Questions and Answers for Combined RFP for WS-3514, 910 and 65. 8/31/15 Question and Answer Round 2 Bldg 65
08 Openings Item #1 states to remove existing and #2 states to Install existing windows and vents; 6.0 B2010 states new louvers and B2020 states provide new windows. Which is correct?
PM RESPONSE: #2 “Install existing windows and vents” shall be changed to “Install NEW windows and vents”
Item #3 states to leave existing rolling doors; 6.0 B2030 states to provide new OVHD and Roll up doors. Which is correct?
PM RESPONSE: Item #3 which states “leave existing rolling doors” is correct. B2030 states “Provide new solid door assemblies” which is referring to any personnel doors that may exist and provides a requirement for overhead doors in the event they had not been removed from the scope.
23 HVAC
Item #2 states to install elec. Unit heaters with 109.7 MBH each; 6.0 D30 states to install elec unit heater with 570 MBU each. Which is correct and what is MBU?
PM RESPONSE: Item #2 states which “install elec. unit heaters with 109.7 MBH each” is correct. Remove the D30 HVAC requirement for “570 MBU” and replace with “109.7 MBU”.
26 Electrical Item #1 states to replace existing interior lighting and bath; 6.0 D5020 states not used, yet D50 states electrical design shall comply with criteria in UFC. Which is correct? What is to be designed that needs to comply with UFC other than mech. If no lights are replaced and all other electrical (D items) are to remain or not used?
PM RESPONSE: 26 Electrical: “Replace existing interior lighting in warehouse area and bathroom with energy efficient T8 light fixtures.” is correct.
Bldg 910 01 Gen Conditions Item b. states Storefront to stay and be protected; 6.0 B2020 states storefronts shall match existing implying they are to be replaced. Which is correct?
PM RESPONSE: “Item b. Store front to stay intact, protect from damage for the duration of the project” is correct.
09 Finishes Item a. states to paint bath walls and ceiling; 6.0 C3010 states UNO all interior wall partitions shall be painted. Are they any other walls and ceiling to be painted other than the bath walls and ceilings?
PM RESPONSE: No other walls to be painted unless replaced or damaged during demolition.
13 Special PEMB Item b. states to repair insulation behind metal panels as needed; 6.0 B2010 Vapor Retarder, Air Barrier and Insulation states to provide continuous insulation imply all insulation to be replace. Which is correct?
PM RESPONSE: “Repair insulation behind metal panels as needed where damaged and/or deteriorated…” is correct.
22 Plumbing
6.0 D2010 states to replace elec water cooler but no water cooler is included in 1.0 work description. Is there a water cooler to be replaced?
PM RESPONSE: “Replace electric water cooler” is correct.
26 Electrical Items a. and b. state to replace interior lighting in warehouse, bath, display and office areas with T8 (fluorescent) fixtures. 6.0 D5020 states to provide complete lighting system, including exit & emergency, fluorescent and HID, to include switches and automatic controls and replace all receptacles. Are we to replace just the items in 1.0 or all items in 6.0?
PM RESPONSE: Both statements are correct. Replace all items in 1.0 and 6.0.
27 Communications There is no mention of Communication in 1.0; However in 6.0 D5030 it states to see cable management policy. Is there any intent to provide any Communications not identified in 1.0?
PM RESPONSE: The cable management policy is a generic Base wide policy provided as a reference if needed. No communication work is anticipated unless wires removed or damaged in the renovation process.
Bldg 3514 26 Electrical Item 4 states to rewire Fire Alarms; 6.0 D40 states not used. Is any Fire Alarm work required?
PM RESPONSE: Both are correct. Replace fire alarm wires.
Item 5 states to replace interior lighting with T8 fixtures; 6.0 D5020 states to provide complete lighting system, including exit & emergency. Exit and Emergency are typically LED. Are Exit and Emergency lights to be replaced?
PM RESPONSE: Yes, replace all lights including existing exit and emergency lights.
NEW QUESTIONS RECEIVED 8/31/15
Bldg 65 During the site visit a shed roof side building containing an old unused boiler near the paint booth was observed. Is this structure and/or equipment part of any scope regarding this solicitation and/or the Seed Project?
PM RESPONSE: Only the single roof is to be replaced. No other work required in the shed.
Bldg 910 10 Specialty: Item b. states to provide new ADA compliant toilet grab bar, mirror, TP and paper towel dispenser. During the site visit it was noted that this toilet room is not ADA accessible. Is there any requirement to modify this toilet room so that it is ADA accessible?
PM RESPONSE: Yes, modifications will be needed as the pilaster in corner interferes with the clear space required around the toilet. To be ADA compliant the toilet will need to be moved approx. 16” further away from the outside wall and the sink will need to move approx. 30” in the same direction. A partition will also need to be constructed flush with the corner pilaster to mount the ADA grab bars.
21 Fire Suppression: During the site visit our engineer indicated that he was told that the base utilized a proprietary fire alarm system/manufacturer but that source was not identified. To ensure we provide pricing for the system required please provide name of proprietary system/manufacturer.
PM RESPONSE: Proprietary system is not required. However, compatibility with existing Monaco D-21 System is required. Reference Attached JBC FD Design Guide for more detailed information about the existing system.
Bldg 3514 07 Roofing: 6.0 B3010 states to provide new felt and ice and water shield. We assume per industry standard that the entire roof will receive felt, However, it does not specify the area to be covered with either the felt or the ice and water shield. Per industry standard ice and water shield is typically applied to the roof peak, valleys and the outer edges. There would be a significant price difference if ice and water shield were required for the entire roof surface. Where specifically is the ice and water shield to be used?
PM RESPONSE: DOR shall determine required location of ice and water shield.
08 Openings: 1.0 states to remove rust, prime and paint/caulk (11) steel windows; 6.0 B2020 states to repair existing windows and that glazing shall be clear glass; Per the drawings provided and confirmed at the site visit, these openings are not windows but rather Access Hatches without any glass and some in really rough shape. Is there any requirement for glass to be used in these openings? To what level of repair are we to bring these to especially those that are in really rough shape?
PM RESPONSE: No glass is required unless replacing existing glass. Openings shall keep water from entering building or structure. Components shall be refinished to maximize life cycle of building.