Atch_5._Schedule_B__8-4-2015.pdf

PDF 687 KB Posted

Attached to
Repair Airfield Pavement Pads Federal contract opportunity
Solicitation number
FA3047-15-R-0069
Issued by
Department of the Air Force Air Education and Training Command

About this file

FA3047-15-R-0069 Kelly Airfield Pavement Pads Attachment 5 Schedule B

View the file

Other files for this federal contract opportunity

Other files attached to Repair Airfield Pavement Pads, newest first.
File Type Posted
Amendment_0002.pdf PDF
FA3047-15-R-0069.pdf PDF
FA3047-15-R-0069.pdf PDF
Amendment_1.doc DOC document
Atch_4._Schedule_of_Materials_Submittals__24_Aug_15.xlsx XLSX spreadsheet
SF_1442_Solicitation.pdf PDF
Atch_3._Wage_Determination_Heavy__Highway_TX150016_01022015__TX16.pdf PDF
Atch_2._Appendix_A-N_1_June_2015.pdf PDF
RFP_15-R-0069.pdf PDF
Atch_1._SOW_Kelly_Airfield_Pavement_Pads_-_27July2015.docx DOCX document
Atch_4._Schedule_of_Materials_Submittals__18_Jun_2015.xlsx XLSX spreadsheet
Map__JBSA-Lackland_Visitor_Center.jpg JPG image
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUANTITY UNIT TOTAL CREW

LABOR

HOURS

AVERAGE

RATE TOTAL UNIT TOTAL UNIT TOTAL

1 01-21-16-50-0150 Contingencies, add to estimate, final working drawing stage Project

2 01-21-53-50-0500-L Factors, cost adjustments, add to construction costs for particular job requirements, cut and patch to match existing construction, add, minimum

Costs

3 01-21-53-50-0800-L Factors, cost adjustments, add to construction costs for particular job requirements, dust protection, add, minimum

Costs

4 01-21-53-50-2000-L Factors, cost adjustments, add to construction costs for particular job requirements, shift work requirements, add, minimum

Costs

5 01-21-53-50-2400-L Factors, cost adjustments, add to construction costs for particular job requirements, work inside prisons and high security areas, add, minumum

Costs

6 01-31-13-20-0120 Field personnel, field engineer, average Week

7 01-31-13-20-0260 Field personnel, superintendent, average Week

8 01-32-13-50-0400 Scheduling, computer-update, micro, including plots, maximum Ea.

9 01-54-33-10-1700-4 Rent per month for concrete equipment rental, without operators, grinder, concrete and terrazzo, electric, wall grinder

Ea.

10 01-54-33-10-2700-4 Rent per month for concrete equipment rental, without operators, vibrators, concrete, electric, 60 cycle, 2 H.P.

Ea.

11 01-54-33-20-2600-4 Rent per month for earthwork equipment rental, without operators, hammer, vibrating, electric hammer or extractor, 200 KW diesel generator, 150 H.P.

Ea.

12 01-54-33-20-4880-4 Rent per month for earthwork equipment rental, without operators, skid steer loader, wheeled, 10 C.F., 30 H.P. gas

Ea.

13 01-54-33-20-5250-4 Rent per month for earthwork equipment rental, without operators, truck, dump, two axle, 12 ton, 8 C.Y. payload, 220 H.P.

Ea.

14 01-54-33-40-1960-4 Rent per month for general equipment rental, without operators, floodlights, trailer mounted with generator, 2 - 1000 watt lights

Ea.

15 01-54-33-40-6410-4 Rent per month for general equipment rental, without operators, toilet, portable chemical 1 x 10 months

Ea.

16 01-54-33-40-6900-4 Rent per month for general equipment rental, without operators, trailer, water tank, engine driven discharge, 5000 gallons

Ea.

17 01-54-33-50-3450-4 Rent per month for highway equipment rental, without operators, road sweeper, vacuum assisted, 4 C.Y., 220 gallons

Ea.

18 01-54-36-50-1300 Mobilization, up to 25 mile haul distance, 50 miles round trip for mobilization or demobilization crew, equipment hauled on towed trailer, 3-ton capacity

Ea.

19 01-56-23-10-0020 Barricades, 5' high, 3 rail @ 2" x 8", fixed L.F.

20 01-74-13-20-0050 Cleaning up, cleanup of floor area, continuous, per day, during construction M.S.F.

21 01-74-13-20-0100 Cleaning up, cleanup of floor area, final by General Contractor at end of job M.S.F.

22 02-41-19-19-2000 Selective demolition, rubbish handling, the following are to be added to the demolition prices. Load, haul, dump and return, 0' to 50' haul, hand carried

C.Y.

23 03-15-16-30-1100 Expansion joints, rubberized asphalt, hot applied, fuel resistant, 1/2" x 1" 102 slabs cut into quarters = 6 sides x 12.5 feet long

L.F.

24 03-81-13-50-0300 Concrete floor and/or slab cutting, includes blade cost, layout and set-up time, saw cut concrete slabs, plain, up to 3" deep

L.F.

25 07-91-23-10-0092 Backer rods, backer rod, polyethylene, 1" diameter L.F.

General Construction Prime Contractor Bonding

CONTRACTOR

Prepared by:

General Construction Contingency

KELL905421A

WORK LOCATION

LINE

TOTAL

EQUIPMENT COSTS OTHER COSTSLABOR COSTS

Proposed Project AmountThis cost proposal is valid for ______________________________days The period of performance to perform this work is ___________ days.

CONSTRUCTION COST ESTIMATE BREAKDOWN

LINE

NO.

UNIT OF

MEASUREITEM DESCRIPTION

MATERIAL COSTS

PROJECT NUMBER

CONTRACT FOR (Work to be performed)

PURCHASE REQUEST NUMBER

General Construction Subtotal

General Construction Prime Contractor Overhead

ADDRESS

General Construction Prime Contractor Profit

General Construction Labor Burden

ITEMS LISTED ARE NOT ALL INCLUSIVE

Attachment 5

4 Aug 15

KELL905421A Airfield Pavement Pads

QUANTITY UNIT TOTAL CREW

LABOR

HOURS

AVERAGE

RATE TOTAL UNIT TOTAL UNIT TOTAL

General Construction Prime Contractor Bonding

CONTRACTOR

Prepared by:

General Construction Contingency

KELL905421A

WORK LOCATION

LINE

TOTAL

EQUIPMENT COSTS OTHER COSTSLABOR COSTS

Proposed Project AmountThis cost proposal is valid for ______________________________days The period of performance to perform this work is ___________ days.

CONSTRUCTION COST ESTIMATE BREAKDOWN

LINE

NO.

UNIT OF

MEASUREITEM DESCRIPTION

MATERIAL COSTS

PROJECT NUMBER

CONTRACT FOR (Work to be performed)

PURCHASE REQUEST NUMBER

General Construction Subtotal

General Construction Prime Contractor Overhead

ADDRESS

General Construction Prime Contractor Profit

General Construction Labor Burden

26 31-23-23-20-9066 Hauling, excavated or borrow, loose cubic yards, excluding loading equipment, including hauling, waiting, loading and dumping, time per cycle (wait, load, travel, unload or dump and return), 18 C.Y.

L.C.Y.

27 31-23-23-25-0700 Compaction, airports, airport subgrade, compaction, non cohesive soils, 90% proctor, 24" depth

S.Y.

28 32-01-29-70-1370 Full depth patching of rigid pavement, pavement preparation includes sawcut, remove pavement and replace 6 inches of subbase and two layers of reinforcement, excluding trucking and haulaway

Ea.

29 32-17-23-13-1110 Painted pavement markings, airport painted markings, painting, white or yellow, taxiway markings, with 12 lb. beads per 100 S.F.

S.F.

Note: this document does not represent all line items required by the SOW

ITEMS LISTED ARE NOT ALL INCLUSIVE

Attachment 5

4 Aug 15

KELL905421A Airfield Pavement Pads

File details come from the government source that posted it. Updated .