Attachment 08 - Q and A.pdf

PDF 797 KB Posted

Attached to
B1947 Install Outlets
Solicitation number
FA480325R0017
Issued by

About this file

This document is a Solicitation Questions and Answers memorandum for Air Force contract FA480325R0014 issued by the 20th Contracting Squadron at Shaw Air Force Base. The document addresses two specific technical questions from potential contractors: 1) whether ladder or lift equipment will be needed for electrical work (ladders are deemed sufficient for the 10' ceiling height), and 2) wire size specifications (8AWG wire confirmed, with ampacity adjusted per National Electrical Code requirements). The memorandum instructs contractors to acknowledge all amendments in their proposal and provides contact information for the Contracting Specialist SrA Tariq Ellis and Contracting Officer SSgt Christon Reed, with a warning that failure to acknowledge amendments may result in a non-responsive proposal.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

20TH FIGHTER WING (ACC)

SHAW AIR FORCE BASE SOUTH CAROLINA

VICTORY BY VALOR

27 March 2025

MEMORANDUM FOR SOLICITATION FA480325R0014

FROM: 20th Contracting Squadron/PKB 321 Cullen Street, Building 216 Shaw Air Force Base, SC 29150

SUBJECT: Solicitation Questions and Answers

1. Can all work be done off of ladders? Or will a lift be required?

a. The plan is to have the electrical run through the ceiling, which is approximately 10’ high, so ladders should be sufficient for the scope of work.

2. The SOW says #8 wire, but we also see #10 wire. What size wire does the facility want for this?

a. As far as the wire size, it should be 8AWG, the ampacity was adjusted for the number of conductors running through the conduit, according to the

NEC.

3. All other information as stated in the Solicitation remains unchanged.

4. Note: Please ensure you include acknowledgement of this and all amendments in your proposal. Failure to do so may result in your proposal being found nonresponsive.

5. Please direct all concerns to the Contracting Specialist, SrA Tariq Ellis at tariq.ellis@us.af.mil and the Contracting Officer, SSgt Christon Reed at christon.reed@us.af.mil