STATEMENT OF WORK
PAINT SIGN STRIPING
GENERAL DESCRIPTION:
The contractor shall provide all materials, labor, supervision, and equipment to complete painting, signage, and striping for work orders listed below. All work shall conform to specifications outlined in the contract, the line item task listing description, and in accordance with (IAW) the Traffic Engineering for Better Signs and Markings SDDCTEA Pamphlet 55-14, the UFC 3-120-01 Design (Sign standard), UFGS 09 90 00, (Paints and coatings), the Manual of Uniform Traffic Control Devices (MUTCD) and California MUTCD standards. Point of contact for this project will be provided at the time of award.
DESCRIPTION OF WORK: FY20 O&M Paint sign & striping projects
Project No.
W/O # BLDG Description
4585774
Interior paint, 150SF
5304410
Interior paint, 750SF
6046107
Interior paint, 1550SF
3541439
Interior paint,1800SF
3541420
3541408
3867923
Interior paint, 2SF
6497094
Interior paint, 35SF
5430682
8 inch Aircraft lines, 2143LF
4046826
Interior paint, 5400SF
4434501 574 Interior paint,1620SF
3434310
Interior paint,900SF
5656150 381
Interior paint,1600SF
6070584
Restripe, 75 parking spots,1350LF
5863497
Restripe, 33 parking spots,375LF
5916772
Interior paint,16SF
5983407
Interior paint,3624SF
6835746
Interior paint,725SF
5135060
Interior paint,10SF
5361717
Interior paint,12SF
5491384
Interior paint,150SF
22 5255021
Interior paint,15SF
5584514
Interior paint,160SF
5581144
Interior paint,160SF
4620295
Interior paint,175SF
4530961 410
Interior paint,175SF
5490919 181
Interior paint,1SF
5195580 176
5189613 176
5440378 660
Interior paint,20SF
5389858 434
Interior paint,20SF
6352957 1355
Interior paint,21SF
5107519 187
Interior paint,22SF
4510907 7763
Interior paint,250SF
5641204 1308
Interior paint,2SF
5454098 409
Interior paint,2SF
5448854 1314
Interior paint,3SF
5450994 380
Interior paint,3SF
6873290 861
Interior paint,432SF
5228757
176 Interior paint, 42SF
41 3966434 381 Interior paint 8624SF
42 3136313 934 Interior paint 280SF
43 2194053 249 Interior paint, 8SF
44 3136160 249 Interior paint, 8SF
45 5491336 1309 Interior paint, 45SF
46 5434355 241 Interior paint, 60SF
47 5383002 664 Interior paint, 3600SF
48 5202621 170 Interior paint, 140SF
49 5143080 214 Interior paint, 384SF
50 5255364 381 Interior paint, 350SF
51 4381417 205 Interior paint, 45SF
52 5155660 381 Interior paint, 150SF
53 5562189 1 Interior paint, 5700SF
54 6304556
SITE
VISIT
Make/Install 142 bldg number signs.
Consolidated
55 4666426
SITE
VISIT
Make/Install 9 desig.
smoking signs, lodging
56 6229145 1354 Make/Install 1 room sign, bldg 1354
57 5890428 130 &
Make/Install 2 bldg signs. Bldg 130 & 934
58 6207240 2010
Make/Install 1 fuel tank area sign. Bldg 2010
59 5345855 7690
Make/Install 1 bldg sign.
Bldg 7690
60 6020550 80&251
Make/Install 2 D2 signs.
Bldg 80&251
6771546
905 Interior paint, 4300SF
4116218
648 Interior paint, 460SF
5260704
1351 Interior paint, 4SF
5277309
1351 Interior paint, 4SF
5491227
1314 Interior paint, 6SF
5499344
1314 Interior paint, 6SF
4932319
1355 Interior paint, 6SF
5228757
442 Interior paint, 70SF
4340270
39 Interior paint, 720SF
70 3581146
1178 Interior paint, 75SF
5298749
10 Interior paint, 75SF
72 5314660
185 Interior paint, 8SF
4917767
1348 Interior paint, 7218SF
6707656
570 Interior paint, 15133SF
6707669
571 Interior paint, 9109SF
76 5486184 440 Interior paint, 42 SF
77 5484894 440 Interior paint,42 SF
78 5481132 1353 Interior paint, 8SF
79 5255364 993 Interior paint, 72 SF
80 5491336 14 Interior paint, 50 SF
ADDITIONAL REQUIREMENTS:
1. All work areas shall be kept as clean as possible during working hours. Debris will not be allowed to accumulate on work site. All debris will be deposited in an authorized container supplied by the contractor.
2. Working drawings shall provide sufficient detail to provide a clear and complete understanding of the work.
3. Special precautions must be made, as needed, to prevent any potential fire hazard. The fire reporting number is 424-4911 from a base phone or 911 from any commercial phone.
4. The contractor shall challenge any requirements in the scope of work (SOW) which are specifically in violation of the governing code. It is the contractor’s responsibility to comply with the governing code unless the construction representative provides specific documentation to the contrary.
5. The contractor shall ensure installation of all items included in the contract. The contractor shall be accountable for all related costs of items not installed.
6. All work shall be in full compliance with the requirements, spirit, and intent of the base compatibility plan (discussed at the Basic Content Pre-construction meeting and a copy provided by the Contracting Officer) and contract specifications.
7. All exposed and visible surfaces shall be finished and provide an aesthetically pleasing appearance.
8. The contractor shall field verify all drawing measurements and any other supplied information given at the site visit
9. Materials storage and clean up: The contractor’s materials and equipment shall be stored and protected after end of each day. Storage facilities are provided by contractor at an approved Government location. Clean up and removal of all debris, spoil and waste shall be accomplished at the end of each day’s work. Disposal shall be off base upon completion.
10. Working conditions: Contractor shall perform work in such a manner as to cause minimum interference to facility and surrounding areas utilities: Reasonable quantities of water and electricity will be provided to the contractor without charge. Needed temporary connections shall be installed maintained and removed at the contractors expense.
PERIOD OF PERFORMANCE:
All work orders will be completed in sixty days (60) days after receipt NTP.