Attachment_7_K7-VAFB_Specific_Requirements.docx
DOCX document 67 KB Posted
- Attached to
- Replace Feeder K7 - Phase II Federal contract opportunity
- Solicitation number
- FA4610-15-R-0005
About this file
VAFB Specific Requirements
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4610-15-R-0005
Attachment 7
3.0 Vandenberg AFB Specific Requirements
3.1 Power Outages
Scheduled power outages shall be minimized and performed on weekends, if necessary, to avoid interruption to Stakeholder personnel facilities and/or launch operations. A minimum of 21 days advanced notice of planned power outages is required. Power outages shall be minimized in all cases and limited to initial disconnections and final connections.
3.1 Stakeholder Requirements
The Contractor shall coordinate with all stakeholders during design and construction. Roadways on South Base are utilized for transportation of oversized vehicles. Setback distances of proposed circuits may vary depending on Stakeholder requirements, including but not limited to crossings of Coast Road must either be underground or at least 93.6 feet high from the road in order to clear the highest payload. Proposed circuit alignments must be a minimum of 10-feet away from the edge of the road at any height.
3.2 Under-build Requirements
Under-built lines are not desired by Base Personnel. If any changes in alignment are necessary during construction, under-built lines shall be avoided.
3.3 “No Dig” Requirement The Contractor shall estimate and account for, as applicable, in the construction schedule “no dig” periods associated with launch activities. Contractor shall assume 7 calendar days per launch and 1 launch per month, totaling 84 calendar days per year. See ”No dig” example letter shown in this attachment.
3.4 Lompoc Gate Procedures
Construction vehicles are required to enter through the Lompoc Gate only, including access to South Base. See Lompoc Gate procedure requirements shown in this attachment.
3.5 Pole Nomenclature Requirement
Poles shall be physically labeled and annotated on drawings using Vandenberg’s nomenclature system. See example below.
image1.png
File details come from the government source that posted it. Updated .