Attachment_38-_Part_2 _Attachment_A _Project-Specific_General_Requirements.pdf
PDF 151 KB Posted
- Attached to
- Repair Warehouses, Bldgs. 65, 910 and 3514
- Solicitation number
- FA4418-15-R-0027
About this file
Attachment 38 Part 2 Attachment A Project-Specific General Requirements Dated 1 June 2015.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 38 Consolidated Projects for WS-3514, 910 & 65 DKGV 14: 2074, 2091 & 2097 Weapons Station JBC 6/1/15
Part 2, Attachment A - Page 1 of 3
Part 2, Attachment A
Project-Specific General Requirements
The following requirements are project specific and may either supplement and/or modify those requirements contained in the body of Part 2, General Requirements, for Small Projects. Paragraph numbers in Part 2 correspond to paragraph numbers used in Part 2, Attachment A.
Paragraph 3 POST AWARD KICKOFF MEETING (PAK)
TBD
Paragraph 4 DESIGN
Submit design drawings or sketches, calculations and manufacturer’s data to demonstrate compliance with contract requirements.
Provide hard & electronic copies of design submittal package to the following reviewers 1 week prior to the review meeting:
Deliverable CE CS
Design Development (35% & 65%)
Half-size Drawings or Sketches 2 1
Full Size Drawings 2 1
Specifications and Manuf. Cut Sheets 2 1
Design/Construction Schedule 2 1
Design Analysis/Calculations 2 1
CD’s / Electronic Copies 2 1
Final Designs (95 &100%)
Half-size Drawings or Sketches 3 1
Full Size Drawings 3 1
Specifications and Manuf. Cut Sheets 3 1
Design/Construction Schedule 3 1
Design Analysis/Calculations 3 1
CD’s / Electronic Copies 3 1
1. The final design submittal must be professionally signed and sealed by the DOR and forwarded to the Contracting Officer prior to the start of construction. Separated final design packages will only be considered for Government review and approval during the Post Award Kick-off Meeting
2. Construction submittals are to be Contractor-approved, except those listed below:
a. DOR Approval required for:
1) Fire Protection related submittals
2) Earthwork and Geotechnical submittals
Part 2, Attachment A - Page 2 of 3
3) All components of the roof and exterior wall.
4) All components of the interior doors, hardware, cabinets, fireproofing/firestopping, railings, paint, finish materials/colors.
5) HVAC Testing, Adjusting, and balancing.
6) Furnishings, fixtures, and equipment packages
b. Government Approval required for:
1) All Finish Material Color Samples
3. Submit the following construction submittals, approved by the DOR, to the Government for surveillance:
a. Submit fire protection related submittals pertaining to spray-applied fire proofing and fire stopping, exterior fire alarm reporting systems, interior fire alarm & detection systems, and fire suppression systems including fire pumps and standpipe systems.
b. Submit roofing submittals pertaining to materials and systems used to make up the roof system.
c. Submit HVAC Testing, Adjusting, and Balancing required submittals.
d. Submit telecommunications shop drawings for coordination with the NMCI Contractor.
e. Submit Performance Verification and Acceptance Testing required by IBC or this RFP.
f. Submit all Interim Special Inspection Reports on a bi-weekly basis until work requiring special inspections is complete. Submit all Structural Observation Reports and the Final Report of IBC Special Inspections.
g. For any pre-engineered buildings, submit shop drawings showing engineering data and complete building drawings, signed and sealed by a registered professional engineer.
Paragraph 5 FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS
No additional requirements
Paragraph 6 QUALITY CONTROL
The Superintendent may not serve also as the Quality Control Manager on this project.
Special inspection, testing, approvals, certifications, observations and quality assurance plans as prescribed in Chapter 17 of the IBC are required.
Paragraph 7 SUBMITTAL PROCESSING
SUBMITTAL/BENCHMARK DURATION BENCHMARK RECEIVED STATUS
1 Quality Control Plan
2 Material Safety Data Sheets
3 Design/Construction Schedule
4 Waste Management Plan
5 Safety and Health Plan
6 Schedule of Prices
8 Record Drawings
9 Operation and Maintenance Information
10 Licenses and Permits
Part 2, Attachment A - Page 3 of 3
11 Badge Requests
12 Statement of Acknowledgement SF 1413
13 Demolition and Work Plan
14 Design Development Docs
15 Final Design Docs
16 Submittal Register
17 Waste Management Opportunity Assessment Form
18 Performance/Payment Bonds
19 Environmental Protection Plan
20 Certificates of Insurance
21 DD Form 1354
Paragraph 15 INVOICES
All invoices submitted through WAWF.
Paragraph 21 ENVIRONMENTAL CONTROLS AND PROTECTION
Attached Division 1 Specifications shall apply:
01 50 10 ENVIRONMENTAL
01 57 50 TEMPORARY ENVIRONMENTAL CONTROLS
Paragraph 22 WASTE MANAGEMENT
Attached Division 1 Specification shall apply: 01 57 20 WASTE MANAGEMENT
Paragraph 23 RECORD DRAWINGS AND OPERATION & MAINTENANCE (O&M) DATA
Attached Division 1 Specifications shall apply:
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
Paragraph 26 WORK HOURS, ACCESS AND PASSES
Attached Division 1 Specification shall apply: 01 14 00 WORK RESTRICTIONS
Paragraph 27 SECURITY REQUIREMENTS
See Part 6 Attachments
Paragraph 34 SAFETY AND OCCUPATIONAL HEALTH
Attached Division 1 Specification shall apply:
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
Sub-Paragraph f., Safety and Health Officer (SSHO) The Site Safety and Health Officer may not serve also as the Superintendent.
Sub-Paragraph h., Hot Work Obtain services from a NFPA Certified Marine Chemist for “HOT WORK” within or around flammable materials (such as fuel systems, welding/cutting on fuel pipes) or confined spaces (such as sewer wet wells, manholes, and vaults) that have the potential for flammable or explosive atmospheres.
**End of PART 2 Attachment A**