FA3047-15-R-0069 Kelly Airfield Pavement Pads Attachment 1 Statement Of Work--Kelly Airfield Pavement Pads

View the file

Other files

File Type Posted
Amendment_0002.pdf PDF
FA3047-15-R-0069.pdf PDF
FA3047-15-R-0069.pdf PDF
Atch_4._Schedule_of_Materials_Submittals__24_Aug_15.xlsx XLSX spreadsheet
Amendment_1.doc DOC document
SF_1442_Solicitation.pdf PDF
RFP_15-R-0069.pdf PDF
Atch_5._Schedule_B__8-4-2015.pdf PDF
Atch_3._Wage_Determination_Heavy__Highway_TX150016_01022015__TX16.pdf PDF
Atch_2._Appendix_A-N_1_June_2015.pdf PDF
Atch_4._Schedule_of_Materials_Submittals__18_Jun_2015.xlsx XLSX spreadsheet
Map__JBSA-Lackland_Visitor_Center.jpg JPG image
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1KELL 90-5421A
27 July 2015

STATEMENT OF WORK

PROJECT TITLE: REPAIR AIRFIELD PAVEMENT PADS Phase 2

PROJECT # KELL 90-5421A;

WORK ORDER # 44797;

LOCATION: Joint Base San Antonio Lackland’s Kelly Runway

1.0 PROJECT SCOPE

1.1 BACKGROUND

JBSA-Lackland’s Kelly Airfield (Figure 1) has only one runway. Major expansion of the airfield was conducted during the early 1940s. In the mid-1950s, Runway 15- 33 was constructed and the airfield was expanded to its present-day configuration. In some cases, World War II-era or earlier pavements were overlaid with additional concrete to achieve final thicknesses and elevations. Since the 1950s, airfield pavements have been removed and replaced, overlaid, or repaired. Substantial repairs to the runway keel sections occurred in the late 1980s. Apparently, airfield construction records were not transferred to Lackland AFB when the real property was transferred in 2001. Runway 15-33 will go through a name change in 2015 of 2016 to Runway 16-34. JBSA-Lackland’s 15/33 runway is an 11,550 foot long runway with 12 taxiways and 4 aprons and 2 arm/disarm pads. It is open 24 hours a day 7 days per week. All Kelly Airfield closures shall be negotiated prior to award of this contract.

Figure 1: Project Location JBSA-Lackland’s Kelly Airfield

1.1.1 Work site existing conditions: JBSA-Lackland’s Kelly Airfield: has a variety of slab sizes. The slabs to be repaired are of varying size, location, age and condition. See Core Map located in Appendix F. The soil is very expansive clay and due to the amount of rain we have been having this year (2015), we have learned that on occasion once the slabs are removed the void fills with water. Also, when it rains the void holds water and does not drain even after days of sitting. Contractor may have to pump rainwater from excavated areas and let the void sit for several days in order for base rock compaction to be achieved.

Alpha Echo Foxtrot Lima 433rd Kilo Juliet Delta Charlie Bravo Alpha TA Ramp Alpha two Alpha one Gate 45

Figure 2: Contract project site.

1.2 GENERAL

1.2.1 The contractor shall identify and comply with all applicable (1) federal, state, local as well as Department of Defense (DoD), Air Force, and JBSA - Lackland statutes, instructions, manuals, handbooks, regulations, guidance, policy letters, and rules (including all changes and amendments), and (2) Presidential Executive Orders, in effect on the date of issuance of this contract.

A. Quantities

Set quantities are 102 full depth slab replacements for the whole airfield. Below are the estimated quantities broken down by location.

1. Phase 1 Non-Runway:

For location, see figure below

a. Building 1610: about two (2) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other. Contractor shall do these slabs first as a demonstration to the government to show the contractor’s means, method and mix align with the specifications.

b. Taxiway Alpha: about six (6) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other. Due to airfield traffic, this will have to be done in three (3) different taxiway closures:

1. Three (3) slab at the intersection of Taxiway Charlie and Taxiway Alpha
2. One (1) slab between Taxiway Alpha one and Delta on Taxiway Alpha

3. Two (2) slabs between Taxiway Alpha Two and past Taxiway Echo on Taxiway Alpha

c. Taxiway Hotel: about Two (2) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other.

d. Taxiway Juliet: about Three (3) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other.

e. Taxiway Kilo: about Five (5) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other.

e. Taxiway Kilo

d. Taxiway Juliet

c. Taxiway Hotel

b. Taxiway Alpha

a. Building 1610 parking

Figure 3: Airfield slabs to be replaced at each location as listed in Paragraph 1.2.2.B.1. The yellow boxes means the slabs are not next to each other

2. Phase 2 Runway:

For location, see figure below

a. about Twenty-nine (29) slabs with more than one full depth crack at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other. Runway access is limited to two months including cure time.

b. After all slabs with more than one full depth crack are counted then the contractor may choose slabs with one full depth crack, to replace at full depth. Do not exceed the total number of slabs to be replace in the whole airfield and do not delay the opening of the runway.

c. Prior to runway long-term closure (5 March 2016) contractor shall mark all slabs to be replace.

Runway

Figure 4: Airfield slabs to be replaced at each location as listed in Paragraph 1.2.2.B.2. The yellow boxes means the slabs are not next to each other

3. Phase 3 Non-Runway:

a. Taxiway Alpha 2: Estimated 36 asphalt capped slabs. Size and condition of slabs is unknown. For bid purposes assume slabs are 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other. Contractor shall remove existing asphalt capped slabs and replace with full depth concrete slabs to match the elevation of surrounding slabs. Do not cap with asphalt. Maintain a crown down the center.

b. Taxiway Alpha 1: about Eight (8) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other. Contractor shall change the depth of the concrete (not the base rock) so the elevation matches surrounding slabs.

c. 433rd hanger tail enclosure: about Three (3) slabs at 19 feet by 19 feet to be replaced at full depth. Slabs are not next to each other.

d. 433rd ramp: about One (1) slab at 19 feet by 19 feet to be replaced at full depth.

e. TA Ramp: about Six (6) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other.

f. Taxiway Foxtrot’s Arm/Disarm pad: about One (1) slab at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet.

b. Taxiway Alpha One

a. Taxiway Alpha Two c & d. 433rd Ramp/Apron

f. Arm/Disarm pad

e. TA Ramp

Figure 5: Airfield slabs to be replaced at each location as listed in Paragraph 1.2.2.B.3. The yellow boxes means the slabs are not next to each other

4. Set Total for whole airfield: 102 slabs

1.3 DESIGN

1.3.1 The Government is the Designer of record.

1.3.2 The Designer of Record (DOR) will use the Unified Facilities Guide Specifications (UFGS), Texas Department of Transportation (TxDOT) Specifications, Federal Aviation Administration (FAA) and the requirements contained in this SOW to fully develop the technical specifications and construction drawings. The technical criteria contained and cited in this SOW and specifications establish minimum standards for the construction quality.

1.3.3 The contractor shall be responsible for preparing, filing, testing, and paying for any fees necessary to obtain all necessary permits or disposal to meet the provisions of this SOW. All testing and/or permitting or disposal fees shall be included as part of the proposal.

1.4 CONSTRUCTION JBSA-Lackland’s Kelly Airfield Pavement Pad replacement KELL 90-5421A 44797

1.4.1 All construction work shall be in strict conformance with design drawings and specifications (SOW Appendix A through SOW Appendix N) and shall include the furnishing of all materials, labor, plant, tools, equipment, and services necessary to accomplish the provisions of this SOW. The work performed by the contractor shall result in complete and fully functioning systems consisting of, but not limited to, the following principal items:

Safely opening the runway, taxiways and other concrete paved surfaces, provide a structurally sound pavement with no cracks, spalls or damage, established grass in all contractor disturbed areas, provide a product constructed per scope of work and attachments, maintain at least a 35-year lifespan, prevent post-pour shrinkage cracks, maximize cure strength and minimize future maintenance and repair costs.

1.4.2 The airfield is a limited access area and all personnel working on the airfield shall be required to have a current base pass and have a legitimate reason for being granted access to that particular part of the airfield. All personnel shall only access areas of the airfield preapproved by the contracting officer who will provide the contractor to a specific driving path. Contractors outside of the preapproved driving path are at risk of being detained by security forces or Port San Antonio security for unauthorized entry. Personnel who have been granted access to the airfield have not been granted access to Restricted Areas or Controlled Movement Areas. Contractor shall assign specific personnel to take the airfield driver’s test. If they pass the airfield driver’s test, they will be given an Airfield Driver’s license (form 483). Personnel with an active 483 may be a driving escort for up to five (5) personnel who have a base pass and have a legitimate reason for being on the airfield. It is the responsibility of the holder of the 483 to keep personnel out of restricted areas and controlled movement areas unless specifically given access to the area every time they enter/leave/move in or near those zones. Restricted area badges are required in order to escort in the restricted areas. Holders of the 483 shall strictly follow AFI 13-213 Airfield Driving found in Appendix L. Photography is not permitted. Crossing red lines is not permitted.

1.4.3 Prior to Construction

A. Contractor shall submit a “Phasing plan” for the Airfield Management, construction schedule and laydown yard site plan within 10 days of award. Contractor shall strictly adhere to specification section 01 32 16.00 20 Small Project construction progress schedules found in Appendix A. Schedule shall include:

1. Phase 1 Non-Runway:

a. Non-runway work shall start no later than 1 December 2015. Phase 1 runs from 1 December 2015 to 4 March 2016 at the end of the work day.

b. Phase 1 can not be extended but Phase 1 work can be moved to phase 3 with no negative affect to the contractor. Weather days accumulated in phase 1 will be added to phase 3.

c. During non-runway airfield work contractor may schedule work Monday through Friday from 7:00 am to 5:00 pm. Contractor may schedule work on Saturdays, Sundays, Holidays and after hours with written approval from the Contracting Officer and with one week’s advance written notice.

d. Schedule shall include start and end dates of work areas (taxiway Alpha, taxiway Bravo, other concrete surfaces …). Taxiways and other concrete surfaces shall be segmented for no more than eight (8) week intervals. Only one (1) taxiway will be provided to the contractor at a time. Only one (1) paved surface will be provided to the contractor at a time.

e. Inspections may be scheduled Monday through Friday between the hours of 9:00 am and 3:00 pm. The contractor’s phasing plan may be adjusted by the contracting officer to accommodate the government’s needs prior to acceptance.

f. Taxiway Alpha work may only be grouped:

1. Intersection of Taxiway Charlie and Taxiway Alpha

2. Between Taxiway Alpha one and Charlie

3. Between Taxiway Alpha Two and past Taxiway Echo

g. Contractor shall use 28-day cure concrete.

2. Phase 2 Runway:

a. Long-term runway closure shall start on 5 March 2016 at 7:00 am and end on 26 April 2015 at 7:00 am with rain days from 16 April 2015 at 7:00 am to 5 May 2016 at 7:00 am. Phase 2 will not be extended due to weather. Sixteen (16) weather days (12 hours shifts) are built into this schedule. Contractor shall start at Taxiway Bravo intersection of the runway and work South.

b. Runway scheduling shall be by task (including but not limited to saw cut, demolish, haul-off, compaction, dowel placement, concrete pour, cylinder break, submittals, testing, meetings…). Schedule runway work in 1000-foot runway increments or by scheduling runway work by limited number of slabs open at one time; such that runway opening is not delayed.

c. Contractor shall start at the North end of the runway and work South.

d. During runway closure contractor may schedule work 24 hours per day seven (7) days per week including holidays. Inspections may only be scheduled Monday through Friday between the hours of 9:00 am and 3:00 pm, unless prior arraignments are made in writing with the Contracting Officer. Contractor shall provide as much notice as possible for unscheduled inspections.

e. Inspections may only be scheduled Monday through Friday between the hours of 9:00 am and 3:00 pm.

f. When concrete is called for in the Scope of Work or Specifications the contractor shall use 28-day cure concrete on the runway.

3. Phase 3 Non-Runway:

a. Phase 3 runs from 6 May 2016 to the end of the contract duration. Phase 1 work can be moved to phase 3 with no negative affect to the contractor. Weather days accumulated in phase 1 will be added to phase 3.

b. During non-runway airfield work contractor may schedule work Monday through Friday from 7:00 am to 5:00 pm. Contractor may schedule work on Saturdays, Sundays, Holidays and after hours with written approval from the Contracting Officer and with one week’s advance written notice.

c. Schedule shall include start and end dates of work areas (taxiway Alpha two, TA ramp, 433rd…). Taxiways and Aprons shall be segmented for no more than eight (8) week intervals. Only one (1) taxiway will be provided to the contractor at a time. Only one (1) paved surface will be provided to the contractor at a time.

d. Inspections may be scheduled Monday through Friday between the hours of 9:00 am and 3:00 pm. The contractor’s phasing plan may be adjusted by the contracting officer to accommodate the government’s needs prior to acceptance.

e. Apron segments shall not be greater than one row at a time on the TA Ramp and one spot at a time on the 433rd Apron. Only one (1) Apron parking row will be provided to the contractor at a time.

f. Contractor shall use 28-day cure concrete.

4. Dates and times of Initial inspections per specification section 01 45 00.00 40 Quality Control located in Appendix A shall be scheduled by “task” also known as ”definable features of work” for all portions of this project. Definable features of work shall include but are not limited to:

Submittals, pre-saw cut, pre- routing of cracks, demolish, compaction, pre-drilling for dowels, tie down placement, welding, static ground placement, concrete pour, testing, saw cut, joint and crack cleaning, joint and crack seal, expansion material placement, soil, sod, inspections, permits, renew of permits, meetings, key dates, restore government property and more

5. The contractor’s phasing plan must be approved by the Airfield Manger prior to being accepted as part of the contract. Government established dates shall not be altered by the contractor. Scheduled may be altered by the Contracting Officer due to Government needs prior to acceptance

B. Contractor shall provide at minimum one airfield licensed driver per every five (5) employees on site and a minimum of two (2) licensed drivers on site at all times. If the contractor does not have one airfield driver per every five (5) employees on site with a minimum of two (2) airfield licensed drivers per site location then the contactor shall three (3) weeks prior to start of work request an Airfield Drivers Class. Contractor shall strictly adhere to Air Force Instruction 13-213 (Appendix L). Classes are held at request only, on Tuesdays, Wednesdays, or Thursdays. They are held once per month from 5:00 a.m. to 3:00 p.m. Class size is limited to between four (4) and six (6) personnel only. If less than four (4) personnel show up to the class then the class may be canceled. Contractors shall bring a contractor owned vehicle with the contractor name and logo on the side to the class for the driving test. Contractor shall provide names, date of birth, Driver’s License number and Driver’s License State of issue, and Driver’s License restrictions of each person taking the class. Drivers with color blindness are not permitted to drive on the Control Movement Area (CMA) portion of the airfield. Color vision proof (i.e. pass or fail) shall be provided by the contractor in written form, and signed by a Doctor. FAA regulations require the control tower to speak English. The driver shall understand and speak English well enough to communicate to the control tower and take a written test; otherwise, they will not be permitted to drive on the CMA. The driver shall have a current state driver’s license.

C. Two (2) or more contractor personnel may be chosen to be contractor escorts. These personnel shall be given a NACI security level background check at the government’s expenses. This background check can take up to six (6) months. Once these individuals with NACI have passed the NACI background check and the airfield driver’s license tests they may be permitted to escort personnel on the airfield. This type of background check is required for work in the red zones located in the aprons and ramps, which shall be scheduled late in the project.

D. All preconstruction submittals shall be submitted and approved prior to start of work. See all submittal in Appendix A.

E. Base passes are required for entry onto the base and airfield. Contractor shall provide the name, Date of Birth, Driver’s License number and Driver’s License State of issue to contracting at least 48 hours prior to start of work to receive base passes. Contractor shall provide a list of delivery truck drivers that will need access to the base, include the name of the company, number of truck, date/time of delivery.

F. Contractor shall, four (4) weeks prior to start of work fill out the request for manifest forms in order to use a dumpster or haul off the airfield any uncontaminated construction debris, contaminated construction debris, recyclable material or soil. The contractor shall dispose of uncontaminated construction debris, contaminated construction debris, recyclable material or soil to a government preapproved disposal site only. Contractor shall be responsible for disposal site fees and testing requirements for any material removed from the airfield. (See Specification section 01 35 35 Environmental Protection in Appendix A)

G. One (1) week prior to start of work contractor shall route a dig permit for signature, see paragraph 10.0.

H. Contractor shall not start construction prior to Construction waiver being signed, phasing plan being approved, preconstruction submittals being approved, manifests being received from environmental and dig permit signed by approving official and approval by Contracting Officer.

I. Contractor shall not start any work in the red zone areas until a written agreement is made with security and approved by Contracting Officer on whether the Apron/Ramp site will be a Free Zone or a Red Line Re-designation. A Free Zone or Red Line Re-designation will be obtained by the Contracting Officer 502 CE Project Manager, and sent to contractor through the Contracting Officer upon request, prior to the start of construction in the Red Zone. When the document is approved and signed by the 502nd ABW Commander, the government will provide the contractor a copy. The contractor must be aware that it can take up to eight (8) weeks to get the document signed and work is not permitted to start until the 502nd ABW Commander signs the waiver. Restricted area badges are required in order to escort in the restricted areas, a 483 does not give the driver permission to enter a restricted area.

J. A construction waiver will be obtained by the 502 CE Project Manager, and sent to contractor upon request, prior to the start of construction. When the document is approved and signed by the 502nd ABW Commander, the government will provide the contractor a copy. The contractor must be aware that it can take up to eight (8) weeks to get the waiver signed and work is not permitted to start on the airfield until the waiver is signed by the 502nd ABW Commander.

K. Contractor shall schedule a meeting with CONS and CE at least once per week for the duration of this project and at least twice per week during runway work.

L. Phasing Plan:

Work adjacent to airfield air operations area (AOA) requires the Contractor to develop a Construction Phasing Plan meeting the requirements of the RFP and Section A15.3 of Attachment 15 in UFC 3-260-01, see appendix C. The Contractor shall submit the phasing plan with the first submittal, and include drawings illustrating phasing details and notes. Contractor shall use word document memo format. Information to include in the phasing plan includes, where applicable:

a. AOA facilities that will be closed or partially closed for construction List the dates and locations of work in detail.

b. Phasing required to maintain minimum aircraft operation with those airfield facilities that will be opened and closed during each identified phase

c. Maximum duration of each phase or closure

d. Time allowance between phases, minimum duration 48 hours.

e. Requirements for temporary marking and lighting, barrier location, covering lights of closed taxiways, and moving arm/disarm pad at Taxiway Foxtrot phase 2

1.4.4 General

A. Work shall only be done if Airfield Operations permits the area to be closed. Contractor shall submit a construction schedule and “phasing plan” for the airfield management showing the dates work is to start and end at each grouping of work for approval. Contractor shall include dates and times of inspections of each new task per specification section 01 45 00.00 40 Quality Control located in Appendix A.

B. Contractor shall not enter red circle marked in Figure below when signs are posted that ordinances are present. If an aircraft is parked on the Hot Cargo Pad 1 or 2 as shown by red aircraft in Figure below then contractor shall assume ordinances are present. Hot Cargo Pad 2 may be close for the duration of this project due to the contractor’s laydown yard is within the 1250 ft radius of Hot Cargo Pad 1 or 2.

Figure 6: Hot Cargo Pad 2 Clear Zone.

Hot Cargo Pad 2: Closed Hot Cargo Pad 1: Open

Hot Cargo Pad 1: Open Hot Cargo Pad 2: Closed

Figure 7: Hot Cargo Pad 1 Clear Zone.

C. The contractor shall always use Gate 45 for entering and exiting the airfield, unless otherwise directed by the contracting officer for a specified purpose and for a specific period of time. Contractor shall always use a predesignated route approve by the contracting officer. See figures below for gate and laydown yard location. Contractor shall check for foreign objects on trucks and equipment prior to leaving the laydown yard, construction site, and prior to entering the paved portion of the airfield.

Gate 45

Figure 8: Gate 45 location and possible laydown yard locations

Gate 45

Figure 9 6: Gate 45 location and possible laydown yard locations

D. Contractor shall provide low profile lite barriers every 50 feet of active construction site perimeter. Contractor shall cover taxiway lights with heavy-duty aluminum foil and construction quality duct tape when taxiway is closed. When taxiway reopens contractor shall remove the aluminum foil and duct tape from the taxiway lights. When working on the Taxiway Foxtrot’s arm/disarm are contractor shall first paint a temporary arm/disarm areas on Taxiway Echo (phase 3)

1.4.5. Laydown yard (See figures 7 & 8 above)

A. Contractor shall provide a laydown yard site plan. The contractor shall construct and maintain temporary 6-foot high chain link fence around the exterior of the laydown-yard site perimeter, trailers and stored materials. The fence shall include woven privacy fabric, 90%-density, bound edging with brass 1”-grommets fastening locations; factory cut wind-holes; color: dark brown, so that visibility through the fence is obstructed. Fence fabric shall be installed on “public” and airfield sides the site’s construction fence and maintained in a neat and tight fashion onto the fence. Fence fabric damaged during the construction portion of this contract, it shall be replaced at the direction of the Contracting Officer. Fence fabric material color shall be dark brown and submitted to the Contracting Officer for approval. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Proper construction signs, keep out signs, and locked gate(s) are required for the duration of the performance period.

B. Equipment, or materials shall not be open to public or airfield view with the exception of those items, which are in support of ongoing work on any given day. All equipment and materials shall be stored in the fenced in area overnight and during non-use periods. The contractor shall not leave any tools, equipment, materials, etc. outside the fenced area during non use periods or overnight.

C. Contractor shall follow preapproved designated driving routes for concrete and contractor vehicles. Contractor shall check for foreign objects on trucks and equipment prior to leaving the laydown yard, construction site, and prior to entering the paved portion of the airfield. Contractor is not permitted to use any gate other than gate 45 unless directed to by the Contracting Officer in writing. See below maps for the designated driving route for accessing the East and West sides of the airfield.

Figure 10: Designated driving route for accessing East side of the airfield.

Figure 11: Designated driving path for accessing the West side of the airfield

1.4.6 Pavement Pad replacement

Contractor shall use “6000 psi compression 650 psi flex” concrete to do full depth replacement. Contractor shall replace shattered slabs and designated slabs. Shattered slabs are defined as slabs with more than one crack. Contractor shall strictly adhere to specification section SECTION 32 13 10 REPAIR OF AIRFIELD PAVEMENT SURFACES RIGID PAVEMENT SYSTEMS and USC 3-270-04 Concrete Repair, see Appendix J. and AC 150-5380-6C repair of airfields, see Appendix K. The number of slabs to be replaced shall be verified by contractor.

A. Location:

The below list is in priority order, not in order of when the contractor will have access to the site.

1. Phase 1 Non-Runway:

For location, see figure below

a. Building 1610: About two (2) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other. Contractor shall do these slabs first as a demonstration to the government to show the contractor’s means, method and mix align with the specifications.

b. Taxiway Alpha: About Five (5) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other. Due to airfield traffic, this will have to be done in three (3) different taxiway closures:

1. One (2) slab at the intersection of Taxiway Charlie and Taxiway Alpha
2. One (1) slab between Taxiway Alpha one and Charlie on Taxiway Alpha

3. Three (3) slabs between Taxiway Alpha Two and past Taxiway Echo on Taxiway Alpha

c. Taxiway Hotel: About Two (2) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other.

d. Taxiway Juliet: About Three (3) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other.

e. Taxiway Kilo: About Five (5) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other.

e. Taxiway Kilo

d. Taxiway Juliet

c. Taxiway Hotel

b. Taxiway Alpha

a. Building 1610 parking

Figure 12: Airfield slabs to be replaced at each location as listed in Paragraph 1.4.6.A.1. The yellow boxes means the slabs are not next to each other

2. Phase 2 Runway:

a. Twenty-nine (29) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other. Runway access is limited to two months including cure time.

b. After all slabs with more than one full depth crack are counted then the contractor may chose slabs with one full depth crack, to replace at full depth. Do not exceed the total number of slabs to be replaced in the whole airfield and do not delay the opening of the runway.

c. Start at the intersection of the runway and Taxiway Bravo and work South.

d. There will be three (3) contractors working on the runway at one time during this closure. This project takes priority. The second project will be starting at the runway intersection of Taxiway Delta and working south to the end of the runway then moving to the runway intersection of Taxiway Bravo. They will be doing concrete work on spalls, cracks and joints. The third contractor will be moving the runway lights from the grass to the asphalt. This contractor will not be working on the concrete. If you have a problem please contact the Contracting Officer.

e. Prior to runway long-term closure (5 March 2016) contractor shall mark all slabs to be replace so the other contractor working on the runway does not patch a slab that is scheduled to be demolished.

Runway

Figure 13: Airfield slabs to be replaced at each location as listed in Paragraph 1.4.6.A.2. The yellow boxes means the slabs are not next to each other

3. Phase 3 Non-Runway:

a. Taxiway Alpha 2: Estimated 36 asphalt capped slabs. Size and condition of slabs is unknown. For bid purposes assume slabs are 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other. Contractor shall remove existing asphalt capped slabs and replace with full depth concrete slabs to match the elevation of surrounding slabs. Do not cap with asphalt. Maintain a crown down the center. See figure below

Figure 14: suspected shattered asphalt capped concrete slabs. Taxiway Alpha 2

b. Taxiway Alpha 1: About Eight (8) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are next to each other. Contractor shall change the depth of the concrete (not the base rock) so the elevation matches surrounding slabs. Slabs are sinking not shattered. See figure below

Figure 15 7: Taxiway Alpha 1 location of sinking slabs number

c. 433rd hanger tail enclosure: About Three (3) slabs at 19 feet by 19 feet to be replaced at full depth. Slabs are not next to each other.

d. 433rd ramp: About One (1) slab at 19 feet by 19 feet to be replaced at full depth.

e. TA Ramp: About Six (6) slabs at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Slabs are not next to each other.

f. Taxiway Foxtrot’s Arm/Disarm pad: About One (1) slab at 25 feet by 25 feet to be replaced at full depth and quartered, reducing the size to 12.5 feet by 12.5 feet. Prior to closing down this area a temporary Arm/Disarm pad shall be painted by the contractor on Taxiway Echo. Contractor shall use yellow airfield paint and beading. Contractor shall not use temporary marking paint or tape. Stripes shall be 6 inches wide. Contractor shall remove temporary Arm/Disarm pad on Taxiway Echo prior to opening Taxiway Foxtrot. Contractor shall not grind markings from Taxiway Echo. Contractor shall not damage concrete surface when removing paint. See figure below

Figure 16: Temporary Arm/Disarm pad to be painted by contractor. Do not paint the numbers, just the yellow lines.

f. Taxiway Alpha One Taxiway Alpha Two Arm/Disarm pad TA Ramp 433rd Ramp/Apron

Figure 17: Airfield slabs to be replaced at each location as listed in Paragraph 1.4.6.A.3. The yellow boxes means the slabs are not next to each other

4. Set Total for the airfield: 102 slabs

B. Dowels shall be placed at one (1) foot increments perpendicular to the direction of traffic. Contractor shall call for inspection seven (7) days prior to drilling each slab to verify dowel location is correct. Contractor shall use UFC 3-270-04 Concrete Repair Chapter 10 for dowel sizing, placement and construction requirements, see appendix J.

C. All pavement pad replacement shall be in compliance with specification SECTION 32 13 10 REPAIR OF AIRFIELD PAVEMENT SURFACES RIGID PAVEMENT SYSTEMS located in Appendix A and AC 150/5380-6C located in Appendix K. Contractor shall use 28-day cure concrete for both runway and non-runway slabs.

D. Contractor shall repaint all lines back to existing conditions or better. Contractor’s painting shall be in compliance with specification section 32 17 23.00 20 Pavement Markings located in Appendix A and ETL 04-2 Standard Airfield Pavement Markings located in Appendix E and AFI 32-1042 Standards for Airfield Markings located in Appendix G. Paint and beading data sheets shall be submitted and approved prior to painting.

E. Base rock shall not be disturbed during demolition and construction. Contractor shall comply with specification SECTION 32 13 10 REPAIR OF AIRFIELD PAVEMENT SURFACES RIGID PAVEMENT SYSTEMS located in Appendix A for preparing base material. Contractor shall not replace base material. Contractor shall protect base material from the elements. Contractor shall schedule work such that the concrete slab’s base material is exposed for the least amount of time.

F. See Core Log Attachment F for concrete thicknesses

G. If slab is greater than 20' X 20', dowel baskets (see figure below) are to be installed both directions and slab shall be saw jointed into quarters after casting. See table below for jointing options

Figure 18: example of dowel baskets and grounded tie down for large aircraft.

H. If slab is 20 feet by 20 feet or less, then slab is to remain in original configuration.

I. Reinforcing steel is only to be used in irregular slabs and only with the approval from Contracting Officer.

J. If a grounding point or tie down is present in a slab that is scheduled to be replaced then the grounding point or ties down shall be replaced with a “Mooring and Grounding Point” if located in an apron. If a grounding point or tie down is present then it shall be replaced with a “Static Grounding Point” if located on any other concrete surface. Contractor shall adhere to UFC 3-260-01 Airfield and heliport planning and design, and the drawing for grounded tie downs located in Appendix C as well as SECTION 34 73 13 MOORING AND GROUNDING POINTS FOR AIRCRAFT located in appendix A and AFM 88-9 Chapter 3 Electrical Design Lightning and Static Electricity Protection located in Appendix M. During Government estimate inspection no grounding points or tie downs were seen in any damaged slabs.

K. Contractor shall re-groove new runway slabs in accordance with specification section 32 01 26.71 GROOVING FOR AIRFIELD PAVEMENTS located in Appendix A

1.4.7 Contactor shall place joints of each replaced slab in compliance with specification SECTION 32 01 11.53 REPAIR OF JOINTS AND CRACKS RIGID AIRFIELD PAVEMENT located in Appendix A and AC 150-5380-6C repair of airfields, see Appendix K. Joint seal and backer rod shall be submitted and approved prior to sealing joints.

A. Contractor shall seal joints along new repairs using Blast and fuel resistant single-component silicon joint sealant that meets the FS SS-S-200E requirements located in Appendix D shall to be used on all parking aprons, warm up areas, arm/disarm areas, and on the runway from the 1000 foot marker to the end of the runway at each end.

B. Contractor shall seal joints along new repairs using asphalt based joint seal that meets the FS-SS-S- 1401C requirements located in Appendix B shall be used in all other runway, taxiways, and roads and non-aircraft parking locations.

C. Remove, clean, reseal the entire length of the concrete joint as directed in specification section SECTION 32 01 11.53 REPAIR OF JOINTS AND CRACKS RIGID AIRFIELD PAVEMENT located in Appendix A.

D. Cleaning is defined as removing 100% of the existing sealant, removing all loose material, dust and moisture. Contractor shall clean per specifications SECTION 32 01 11.53 REPAIR OF JOINTS AND CRACKS RIGID AIRFIELD PAVEMENT located in Appendix A to repair full length of all cracks. Contractor shall install expansion joint fiberboard with a cap along the joint prior to pouring concrete.

E. Contractor shall use below table to determine proper width and depth of new joints. Joints shall be cut straight, square and true, lining up with the center of the dowels and existing and future joints. First cut of the joint shall be ¼ the depth of the slab at ¼ of an inch wide. The second cut shall be as listed in the below table:

Joint Width
3/8"
1/2"
3/4"
1"
Recess Below Surface
1/4"
1/4"
1/4"
1/2"
Thickness of Sealant
1/4"
1/4"
3/8"
1/2"
Backer Rod Diameter
1/2"
5/8"
7/8"
1 1/4"
Total Depth of Joint
1"
1 1/8"
1 1/2"
2 1/4”

1.4.8 Daily and Final Site Clean Up

A. Contractor shall leave no foreign objects (rocks, sand, thick dust, trash…) on the outside of the laydown yard for any length of time. This is not a construction site. This is an active airfield. Treat it as an active airfield. No supplies, tools, materials shall be left on the outside of the laydown yard overnight or during nonworking times. All objects shall be placed in the lay down yard. Dispose of cigarette butts in your pocket only.

B. Contractor shall check for foreign objects (aka FOD check) in their tires, truck beds, floor boards, wheel wells, scraper blades, equipment, sweepers and brooms prior to entering the airfield, prior to leaving the work zone and where FOD check signs are posted.

C. All government property shall be restored back to the original condition or better. Repaint/ repair where contractor damaged or removed anything. This includes but is not limited contractor damage to existing slabs or joints creating a void greater than one (1) inch wide, contractor damage to grass, shoulders, lights, paint, gate, fence, aircraft, government equipment and government property.

D. Contractor shall remove all spoils and construction debris prior to final inspection. Contractor shall sweep and restore laydown yard, and have all contractor property removed from the lay down yard prior to final inspection.

E. Contractor shall use top soil and sod to restore all areas used by the contractor to existing or better condition. Due to the location that the sod is being placed it is imperative that there be no dust. Contractor shall plant sod within 24 hours of vegetation removal. Contractor responsible for watering the grass being restored. Grass shall be restored using Specification section 32 92 23 SODDING located in Appendix A.

F. Debris

1. Contractor shall fill out the request for manifest forms in order to use a dumpster or haul-off of the airfield any uncontaminated construction debris, contaminated construction debris, recyclable material or soil. The contractor shall dispose of uncontaminated construction debris, contaminated construction debris, recyclable material or soil to a government approved disposal site only. Contractor shall be responsible for disposal site fees and testing requirements for any material removed from the airfield. (See Specification section 01 35 35 Environmental Protection in Appendix A)

2. Contractor shall restore site to existing condition or better.

G. Contractor shall continually sweep construction site, driving paths, and laydown yard to ensure no foreign objects (rocks, construction debris, drink bottles..) or dust is blown outside of the working site. The contractor shall clean up debris on a continually basis. The construction site shall be kept clean, orderly, and safe for workers at all times. Do not allow dust to accumulate to the point where tires track the dust onto any active area.

H. Prior to the runway reopening after the long-term closure the contractor shall sweep paved portion of the airfield including but not limited to roads, shoulders, closed taxiways, open taxiways, aprons, ramps, and runway. No FOD checks are required during long-term closure of runway.

I. Contractor shall repaint all lines back to existing conditions or better. Contractor’s painting shall be in compliance with specification section 32 17 23.00 20 PAVEMENT MARKINGS located in Appendix A and ETL 04-2 Standard Airfield Pavement Markings located in Appendix E and AFI 32-1042 Standards for Airfield Markings located in Appendix G. Paint and beading shall be submitted and approved prior to painting.

1.4.9 Acceptance

A. Concrete work shall be free of spalls, cracks, damage, debris, holes. Workmanship shall be of good quality. Work shall be per specifications including but not limited to smoothness. The Crown shall not be altered. Texture shall be medium broom finish. Existing slabs and joints shall be brought back to original condition or better. Saw cuts shall be straight and true.

B. Work areas may be accepted intermittently instead of at the end of the phase.

C. All tasks shall be completed prior to final inspection including but not limited to demobilizing the laydown yard and establishment of grass.

1.4.10 Close-out

A. An interim pre-final inspections of each work site shall be done prior to the contractor being permitted access to the next work site. Contractor shall give seven (7) working days written notice when requesting a pre-final inspection for a work site.

B. Close-out submittals

1. GIS or AutoCAD As- build drawings shall be provided by the contractor Include the location of the slabs being repaired, type of repair, size of repair; location of joints being reshaped, reshaped joint width and depth

2. DD1354

3. Extended Warranty Letter with contact information

4. Release of Claim

1.5 CODES AND REGULATIONS: All work shall be accomplished in accordance with the latest edition of applicable codes, standards, regulations and other requirements. In the case where two or more standards are applicable, the contractor shall ensure compliance with the more stringent of the standards.

2 GENERAL:

Applicable provisions of the Contract Clauses of the contract will govern work under each section of these specifications located in Appendix A.

2.1 JBSA AIRFIELD WORK RESTRICTIONS

2.1.1 Coordination: Work performed under this section shall be coordinated with, and approved by the Contracting Officer. Due to the need to shut the airfield taxiways, or aprons down to complete this work the Base Project Manager will determine the dates and hours that work will occur. It is the contractors responsibility to ensure that the work begins and ends within the agreed to times.

2.1.2 Schedule of Work: Construction schedule on the airfields is determined by the Airfield Manager. Contractor will be given access to the site when airfield operations dictates. Contractor will be given access to no more than one taxiway or one apron parking row at a time. All inspections and restricted area escorts shall be scheduled seven (7) working days in advance. In the event of any emergency, intense operational demands, adverse weather conditions, and other unforeseen difficulties, the contractor may be required to discontinue all work at locations in the aircraft operational area. If lighting occurs within 5 miles of the airfield then all work shall stop, and all people shall take shelter in their vehicles; plan accordingly. The contractor shall notify the Contracting Officer and Project Manager of any changes as soon as the contractor becomes aware of the issue.

2.1.3 Maintenance of Traffic

A. The operation of equipment and the performance of work upon and in the vicinity of airfields shall be coordinated with the Airfield Manager through the Contracting Officer. Neither equipment nor personnel shall use any portion of an airfield without permission of these officers. In all cases, verbal communication shall be maintained with the Airfield Manager before and during work in the vicinity of the airfield. The Airfield Manager shall be advised when work is completed. A minimum of two contractor personnel shall have an airfield driver’s license and remain on site at all times. Contractor shall drive on this contract’s designated driving route only. Airfield Manager through the Contracting Officer may change the designated traffic route depending on the location of the active construction.

B. A construction waiver will be obtained by the Project Manager prior to the start of construction. The contractor does not have to do anything to obtain this waiver but they must be aware that it can take up to 8-12 weeks to get the waiver signed and work is not permitted to start until the waiver is signed by the 502nd ABW Commander and approve by the Contracting Officer. A copy of the waiver is available upon request through the Contracting Officer.

2.1.4 Radio Communication: A radio for this purpose will be made available by the Airfield Operations. Airfield driving course will be provided by the Government.

2.1.5 Safety:

A. Comply with OSHA 29 CFR 1910 and AFI 13-213 and USACE EM 385-1-1. Also, prior to beginning work on the airfield contractor must ensure that designated contractor personnel receive training on airfield safety and flight line driving from the government.

B. The contractor shall provide one airfield driver per every five (5) employees with a minimum of at least two (2) contractor employees with airfield driver’s license per construction location who has taken the Airfield driving course and has a current AF Form 483 Certificate of Competency. Contractor shall strictly adhere to Air Force Instruction 13-213 (Appendix L).

C. For airfield safety requirements contractor must coordinate with the Airfield Manager, 502 OSS/OSAA, JBSA-Lackland phone - 210-925-5880 at least 14 days prior to beginning work on the airfield. For flight line, driving training contractor must contact the project manager at least 30 days prior to beginning work.

D. Use of hard hats is at the discretion of the contractor. However, if a hard hat is used then it must be secured tight to the head under the chin with an authorized manufacturer recommended attachment. Other hats are permitted if secured tight to the head under the chin. Scarves and bandanas are not permitted. Other hats are permitted if they have a manufacturer built in way of securing tight the hat to the head under the chin. Scarves and bandanas are not permitted.

E. The Contractor shall familiarize and comply with the current general safety requirements IAW DOL regulations, OSHA 29 CFR Part 1926, as well as applicable current EM 385-1-1 USACE Safety and Health Manual, AFOSH standards and AFRs. These standards and AFRs are available in the 502 ABW OL-A/SEG, Ground Safety Office, building 2484.

2.1.6 Job site tools and equipment:

All hand tools and equipment shall be maintained in good working conditions, clean and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations. All tools and equipment shall be at hand prior to the contractor commencing work. Do not use any equipment that has been altered or has frayed wiring.

2.1.7 Access: The airfield is a limited access area and all personnel working on the airfield shall be required to have a current base pass and have a legitimate reason for being granted access to that particular part of the airfield. All personnel shall only access areas of the airfield preapproved by the Contracting Officer who will provide the contractor to a specific driving path. Contractors outside of the preapproved driving path are at risk of being detained by security forces or Port San Antonio security for unauthorized entry. Personnel who have been granted access to the airfield have not been granted access to Restricted Areas or Controlled Movement Areas. Contractor shall assign specific personnel to take the airfield driver’s test. If they pass the airfield driver’s test, they will be given an Airfield Driver’s license (form 483). Personnel with an active 483 may be a driving escort for up to five (5) personnel who have a base pass and have a legitimate reason for being on the airfield. It is the responsibility of the holder of the 483 to keep personnel out of restricted areas and controlled movement areas unless specifically given access to the area each and every time they enter/leave/move in or near those zones. Restricted area badges are required in order to escort in the restricted areas. Holders of the 483 shall strictly follow AFI 13-213 Airfield Driving found in Appendix L.

2.1.8 Foreign Object Damage (FOD): Foreign object damage is very dangerous as a result foreign object debris is not allowed on the airfield. Remove rock and pebbles from your shoes and vehicle wheels, and truck beds or floor boards prior to entering the airfield and at all FOD checks. Clean dirt clumps from equipment. No hard hats unless secured, soft hats unless secured, lose clothing, scarf, lose papers, drinking cups, cans or bottle, gum, cigarette butts, chew, trash or anything that can be picked up by the wind of an aircraft engine is allowed outside of a vehicle. Smoke in your car. Sweeping is required. All equipment including but not limited to truck, sweeper, broom truck, back hoe, dump truck shall be cleaned thoroughly including but not limited to blades, wheel wells, tires, truck beds, floor boards, buckets and free of foreign objects that could damage an aircraft such as but not limited to rocks, dirt clumps, metal fibers, sand, plastic fibers, paper cups, trash, plastic bottles. If it is found that Foreign Object related to the construction site caused damage to an aircraft or delayed the airfield usage, then the contractor may be held responsible.

2.1.9 Security:

A. Stay…