Atch_4_-_Schedule_of_Material_Submittals.pdf
PDF 373 KB Posted
- Attached to
- Repair (Sus) Airfield Lighting System (South)
- Solicitation number
- FA4621-13-R-0003
About this file
FA4621-13-R-0003 Atch 4 Schedule of Material Submittals
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPROVED DISAPPROVED
1 Section 01 10 00, Para 1.08.A Environmental Handling & Disposal Plan 4 Prior to Start
Work 2 Section 01 10 00, Para 1.08.B
Dust Control Haul Routes 4 4 5 Days Prior to Haul
3 Section 01 10 00, Para 1.08D.
MSDS Sheets 4 21 Days After
NTP
4 Section 01 10 00, Para 1.08F.
RECYCLED/RECLAIMED/DISCARDED
MATERIALS
4 15 Days Prior to closeout
5 Section 01 10 00, Para 1.11 Quality Control 4 21 Days After
NTP
6 Section 01 10 00, Para 1.12A
Redline Record Drawings & Specs.
Prior to Final
Inspection 7 Sectin 01 10 00, Para 1.12.C
Final Record Drawings 10 Days After
Final Inspection 8 Section 01 10 00, Para 1.13
Geospatial Data Quality Control Report 2 2 10 Days After Final Inspection
9 Section 01 10 00, Para 1.12.H.7 DD Form 1354 4 60 Days Prior
Final Inspection 10 Section 01 10 00, Para 1.16A
Pre-final Inspection Request 14 Days Prior to
Completion 11 Section 01 10 00, Para 1.16.B
Final Inspection Request 7 Days Prior to
Completion 12 Section 01 10 00, Para 1.17
Utility Interruption 4 30 Days Prior
13 Section 01 10 00, Para 1.20 Lockout/Tagout Procedure 4 Prior to Start
Work 14 Section 01 10 00, Para 1.24
Training on Facility Systems Notice 4 7 Days Prior to Final Inspection
15 Section 01 10 00, Para 1.26 Site Plan for Temporary Facilities 4 Prior to Start
Work 16 Section 01 17 00, Para 1.4
Site Security Plan 4 14 Days Prior to Coord Meeting
Section 01 30 00 , Para 1.5.1
List of contact personnel
21 Days After NTP and Update
As-Required 18 Section 01 30 00 , Para 1.2
View location map 4 21 Days After
NTP
4 letters
4 letters
M A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
2 sets of Drawings, 2 sets Specifications
3 CD's, 1 half size blackline
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
FA4621-13-R-0003 Attachment 4 Schedule of Material Submittals
M A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
19 Section 01 30 00 , Para 1.3 Progress and completion pictures 4 Monthly
20 Section 01 32 01.00 10 , Para 3.4 Project Schedule 4 15 Days After
NTP
Section 01 35 26 , Para 1.6 Accident Prevention Plan (APP)
4 15 Days After
NTP
22 Section 01 35 26 , Para 1.7 Activity Hazard Analysis (AHA) 4 21 Days After
NTP
23 Section 01 35 26 , Para 1.5.1.3
Crane Operators 4 21 Days After
NTP
24 Section 01 35 26 , Para 1.11.1 Accident Reports 4 5 Days After
Accident 25 Section 01 35 26 , Para 1.8
Confined Space Entry Permit 4 Before Confined Space Entry
26 Section 01 35 26 , Para 1.8 Hot work permit 4 Before Starting
Hot Work 27 Section 01 35 26 , Para 1.11.4
Certificate of Compliance 4 21 Days After
NTP
28 Section 01 35 60 , Para 2.1.3 Mill Certificate or Manufacturer Affidavit 4 21 Days After
NTP
29 Section 01 50 00, Para 1.4
Construction site plan 4 21 Days After
NTP
Section 01 50 00 , Para 3.3.1
Traffic control plan 4 30 Days Prior
Section 01 57 16, Para 1.5.4
Pesticide Treatment Plan 4 4 7 Days Prior to
Application
32 Section 01 57 16, Para 1.5.3 Certificate of Competency 4 7 Days Prior to
Application 33 Section 01 57 20.00 10, Para 1.7
Environmental Protection Plan 4 10 Days Prior to Construction
Section 01 74 19, Para 1.6 Waste Management Plan
4 10 Days Prior to Construction
35 Section 01 78 00, Para 1.3.2 As-Built Record of Equipment and
Materials 4 10 Days After
Final Inspection
A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
Section 01 78 00 , Para 1.6.1 Warranty Management Plan
30 Days Prior to
Warranty Conference
Section 01 78 00 , Para 1.6.5 Warranty Tags
During
Equipment Installation
Section 01 78 00, Para 1.7
Operation and Maintenance Manuals 4 30 Days Prior to
Testing
Section 01 78 00, Para 1.3.1
Record Drawings 4 10 Days After
Final Inspection
40 Section 01 78 00, Para 1.9 Interim Form DD1354 4 60 Days Pror to
Pre-Final
Section 01 78 00, Para 1.9 Checklist for Form DD1354
4 60 Days Pror to Pre-Final
42 Section 02 41 00 , Para 1.11 Existing Conditions 4 21 Days After
NTP
Section 02 41 00, Para 1.2.1 Demolition Plan
10 Days Prior to
Start of Construction
Section 02 41 00, Para 1.7
Notification
10 Days Prior to Start of
Construction 45 Section 03 30 00, Para 1.7.2.1
Shop Drawings 4 21 Days After
NTP
46 Section 03 30 00, Para 2.4.6 Materials for curing concrete 4 21 Days After
NTP
47 Section 03 30 00, Para 2.4.9
Joint sealants 4 21 Days After
NTP
48 Section 03 30 00, Para 2.4.8 Joint filler 4 21 Days After
NTP
49 Section 03 30 00, Para 2.4.1
Cement 4 21 Days After
NTP
50 Section 03 30 00, Para 2.4.1.3 Portland Cement 4 21 Days After
NTP
51 Section 03 30 00, Para 2.3.2
Ready-Mix Concrete 4 21 Days After
NTP
A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
52 Section 03 30 00, Para 2.8 Bonding Materials 4 21 Days After
NTP
53 Section 03 30 00, Para 2.3.3
Concrete Curing Materials 4 21 Days After
NTP
54 Section 03 30 00, Para 2.7 Reinforcement 4 21 Days After
NTP
55 Section 03 30 00, Para 1.7.2.1
Reinforcement Materials 4 21 Days After
NTP
56 Section 03 30 00, Para 2.2.1 Waterstops 4 21 Days After
NTP
57 Section 03 30 00, Para 2.4.9.3
Waterstops 4 21 Days After
NTP
58 Section 03 30 00, Para 3.14.2 Waterstops 4 21 Days After
NTP
59 Section 03 30 00, Para 1.5
Welding 4 24 Hours Prior to Welding
60 Section 03 30 00, Para 2.4.9.3 Dumbbell Type 3 21 Days After
NTP
61 Section 03 30 00, Para 2.4.9.3
Polyvinylchloride (PVC) 3 21 Days After
NTP
62 Section 03 30 00, Para 2.3.1 mix design 4 21 Days After
NTP
Section 03 30 00, Para 1.7.4.1 Concrete mix design
4 21 Days After
NTP
Section 03 30 00, Para 1.7.4.2
Fly ash 4 21 Days After
NTP
Section 03 30 00, Para 1.7.4.2
Pozzolan 4 21 Days After
NTP
66 Section 03 30 00, Para 1.7.4.3 Ground granulated blast-furnace slag 4 21 Days After
NTP
67 Section 03 30 00, Para 1.7.4.4
Aggregates 4 21 Days After
NTP
68 Section 03 30 00, Para 3.12.2.3 Compressive strength tests 4 7 & 28 Days
After Test 69 Section 03 30 00, Para 3.12.2.4
Air Content 4 5 Days After TestFA4621-13-R-0003 Attachment 4 Schedule of Material Submittals
A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
70 Section 03 30 00, Para 3.12.2.1 Slump 4 5 Days After
Test 71 Section 03 30 00, Para 2.9.1
Air Entrainment 4 5 Days After Test
72 Section 03 30 00, Para 1.7.2.2 Reinforcing Steel 4 21 Days After
NTP
Section 03 40 00.00 10, Para 1.5.2.2 Quality Control Procedures
4 5 Days After Test
Section 03 40 00.00 10, Para 1.4.1
Standard Precast Units 4 21 Days After
NTP
75 Section 03 40 00.00 10, Para 1.4.2 Custom-Made Precast Units 4 21 Days After
NTP
76 Section 03 40 00.00 10, Para 1.4.1
Standard Precast Units 4 21 Days After
NTP
Section 03 40 00.00 10, Para 2.1.9
Accessories 4 21 Days After
NTP
Section 03 40 00.00 10, Para 1.4.2
Design Calculations 4 21 Days After
NTP
Section 03 40 00.00 10, Para 1.4.4.1
Concrete Mix Proportions 4 21 Days After
NTP
80 Section 03 40 00.00 10, Para 1.5.2.2 Test Reports 4 5 Days after
Test 81 Section 03 40 00.00 10, Para 1.5.2.2
Quality Control Procedures 4 21 Days After
NTP
82 Section 26 08 00, Para 3.1 Acceptance tests and inspections 4 14 days Prior to inspection
Section 26 08 00, Para 1.4.1 Qualifications
4 21 Days After
NTP
84 Section 26 08 00, Para 1.4.3 Acceptance test and inspections procedure 4 45 days Prior to inspection
Section 26 56 20.00 10, Para 1.4.5
As-Built Drawings 4 10 Days After
Final Inspection
A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
86 Section 26 56 20.00 10, Para 2.1 Materials and Equipment 4 21 Days After
NTP
87 Section 26 56 20.00 10, Para 1.4.3
Protection Plan 4 21 Days After
NTP
88 Section 26 56 20.00 10, Para 3.12 Training 4 4 21 Prior to Final
Inspection 89 Section 26 56 20.00 10, Para 3.12
Special Tools 4 4 21 Prior to Final Inspection
90 Section 26 56 20.00 10, Para 3.12 List of Parts 4 4 21 Prior to Final
Inspection 91 Section 26 56 20.00 10, Para 3.11
Field Quality Control 4 5 days after test
92 Section 26 56 20.00 10, Para 1.4.2 Qualifications 4 21 Days After
NTP
93 Section 26 56 20.00 10, Para 2.1
Materials and Equipment 4 21 Days After
NTP
94 Section 26 56 20.00 10, Para 3.12 Operation and Maintenance
Procedures 4 14 days Prior to
Final Inspection
95 Section 31 00 00, Para 3.5 Shoring 4 15 Days Prior to
Construction 96 Section 31 00 00, Para 1.3.2
Dewatering Work Plan 4 21 Days After
NTP
97 Section 31 00 00, Para 3.9 Utilization of Excavated Materials 4 21 Days After
NTP
98 Section 31 00 00, Para 3.4
Opening of any Excavation 4 5 Days Prior
99 Section 31 00 00, Para 3.16 Testing 4 7 days after test
100 Section 31 00 00, Para 3.16 Testing 4 7 days after test
101 Section 32 92 19 , Para 2.5.1 Wood cellulose fiber mulch 4 21 Days After
NTP
102 Section 32 92 19 , Para 2.4
Fertilizer 4 21 Days After
NTP
Section 32 92 19 , Para 2.2.3
Topsoil composition tests 4 7 days after test
A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
Section 32 92 19 , Para 2.1 seed 4 4 21 Days After
NTP
Section 32 92 19 , Para 2.7 Erosion Control Materials
4 21 Days After
NTP
106 Section 33 05 23.19 , Para 2.1 Piping casing 4 21 Days After
NTP
107 Section 33 05 23.19 , Para 2.3
Bentonite 4 21 Days After
NTP
108 Section 33 05 23.19 , Para 1.5.1 Design calculations of pipe casing 4 21 Days After
NTP
109 Section 33 05 23.19 , Para 2.1
Piping casing 4 21 Days After
NTP
110 Section 333 46 16 , Para 2.2 Filter Fabric 4 4 21 Days After
NTP
Section 333 46 16 , Para 2.1 Pipe for Subdrains
4 4 21 Days After
NTP
Section 333 46 16 , Para 2.2
Filter Fabric 4 4 21 Days After
NTP
113 Section 33 70 02.00 10, Para 1.3.1 Detail Drawings 4 21 Days After
NTP
Section 33 70 02.00 10, Para 1.3.2 As-Built Drawings
4 10 Days After Final Inspection
Section 33 70 02.00 10, Para 2.2
Nameplates 4 21 Days After
NTP
Section 33 70 02.00 10, Para 2.1
Material and Equipment 4 21 Days After
NTP
117 Section 33 70 02.00 10, Para 3.8 Field Testing 4 10 Days Prior to
Test 118 Section 33 70 02.00 10, Para 3.8.7
Operating Tests 4 7 days after test
Section 33 70 02.00 10, Para 3.3.1.5
Cable Installation 4 21 Days After
NTP
A
N U
FA
C
TU
R
E R
'S W
A R
R A
N
TY
C A
TA
LO
G D
A
TA
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A
TE
LI
N
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
SCHEDULE OF MATERIAL SUBMITTALS
(To be completed by Project Engineer)
NUMBER OF COPIES REQUIRED
D A
TE
R
E C
E
IV
E D
IN
C
O N
TR
A
C
TI
N G
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
S C
H E
D U
LE
S
, L
IS
TI
N
G S
, R E
P O
R
TS
, P
LA
N S
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
FI
E
LD
R
E P
O R
TS
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
TE
C
H N
IC
A
L D
A
TA
TE
S
T R
E P
O R
TS
PROJECT TITLE:
Repair South Duct Bank
DATE CONTRACTOR
NOTIFIED
PROJECT NUMBER:
PRQE05-0101S
(To be completed by Contract Administrator)
SOLICITATION / CONTRACT NO.
S U
B M
IT
TA
L N
U M
B E
R S
C O
N
TR
A C
TO
R
R E
S U
B M
IT
TA
L
FI
N
A L
A P
P R
O V
A L
REMARKS
R E
TU
R
N S
U S
P E
N S
E D
A
TE
D A
TE
T
O C
IV
IL
E N
G
IN
E E
R
IN
G
Section 33 70 02.00 10, Para 2.1
Material and Equipment 4 21 Days After
NTP
121 Section 33 70 02.00 10, Para 3.9.2 Installation Engineer 4 Delivery of
Equipment
Section 33 70 02.00 10, Para 3.9.1 Operation and Maintenance Manuals
4 10 Days After Final Inspection
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP)
Material Submittals Schedule
File details come from the government source that posted it. Updated .