the north end of existing wall and security fence? Does the Government have a preferred route they would like the contractor to adhere to within this area?

The property line varies in distance from the perimeter fence line and driving along the north side of the perimeter may require the government to get a right of way from the abutting property owner depending on the size of the equipment and space need for construction. Anticipate approximately three months for the Air Force to process the right of entry request from the property owners.

NO REFERENCE GIVEN

What is the period of performance remaining for the contractor working near the ranch vale highway? It was discussed the contractor will need to coordinate and secure the site at the end of each day during this phase.

Both contracts will be working simultaneously. Government will coordinate access once a schedule is submitted for review. Contractor to anticipate a schedule review time of 30 calendar days to coordinate.

NO REFERENCE GIVEN Will weekend work be permitted if need be on this contract?

Weekend work should not be anticipated on this project, however, with a valid justification exceptions will be made on a case by case basis.

SOW §3.1.1

Is the contractor responsible for providing the industrial pad locks to be used on these gates?

If so please provide requirements.

Padlocks will not need to be included as part of this contract but the locking mechanism must be capable of accepting a padlock identified in the Cannon AFB Door Hardware Specification Guidline and

Performance Specification.

SOW §3.3.1 Is this gate to match the existing gate east of bldg. 7019? NO, Refer to drawings and details for clarification.

SOW §3.3.2 Is this gate to match the existing gate east of bldg. 7019? NO, Refer to drawings and details for clarification.

SOW §3.4 Is this gate to match the existing gate east of bldg. 7019?

Yes, the new gate is to match the existing gate East of building 7019 and 7008.

SOW §3.4.2 Please provide a detailed drawing and any further requirements for these signs.

Exact verbiage to be confirmed. For the purposes of estimating a cost, the sign shall be a MUTCD type sign and will not exceed 9 square feet in size.

SOW §3.5.1

Will the contractor be allowed to drive vehicles and delivery trucks along the unsecured side of this fence and wall? Will contractor be allowed to store material on the unsecured side of this fence and wall?

The contractor will be allowed to drive on unsecure side of the fence, however, driving along the north side of the perimeter may require the government to get a right of entry from the abutting property owner depending on the size of the equipment.

SOW §3.9

Please provide the wiring requirements for the locks to be used on these doors. Will magnetic door hold-open devices be used? What other hardware will be required (i.e. kick plates, wall bumpers, floor sweeps, smoke seal)?

Double Lock (DBL Doors) Part#1512V

Desk Top Release Button Part#DTOM-1

Mechanical Request to Exit Bar Part#MSB550V

Motion Detector (2nd Form of Egress) Part#MD-31DOW

Door Release Lanyard Remote Part#WRC-R2/RB

Exit Button (AHJ prerequisite Form of Egress) Part#422U

Magnetic Hold Opens Part#EH201224A

Keypad/Prox reader (Authorized Egress) Part#920P

Proximity Cards Part#HID1326-25

Power Supply Part#602RF

Emergency Release (AHJ Prerequisite) Part#492

Backup Batteries (Upon Power Failure) Part#RB12V4-2

Power Controller (Audit Trail) Part#IPPRO

Parts list from Http://sdcsecurity.com or an equal product.

Install per manufacturers instructions and connect alarm signal to fire alarm panel. Door, frame, kick plates, hinges, child finger protection, closures, latches, exit devices, strike plates, wall bumpers, smoke seal, floor sweeps, threshold, and wiring for a complete door system.

SOW §3.11 Please provide a detailed drawing and any further requirements for these signs.

Install new warning signs to match existing on the new wall, fence, and at each gate. Max spacing for wall and fence shall be 200 feet. Follow the Air Force Visual Aid (AFVA) 31-

211 Installation Warning Sign

18X15 design and AFVA 31-206, Military Working Dog Notice, directly below AFVA 31-211. These signs should use a white background and black for the lettering. Signs adhered to sheet metal and fastened to the block wall, rod iron, and/or chain link fence.

SOW §3.12 What are the requirements for temporary fencing?

Work area shall have a weather-proof sign posted on the external side of the gate listing the prime contractor, contact information, the current contact number(s), and the expected completion date of the contract. In addition to this information, the contractor is required to comply with EM 385-1-1 and OSHA standards for work safety signage.

(e.g. EM 385-1-1 04.A.04 and applicable paragraphs of section 8 for the work elements to be performed).

SOW §3.14.1 Can these doors be installed during off hours when there will be no pedestrians present?

Work hours outside of the Daily Work Schedule (SOO paragraph 14) should not be anticipated on this project, however, with a valid justification exceptions will be made on a case by case basis.

SOW §23 What are the signage requirements for temporary fencing?

Work area shall have a weather-proof sign posted on the external side of the gate listing the prime contractor, contact information, the current contact number(s), and the expected completion date of the contract. In addition to this information, the contractor is required to comply with EM 385-1-1 and OSHA standards for work safety signage.

(e.g. EM 385-1-1 04.A.04 and applicable paragraphs of section 8 for the work elements to be performed).

Red and Green Bordered Work Area Descriptions

How much room north of the north work area will be available for transportation and work area?

The property line varies in distance from the perimeter fence line and driving along the north side of the perimeter may require the government to get a right of entry from the abutting property owner depending on the size of the equipment and space need for construction. Anticipate approximately three months for the Air Force to process the right of way request from the property owners.

Red and Green Bordered Work Area Descriptions Several trees are along the proposed north fence area. Which of these will be retained?

Contractor to remove trees along fence line. Note to be added to documents.

Red and Green Bordered Work Area Descriptions Should note on red bordered photo say with “outriggers”. Yes, refer to specifications section 32 31 13 Chain Link Fence and Gates

Blue Bordered Work Area

Descriptions What vertical clearance is required from overhead power lines?

XCEL power lines are 115 KV and vary in height

Refer to OSHA 1926.1408(h), NFPA 70E table 130.4(D)(a), and IEEE C2 for minimum clearance distances.

Blue Bordered Work Area

Descriptions Is this wall to be a decorative cmu fence?

Wall to match existing wall at the eastern perimeter and south of the

Entry Control Point refer to picture labeled SOW 3.7 and drawings for details.

Yellow Bordered Work Area

Descriptions

What vertical clearance is required from overhead power lines?

XCEL power lines are 115 KV and height varies along NM311

Refer to OSHA 1926.1408(h), NFPA 70E table 130.4(D)(a), and IEEE C2 for minimum clearance distances.

Sheet C-303 A pedestrian type gate entrance is shown on this sheet but not referenced on the plans. Is a gate to be included.

Yes, a gate with a latch capable of installing a base padlock. Drawings and Statement of Work updated for clarification

Sheet C-303 On detail 2, a reference is made to sheet A-302 for reinforcing and fill. Should the reference be to C-305. Yes, drawings updated to reflect changes.

Sheet C-304 On drawings 1 and 4, references are made to a cable conduit and a reference to A-302. Is a conduit needed and, if so, what size? Cable and conduit not used on this project. Detail to be updated.

Sheet AS401 This sheet has details for a fence for a dumpster enclosure. Is a dumpster enclosure required?

Dumpster enclosure not required on this project and documents revised.