Attachment_14-SOW_Wilderness_Trail.docx

DOCX document 79 KB Posted

Attached to
Repair Wilderness Trail, JBSA Camp Bullis
Solicitation number
FA301618R0051
Issued by

About this file

SOW Wilderness Trail

View the file

Other files

File Type Posted
Attachment_15_Roads_for_Detour_Map.pptx PPTX presentation
Attachment_19_Revised_Culvert_Map.pptx PPTX presentation
Attachment_17_Historic_Culvert_Restoration.docx DOCX document
Attachment_22_Site_Visit_Questions&Answers.docx DOCX document
Attachment_16_Water_Map_Wilderness_Trail-1.pptx PPTX presentation
Attachment_23_Site_Photos.pdf PDF
Attachment_21_Revised_SOW_Wilderness_Trail_12_Jun_18.docx DOCX document
FA301618R0051_0001_Amended_solicitation.docx DOCX document
Attachment_18_Range_Gate_Distance_to_Demo.pptx PPTX presentation
Attachment_20_Wastewater_Map_Wilderness_Trail.pptx PPTX presentation
Range_Gate_Distance_to_Demo.pptx PPTX presentation
11_June_2018Site_Visit_Questions&Answers.docx DOCX document
SITE_VISIT_ATTENDANCE_RECORD.docx DOCX document
Revised_Culvert_Map.pptx PPTX presentation
Wastewater_Map_Wilderness_Trail.pptx PPTX presentation
Historic_Culvert_Restoration.docx DOCX document
Water_Map_Wilderness_Trail-1.pptx PPTX presentation
03K_Attachment_10_-_Appendix_C_JBSA_-_Lackland_Enviromental_Protection_Specification.pdf PDF
03C_Attachment_2_Culvert_Map.pptx PPTX presentation
Attachment_13_Wage_Determination.docx DOCX document
Appendix_G_Radioactive_Material_Request.pdf PDF
Appendix_M_Digging_Clearance.pdf PDF
Attachment_12-COSA_HMAC_Spec_with_TxDOT_Language_Highlighted.pdf PDF
AppendixA_Division_1_General_Requirement_Project_Specs.rtf RTF text file
03E_Attachment_4_Range_Entrance_Gate_Demo.pptx PPTX presentation
03J_Attachment_9_AutoCAD__901_35_1320_00_Special_Project_Procedures_CAD.pdf PDF
Attachment_11-COSA_SPecification_402_High_Density_Corrugated_Pipe.pdf PDF
Appendix_B_Required_Construction_Specs_(COSA).pdf PDF
03H_Attachment_7-Removing_Graffiti_From_Historic_Masonry.pdf PDF
Appendix_J_CAD_and_As-Built_Information.pdf PDF
03G_Attachment_6-Dangers_of_Abrasive_Cleaning_to_Historic_Buildings.pdf PDF
03B_Attachment_1_New_Pavement_Location_Map.pdf PDF
Attachment_15_Submittal_Register.xls XLS spreadsheet
03D_Attachment_3_New_Pavement_at_Water_Supply_Point_Circle.pptx PPTX presentation
03F_Attachment_5-Assessing_Cleaning_and_Water_Repellent_Treatments_for_Hostoric_Masonry_Buildings.pdf PDF
03I_Attachment_8-Repointing_Mortar_Joints_In_Historic_Masonry_Buildings.pdf PDF
FA301618R0051_Repair_Wilderness_Trail.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PROJECT #JBSF110004, RPR-REPAIR WILDERNESS TRAIL

JBSA – CAMP BULLIS

2 April 2018

1) PROJECT SCOPE

(1) The purpose of this project is the replacement of the existing 16 foot wide road and increasing the width of the pavement on Wilderness Trail from 16-feet to 24-feet, beginning at the at the paved circle at the Overhead Water Supply Point on Wilderness Trail, which is approximately 588-ft south east of the intersection of Camp Bullis Rd and Wilderness Trail, and proceeding approximately 6,336 linear feet along Wilderness Trail, ending at the first road approximately 330 feet past KD Range Bravo on Joint Base San Antonio – Camp Bullis, Texas. See SOW Attachment 1.

(2) The pavement on Wilderness Trail is damaged by heavy vehicles, at the end of its life cycle, and shall be replaced. Additionally, the existing pavement width shall be increased to 24-feet.

(3) Most daily traffic can be bypassed around the construction site. However, the Ranges on Wilderness Trail typically have traffic everyday including weekends. When weapons firing is taking place on the Ranges, the Contractor can still continue to work on the road. Contractor shall brief all employees and subcontractors that they are not authorized to go out on the ranges at any time, whether firing is in progress or not.

(4) The scope of pavement work includes demolition of the existing 16-foot wide asphalt road down to the subgrade, lime stabilization of the 24-foot wide subgrade, installation and compaction of the 24-foot wide base course, installation of new 24-foot wide asphalt pavement, restoration/relocation of historical headwalls/culverts, replacement of old culvert pipe with new pipe and mill and overlay.

2) DESIGN

(1) The Design Submittal shall include: Cover Sheet, Overall Site Plan Sheet, Construction Notes, Plan and Profile Sheets, Roadway Striping Plan Sheet, and Details/Pavement Section Sheets.

Contractor shall design the street such that it includes the radius of the adjoining streets and or driveways.

The Contractor shall use City of San Antonio Specifications and the requirements contained in this SOW to fully develop technical specifications if required.

Specifications: The Contractor shall comply with the following applicable City of San Antonio Standard Specifications for Construction found at: https://www.sanantonio.gov/Portals/0/Files/CIMS/StandardSpecifications/CIMSConstructionSpecifications062008.pdf

Item 101Preparing Right of Way
Item 107Embankment
Item 108Lime Treated Subgrade
Item 200Flexible Base
Item 202Prime Coat
Item 203Tack Coat
Item 205Hot Mix Asphaltic Concrete Pavement
Item 208Salvaging, Hauling & Stockpiling Reclaimable Asphalt Pavement
Item 210Rolling
Item 220Blading
Item 230Base and Pavement Replacement
Item 237Pothole Repair
Item 400Excavation, Trenching, and Backfilling
Item 402High Density Corrugated Polyethylene Pipe
Item 516Sodding
Item 530Barricades, Signs, and Traffic Handling
Item 535Hot Applied Thermoplastic Pavement Markings
Item 537Raised Pavement Markers
Item 540Temporary Erosion, Sedimentation and Water Pollution Prevention and Control
Item 554Erosion Control Matting

(1) Contractor shall employ a Registered Professional Land Surveyor (RPLS) to provide all horizontal and vertical data and field conditions required for the Design Engineer to execute a complete design.

(2) Contractor shall field verify all required dimensions and information to produce the design documents. Contractor shall develop accurate electronic plans in AutoCAD 2010/2011drawing format (.dwg) and PDF format. See Attachment 9 Special Project Procedures CAD. As-Builts will not be accepted if not drawn per Attachment 9.

(2) The contractor shall submit for government review and approval electronic copies of 100% and For Construction Design Package signed and sealed by a Texas State Licensed Professional Engineer. The Design Package consists of plans and specifications for the construction work required to rebuild/repair Wilderness Trail. Contractor shall submit a signed and sealed For Construction design package incorporating all corrections for 100% review.

(3) Mobilization and construction effort will only be allowed to begin upon: a) The receipt of signed and sealed For Construction design package. b) All submittals are approved. c) Road/lane closure and the Traffic Control Plan is approved by the 502 Air Base Wing and Camp Bullis Leadership. All electronic copies shall be provided to the government in the native file format and PDF format.

3) CONSTRUCTION

(1) Construction Surveying-Contractor shall provide surveying or survey related activity necessary to provide pavement horizontal location, control grade, thickness, and smoothness of the base and the pavement.

(2) Traffic Control Plan-The Contractor shall prepare and submit a Traffic Control Plan drawn in AutoCAD. The Traffic Control Plan shall provide alternate access to all areas on Camp Bullis impacted by lane and road closures and detours required for construction. The Traffic Control Plan shall clearly show all detour routes, detour signs, barricade locations and type, cone locations, and any temporary roads constructed by Contractor. The Traffic Control plan shall be prepared in accordance with the Texas Manual of Uniform traffic Control Devices (MUTCD).

The Contractor shall prepare the Traffic Control Plan as soon as possible after contract award to provide the Government Project Manager time to prepare and process the electronic Staff Summary Sheet (eSSS) required to get road closures and detours approved by the Camp Bullis Leadership and Air Base Wing Commander before start of construction work. The Contractor will be responsible for setting up and maintaining all traffic control signs and devices during the entire period of construction and removal when no longer needed. Contractor shall modify the Traffic Control Plan during construction as required to improve traffic flow and safety.

(3) Asphalt Pavement-The Overhead Water Supply Point (Attachment 3) asphalt pavement shall be milled and overlaid with 3-inches of new Type D asphalt. See Attachment 3.

(4) Roadway new asphalt pavement shall be 24-feet wide with a 2 foot wide shoulder made from compacted A2 base on each side of road. The pavement shall be 2.0-inches thickness of Type D HMAC over 2.5-inches thickness of Type B HMAC, TxDOT Item 340 and 6.0 inches thickness of TxDOT A2 Base over 6 inches thickness of lime stabilized subgrade. When the lime stabilized subgrade and base course are tested and approved, the 2.5 inch lift of Type B HMAC will be laid and compacted directly onto the base course without prime coat (Camp Bullis Environmental Requirement). When the construction of the first lift of Type B is approved, the Contractor will apply tack coat at the rate of 0.1 gallons per square yard and then construct the final lift of 1-1/2 Type D HMAC.

(5) Storm Water Pollution Prevention Plan. Shall include NPDES Permit and construction of: Silt Fence, Inlet Protection, Concrete Washout Pit, and any other Best Management Practices required by laws and regulations.

(6) Striping Plan- Contractor shall restripe the new pavement with 120 mils thickness reflective thermoplastic paint for the edge lines, centerlines, stop bars, painted islands and arrows.

(7) Testing of asphalt, asphalt temperature, base, and subgrade shall be per specifications. Contractor shall provide testing results to the 502 CES Quality Assurance Project Manager as soon as they are available. Pavement will not be opened to traffic until all testing has been reviewed and approved by 502 CES.

(8) Potholing - Contractor is responsible for patching pavement from potholing if done prior to road closure.

(9) Restoration of Turf is required for all areas disturbed by the Contractor outside of the road and shoulder areas by sodding or hydromulch including construction of a temporary irrigation system or use a water tanker truck to water turf until it is restored.

(10) Pavement Removal- pavement removal by milling is preferred method.

(11) Base Course-The Contractor shall bring in new base material as required to meet proposed grade and 2% grade cross slope and rolling it and moisturizing it until it achieves COSA compaction requirements.

(12) Demolition of Range Gate and Fence – Contractor shall demolish the range gate and fence located near the traffic circle at the overhead water supply point. See SOW Attachment 4.

(13) Contractor Laydown Yard - Contractor laydown yard shall be a restricted area and it will be the Contractor’s responsibility to secure, protect, and maintain this area during construction and restore the laydown area after construction.

(14) Bexar County Flood Plain Permit - The contractor shall be responsible for paying Bexar County Flood Plain Permit Fee of $50.00 after award of the contract.

(15) Testing Fees - The contractor shall be responsible for paying all testing fees incurred during construction.

(16) Repair and Replace Historical Culvert Pipe: The existing 5 pipes between the Historical Culvert headwalls shall be demolished, removed, and properly disposed of. Contractor shall install the new pipes, (one 30-inch inside diameter and four 24-inch inside diameter, all 30-feet long), per COSA Item 402- High Density Corrugated Polyethylene Pipe.

(17) Historical Culverts Headwalls: The Standard for the treatment of the culvert headwalls will be restoration as found at: https://www.nps.gov/tps/how-to-preserve/briefs.htm

(18) There are a number of National Park Service Technical Briefs that would be pertinent to the removal of paint from the rock. These Technical Briefs are listed by number and website below:

(a) Attachment 5 #1. Cleaning and Water-Repellent Treatments for Historic Masonry Buildings

(i) Attachment 6 #6. Dangers of Abrasive Cleaning to Historic Buildings

(ii) Attachment 7 #38. Removing Graffiti from Historic Masonry

(iii) Attachment 8 #2. Repointing Mortar Joints in Historic Masonry Buildings

(b) The Standard for the treatment of the culvert headwalls will be “Restoration”.

(c) https://www.nps.gov/tps/standards/four-treatments/treatment-restoration.htm

(d) Contractor shall read the web page and understand that the culvert headwalls should be built back the way that they were originally. Contractor shall use the same kind of materials (stone and mortar or concrete) and rebuild the headwalls to the same specifications as the original as best as can be determined from the evidence in the field. The Masonry techniques used by the original Constructors of the headwalls is call “random rubble” and the Contractor can use local stone found on Camp Bullis. Contractor shall not make them larger, smaller, taller or lower than what is known unless permission is obtained from the Cultural Resources Management Office: Osmar Alaniz 210-652-5787, Arlan Kalina 817-584-4948, Alan White 210-336-9098.

(e) The location of the Historic Culverts is shown in SOW Attachment 2.

4) HISTORIC CULVERT RESTORATION

(1) Historic Culvert I-7 (Range Side) - restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, replacement of missing stones. Contractor shall install 2 new yellow reflectors attached to one new galvanized steel pole with concrete foundation on each side of each headwall. Reflector poles shall be located about a foot past the edge of the shoulder.

(2) Historic Culvert I-7 (Salado Creek Side) - restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, grading around the culvert pipe to facilitate positive drainage out of the culvert pipe. Additional landscaping is required for 20 feet from the culvert headwall to Salado Creek and the width of the headwall plus 5-feet on each side. This shall include clearing all brush and small trees and insuring the area around the pipe outfall is unobstructed and provides positive drainage.

(3) Historic Culvert I-9 (Range Side)- restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, replacement of missing stones, installation of new stone to raise the top of headwall about 12-inches above the pavement surface, and grading around the culvert pipe to facilitate positive drainage into the culvert pipe. Contractor shall rebuild Historic Culvert I-9 (Range Side) to the same dimensions as Historic Culvert I-10 (Range Side). Historic Culvert I-9 (Range Side) shall be moved about 6-feet from its current location to allow for asphalt pavement to be widened to 24-feet, plus 2 foot shoulder each side. Distance between the I-9 headwalls should be 28-feet.

(4) Historic Culvert I-9 (Salado Creek Side) - restoration involves replacement of missing stones and grading around the culvert pipe to facilitate positive drainage into the culvert pipe. Additional landscaping is required for 20 feet from the culvert headwall to the creek. This shall include clearing all brush and small trees and insuring the area around the pipe outfall is unobstructed and provides positive drainage.

(5) Historic Culvert I-10 (Range Side)- restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, replacement of missing stones, and grading around the culvert pipe to facilitate positive drainage into the culvert pipe. Historic Culvert I-10 (Range Side) shall be moved about 2-feet from its current location to allow for asphalt pavement to be widened to 24-feet, plus 2 foot shoulder each side. Distance between the I-10 headwalls should be 28-feet.

(6) Historic Culvert I-10 (Salado Creek Side) - restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, replacement of missing stones, and grading around the culvert pipe to facilitate positive drainage towards Salado Creek.

(7) Historic Culvert I-11 (Range Side)- restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, replacement of missing stones, and grading around the culvert pipe to facilitate positive drainage into the culvert pipe. Historic Culvert I-11 (Range Side) shall be moved about 3-feet from its current location to allow for asphalt pavement to be widened to 24-feet, plus 2 foot shoulder each side. Distance between the I-11 headwalls should be 28-feet.

(8) Historic Culvert I-11 (Salado Creek Side)- restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, replacement of missing stones, and grading around the culvert pipe to facilitate positive drainage into the culvert pipe. Additionally, the newer TxDOT Type Headwall in back of Historic Culvert I-11 South is to be demolished and removed completely and replaced with pipe.

(9) Historic Culvert I-12 (Range Side) - restoration involves complete rebuilding of headwall and grading around the culvert pipe to facilitate positive drainage into the culvert pipe. Contractor shall rebuild the headwall to the dimensions of Historic Culvert I-8 South. Historic Culvert I-8 (Range Side) shall be moved about 3-feet from its current location to allow for asphalt pavement to be widened to 24-feet, plus 2 foot shoulder each side. Distance between the I-8 headwalls should be 28-feet.

(10) Historic Culvert I-12 (Salado Creek Side)-restoration involves non-abrasive complete removal of all paint and cleaning of the culvert headwall, replacement of missing stones and grading around the culvert pipe to facilitate positive drainage.

(11) Contractor shall protect government equipment and property from damage during construction. Contractor is responsible for properly documenting the condition of the property prior to the start of construction. Contractor shall be responsible for repairing any damages to government property due to contractor’s negligence, at contractor’s own cost.

(12) At the conclusion of the project, all demolished materials will become the property of the contractor and shall be removed off-site and disposed in accordance with all applicable local, state, and federal laws.

5) CODES AND REGULATIONS

(1) All work shall be accomplished in accordance with the latest edition of applicable codes, standards, regulations and other requirements. In the case where two or more standards are applicable, the contractor shall ensure compliance with the more stringent of the standards as determined by the 502 CES PM.

2) SITE PLAN

(1) The contractor shall prepare a site plan indicating the proposed location and dimensions of any area to be isolated/fenced for use by the contractor, avenues of ingress/egress to the project area, and laydown/storage area. Any areas, which may have to be graveled to prevent the tracking of mud, shall also be identified. The contractor shall also indicate if the use of a supplemental or other staging area is desired. Contractor site plan shall be submitted for approval by the government. Contractor shall coordinate and obtain approval from the 502nd CE Project Manager for location of laydown yard.

3) IDENTIFICATION OF EMPLOYEES

(1) The contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the work to display, identification as approved and directed by the Contracting Officer. Prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon release of any employee. All contractor and sub- contractor personnel shall wear identifying markings on hard hats and safety vests clearly identifying the company for whom the employee works.

4) EMPLOYEE PARKING

(1) Contractor employees shall park privately owned vehicles in an area designated by the Contractor to the 502d CE/PM and Contracting Officer. This area will be within reasonable walking distance of the construction site. Contractor employee parking shall not interfere with existing and established parking requirements of the military installation. Contractor shall provide the 502d CE Project Manager the location and map.

5) JOB SITE TOOLS AND EQUIPMENT

(1) All hand tools and equipment shall be maintained in good working conditions and properly stored when not in use. Construction attire shall be IAW applicable OSHA regulations. All tools and equipment shall be at hand prior to the contractor commencing work for the day.

6) AVAILABILITY AND USE OF UTILITY SERVICES

(1) All temporary utilities are the responsibility of the Contractor to provide and fund. The contractor, at its expense and in a manner satisfactory to the Contracting Officer, shall provide and maintain necessary temporary connections and distribution lines.

(2) In order to hook up to the fire hydrant on JBSA the contractor shall provide a meter and a backflow preventer. The backflow prevention device shall be approved prior to installation by JBSA Backflow Program Manager via Project Manager (PM)/ Inspector. In order to test a backflow preventer the contractor must have a licensed backflow prevention assembly tester. A copy of their license shall be provided. The test gauge used by the tester must be tested annually for accuracy and a copy of the last test report must be provided. All backflow prevention devices shall be tested upon installation and annually thereafter until removal. A copy of the Testing and Maintenance (T&M) report shall be provided. Ensure that the meter (where applicable) and the backflow are the only things connected to the fire hydrant. Any other hoses, fittings, pipes etc. cannot be connected until after the device has passed inspection. The PM/ Inspector will witness the test and ensure the Fire Dept. is notified of the hydrant being used. The backflow device cannot be the open/close (isolation) valve for the water flow. The hydrant nut must be operated with an approved spanner wrench (no pipe wrenches) when water is needed. Hydrants are not to remain in the “on” position. At the completion of the project or when the hydrant is no longer needed, the contractor shall coordinate with PM/ Inspector to ensure Fire Dept. is aware that the hydrant is no longer in use.

(3) If the use of another backflow device at another job site or another location on your current job site is required, the process shall be repeated. Every time a new connection is made to the potable system backflow device must be tested.

(4) Hooking up a backflow device to a non-potable source (i.e. sprinkler system) requires the licensed tester to use a dedicated non-potable test gauge and Backflow must be marked “Non Potable Use Only”. Once a backflow device has been used within a non- potable system, it can never be returned to us on a potable water system.

(5) Electricity will not be provided by the government.

7) SANITATION

(1) The contractor shall be responsible to provide and maintain within the construction area minimum field-type sanitary facilities. Government toilet facilities will not be available to contractor’s personnel. Contractor shall bring a sanitary station (Port-O-John) to have on site or at laydown yard. Sanitary station shall be secured such that high winds will not push it over.

8) CONTRACTOR'S TEMPORARY FACILITIES

(1) Storage Area-The government will provide an area for contractor laydown yard. The laydown yard shall be returned to the original condition and grass shall be restored prior to final payment. A submittal for the laydown yard is required. Submittal shall include plan of the laydown yard, number of facilities inside the laydown yard, and haul route. Allow about 14 days for approval. Contractor may not mobilize until laydown yard is approved. The contractor shall construct and maintain temporary 6-foot high chain link fence around the exterior of the trailers and stored materials. The fence shall include woven privacy fabric, bound edging with brass 1”-grommets fastening locations; factory cut wind-holes; color: dark brown, so that visibility through the fence is obstructed. Fence fabric shall be installed on the “public” side of the site’s construction fence and maintained in a neat and tight fashion onto the fence.

(2) Fence fabric damaged during the construction phase shall be replaced at the direction of the Contracting Officer. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Materials, or equipment shall not be placed or stored outside the fenced area unless such materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the military boundaries. Trailers, equipment, or materials shall not be open to public view with the exception of those items which are in support of ongoing work on any given day.

(3) Materials shall not be stockpiled outside the fence in preparation for the next day's work. Mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment, shall be parked within the fenced area at the end of each workday.

9) MAINTENANCE OF STORAGE AREA/LAYDOWN YARD

(1) Fencing shall be kept in a state of good repair and proper alignment. Should the contractor elect to traverse with construction equipment or other vehicles, grassed or unpaved areas, which are not established roadways, such areas, shall be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways; gravel gradation shall be at the contractor's discretion. The contractor shall mow the grass located within the boundaries of the construction site and the contractor shall mow five (5) feet outside the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers shall be edged or trimmed neatly.

(2) Contractor shall remove debris from the fence line daily.

10) SECURITY PROVISIONS

(1) Adequate outside security lighting shall be provided at the contractor's laydown yard, stockpile and during night construction. The contractor shall be responsible for the security of contractor’s own equipment; in addition, the contractor shall notify appropriate law enforcement agency requesting periodic security checks of the temporary project field office.

11) REMOVAL OF TEMPORARY FENCE (LAYDOWN YARD)

(1) The contractor shall remove the temporary fence upon completion and acceptance of the project. In case the fence needs to be removed for the completion of obstructed areas, such as landscaping, the site shall remain in neat appearance with all proper barricades, as specified.

12) BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN

(1) Bulletin Board-Immediately upon beginning of work, the contractor shall displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, and other information approved by the Contracting Officer.

(2) All information shall be located at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer. Legible copies of the aforementioned data shall be displayed until work is completed. Upon completion of work the binder shall be removed by and remain the property of the contractor.

(3) Project and Safety Signs-The contractor shall prominently display any safety signs necessary to prevent any accidents to contractor’s employees, government employees, or any other visitors in the project area. The signs shall be posted within 10 working days after receipt of the notice to proceed (NTP) for construction. The signs posted shall help anyone understand they aren’t allowed in construction area and allowed an alternate route to their location. Upon completion of the project, the signs shall be removed from the site.

13) CLEANUP

(1) At the end of each working day, contractor shall clean up the work site by the removal of all construction debris, waste materials, packaging material and the like. If the aforementioned items could become airborne, they shall be placed in secure refuse containers immediately. Clean up of the work site shall include the construction areas, material storage areas, parking and eating areas, and any other areas affected by the construction process. Any dirt or mud, tracked on to any street, parking area, sidewalk, patio, driveway, or building shall be cleaned away daily. Materials resulting from demolition activities that are salvageable shall be stored within the laydown area described above or at the supplemental storage area. All stored material, whether new or salvaged, shall be neatly stacked when stored and protected from weather damage.

14) RESTORATION OF GOVERNMENT AREA

(1) Areas used by the contractor for the storage of equipment or material, or other use, shall be restored to the original or better condition prior to opening to the public or returning to the government.

15) ENVIRONMENTAL MANAGEMENT

(1) The contractor shall comply with all provisions of JBSA Environmental Protection specification as applicable to this contract. Attachment 10 includes a copy of the JBSA Environmental Protection specification.

16) EXISTING UTILITIES

(1) Any utility line made known to the Contractor and damaged during construction work shall be repaired immediately by the contractor at no cost to the government. It shall be the responsibility of the contractor to protect the utility markings made by the government during the issuance of Digging Permit throughout the duration of the contract period.

17) SUBMITTALS

(1) Newly installed products and/or reference material that are to remain government property at the conclusion of this project.

(2) Contractor shall utilize the Submittal Registry to provide submittals on AF IMT 3000 Material Approval Submittal Form for all listed items, prior to work or installation of materials. Do not purchase or conduct work until the approved submittal form has been returned from 502 CONS. The contractor shall allow up to 14 days for government review of all submittals for approval or disapproval.

18) PRE-CONSTRUCTION MEETING

(1) The contractor shall be required to attend a preconstruction meeting with the Contracting Officer prior to the commencement of any construction work. The preconstruction meeting shall be attended by at minimum the contractor’s Project Manager, Site Superintendent, Quality Control, and Site Safety and Health Officer.

19) QUALITY ASSURANCE

(1) Provide a Quality Control (QC) person at the work site at all times for continuous surveillance of project activities to ensure workmanship, methods, materials, and equipment conform to contract requirements. QC shall have the “stop work” authority to prevent or stop performance inconsistent with the contract requirements.

(2) The contractor shall submit a Quality Control Plan (QCP) for government approval to the Contracting Officer at least 14 calendar days prior to commencing work. Work cannot proceed without an approved QCP. At minimum, the QCP shall discuss the following topics:

(a) Introduction: task order description, and quality commitment statement

(b) References

(c) Project Organization: key project personnel and responsibilities

(d) Quality Control Plan Elements

(e) Submittals

(f) Quality Management Procedures

(g) Testing / Inspection / Monitoring

(h) Closeout Inspection

(i) Documentation and Control

(j) Forms and Records

(k) Nonconformance and Corrective Action

20) GENERAL SAFETY REQUIREMENTS

(1) Provide a Site Safety and Health Officer (SSHO) at the work site at all times to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The Contractor QC can be SSHO on this project. Contractor shall use and comply with EM385-1-1 Safety Manual dated 2014 also known as the Red book (online in PDF).

(2) The contractor shall submit a site specific Accident Prevention Plan (APP) for government approval to the Contracting Officer at least 7 calendar days prior to commencing work. Work cannot proceed without an approved APP. All changes to the approved APP shall be made with the knowledge and concurrence of the Contracting Officer and 502 CES PM. At minimum, the APP shall follow the EM385-1-1abbreviated safety plan.

(3) Obey the posted base speed limits. Wear Seat belts on base IAW AFI 91-207.

(4) Report contractor accidents involving injury to Air Force personnel or damage to government property to the Contracting Officer, 502 CES PM, 502 CES Inspector and the 502 ABW OL- A/SEG, Ground Safety Officer immediately.

(5) The Contractor shall familiarize and comply with the general safety requirements IAW DOL regulations, OSHA 29 CFR Part 1926, as well as applicable AFOSH standards and AFRs. These standards and AFRs are available in the 502 ABW OL-A/SEG, Ground Safety Office, Building 2484.

(6) REQUIRED

STANDARD
SECTION
SUBJECT
OSHA 1910
.132
Personal Protective Equipment
OSHA 1910
.215
Explosives

AFM 91-201

Explosives Safety Standard

OSHA 1926
Subpart H
Material Handling
OSHA 1926
Subpart O
Mechanized Equipment
OSHA 1926
Subpart Q
Concrete Forms
OSHA 1926
.850
Demolition

AFOSH 161-4

Asbestos and PPE

910
.1001
1926
.58

AFOSH 91-4

Ladders

AFOSH 91-5

Welding, Cutting, Brazing

AFOSH 91-25

Confined Spaces

NEC

Electrical Work

1926
Subpart P
Trenching
1926
.202, .203
Barricades

AFOSH 91-25

Confined Space Entry

1925
.461
Scaffolding

21) BARRICADES AND WARNING SIGNS

(1) Adequate barricades, warning signs and flares shall be furnished, installed, and maintained by the contractor. Barricades and signs shall meet the requirements established and in the National Manual on Uniform Traffic Control Devices for Streets and Highways, pertaining to safety and barricades. Barricades shall have warning lights with low-intensity electric flashers for night application.

22) DIGGING PERMIT (WORK CLEARANCE REQUEST)

(1) To initiate a clearance/outage, the requestor must complete sections 1, 2, 6, 7 & 8 of the AF Form 103. The requestor must attend the digging clearance/outage request meeting held every Monday at 0900 Hours in the Civil Engineer (CE) conference room in Bldg. 4197 JBSA Ft Sam Houston, AF Form 103 and drawing or Map printed from the internet.

(2) During the Clearance/Outage request meeting all digging clearance and outage request, will be scheduled and or signed off by each CE shop for their respective area of responsibility. If the area needs to have utilities located the CE shops will schedule and perform the utility locates during that week.

(3) The requestor is also required to contact Dig Tess for all commercial utility locates. The phone number for Texas One Call is located on the digging clearance form

(4) The requestor will be required to attend the digging clearance meeting the following Monday to have the clearance signed off by any shop that required the area to be marked. Safety, Security Forces, Fire Dept. and the Natural Resources Management Section will not attend this meeting. The requestor will be required to make contact as necessary.

(5) Utility Outage Requests are require to be approved at least 2 weeks prior to the scheduled outage. The Requestor must notify the 502 CES Operations Flight Chief, Mr. Antony Person of the outage request once approved.

(6) Upon completion of digging clearances or outage request the requester is required to return the completed signed clearance along with all related documents and e-mails received by the Texas One Call & commercial utilities to the 502 CES approving authority for Approval and Signature.

(7) The 502 CES Approving Authority: Mr. Paul Parker or Mr. John Patrick. Building 4197 FSH.

(8) Paul Parker, 502 CES Electrical Superintendent, JBSA-Ft Sam Houston: Office: 210-221-8322 Cell: 210-389-3845 Paul.e.parker10.civ@mail.mil

(9) John Patrick, 502 CES Structures Superintendent, JBSA-Ft Sam Houston: Office: 210-221-5374 Cell: 210-872-6819 John.c.patrick8.civ@mail.mil

23) UTILITY OUTAGES

(1) Utility outages is defined as a stoppage in electric, gas, potable water, sewer, chilled or hot water, steam, telephone, Energy Monitoring and Control System (EMCS), or any other similar utility whether serving all or a part of a single facility or of several facilities.

(2) All utility outages shall be coordinated with the Using Agency through the Contracting Officer or the 502 CES PM. Notice of the necessity for an outage shall be provided by the contractor to the Contracting Officer, in writing, not less than 14 calendar days prior to the time of the required outage and written approval for the outage will be issued by the Contracting Officer. All work shall be coordinated and arranged to ensure that the outage will be of minimum duration.

(3) Once a utility outage is arranged and work begun, work shall continue until all utilities are restored to the affected facility or facilities.

(4) In the event a scheduled utility outage is cancelled by the government, notification will be given to the contractor at least 24 hours in advance of the time for the outage to start. Rescheduling of a cancelled outage must be coordinated with written notification as described above.

24) WELDING

(1) Welding shall not be performed without first obtaining a hot work permit issued by the Base Fire Department, Bldg. 4196 Fort Sam Houston. The contractor shall wait four to eight hours before leaving the project site or location of where the welding was taken place.

25) RADIOACTIVE EQUIPMENT

(1) Use of radioisotopes or radiation producing equipment (density gauging, Non-Destructive Evaluation (NDE) weld testing, etc.) requires a Nuclear Regulatory Commission (NRC) Radioactive Material License, with all documentation submitted and approved prior to bringing the material on base. To obtain authorization, coordinate the request through 502 CES PM.

(2) The Contractor shall also comply with all requirements of AFI 40-201.

(3) Contractor shall forward application to the Contracting Officer 30 calendar days prior to commencing operations using radioactive materials.

(4) Contractors possessing Agreement State Licenses must also submit an NRC Form 241 to NRC in compliance with 10 CFR 150.20. Request shall include the following:

(5) Description of proposed activities on NRC Form 241.

(6) Procedures established to ensure radiological health and safety of all personnel.

(7) Name of responsible contractor representative.

(8) Current copy of application for NRC or Agreement State License. The license must specifically state the installation by name or approval for temporary job sites anywhere in the United States where the NRC or Agreement State maintains jurisdiction.

(9) The part of the Air Force contract describing work to be done at the base and the inclusive dates of such work.

(10) An acknowledgement that the base representative can make periodic checks to ensure the contractor is following applicable radiological health and safety practices.

(11) Contractors requiring more than 180 calendar days per calendar year of operation must possess an NRC license.

26) FIRE REGULATIONS AND PREVENTION PRACTICES

(1) The contractor shall comply with fire prevention practices as set forth by the National Fire Protection Association, other recognized fire prevention agencies, and base regulations.

27) EXPLOSIVE OPERATED HANDTOOLS

(1) The contractor shall comply with OSHA Standard 1910.215(c) when utilizing explosive operated hand tools. Storage of explosive cartridges on the installation shall be in metal containers and limited to one days' supply. The contractor shall provide adequate controls to prevent loss/theft of cartridges used and stored on the installation.

28) PREVENTION OF FUEL SPILLS

(1) Contractor may use temporary fuel tanks upon approval by the Contracting Officer. Tanks shall be surrounded by an earthen berm which provides 110% of the tank capacity. The berm shall be lined with a 40 mil polyethylene sheet held in place with weights located on the outside of the berm. All berms shall be inspected by the 502 CES PM or the PI prior to filling fuel tanks.

29) GENERATED REFUSE

(1) The contractor shall take positive action to prevent work-generated refuse from entering the sewer system. All contractor generated refuse and waste shall be hauled from the construction site daily to a disposal area located outside the physical boundaries of the installation or on-base when indicated. This refuse and waste material shall be hauled in trucks with tight-fitting beds and covers to prevent spillage on roadways. The construction site shall be kept neat, orderly, and safe for workmen at all times. All required manifests shall be obtained prior to the transportation of refuse off-site.

30) WATER CONSERVATION

(1) Conserve water to the greatest extent possible.

(2) If JBSA- implements water usage restrictions, the contractor is required to comply with these restrictions, at no additional cost to the government. In the event the contractor cannot comply with water usage restrictions and still meets other contract requirements (particularly when installing sod or hydro-mulching), then he can request permission from the Contracting Officer for relief from the restrictions.

(3) Waivers: Submit request for waivers to water conservation restrictions in writing. The Contracting Officer will consider such cases on an individual basis and grant waivers only in extreme cases. Submit detailed requests with appropriate manufacturer’s/supplier’s data to show unavoidable noncompliance with the water usage restrictions. In the event a restriction is conditionally waived, use only the minimum amount of water necessary to comply with contract requirements.

31) INSPECTION AND ACCEPTANCE

(1) Inspections and final acceptance will be made as completed by the contractor with the following additional provisions:

(2) The contractor shall give the government a minimum of three (3) working days’ notice for all requested inspections. Inspections shall be staggered such that two inspections will not occur at the same time, unless it is required.

(3) The contractor shall make sure that the work is ready for all inspections. The presence of an unreasonable number of deficiencies, as determined by the 502 CES PM, may cause the inspection to be rescheduled.

32) DD FORM 1354

(1) The contractor shall prepare and submit DD Form 1354, Transfer and Acceptance of Military Real Property prior to acceptance of the project by the government. The completed DD Form 1354 shall be turned over to the 502 CES PM at least 14 calendar days prior to pre-final inspection. A final copy of the DD Form 1354 shall be submitted within 7-calendar days of final acceptance of the project.

33) OCCUPATIONAL SAFETY

(1) The contractor shall be subject to no-notice inspections under Occupational Safety and Health Act (OSHA) Program by inspectors of the Department of Labor.

34) SEVERE WEATHER

(1) Upon receipt by the Contracting Officer of a severe weather warning with anticipated winds of 35 knots or higher, the following sequence of actions shall be carried out:

(2) Contractor is responsible for watching for severe weather warnings.

(3) Contractor shall secure all materials and equipment.

(4) The contractor shall take immediate action to tie down, remove, protect, and/or secure construction materials and equipment to the satisfaction of the 502 CES PI in order to reasonably assure that government property will not be damaged. If the contractor fails or refuses to secure materials and equipment to the satisfaction of the 502 CES PI, the work will be accomplished by government personnel and the cost thereof charged to the contractor.

(5) Contractor shall secure their sanitary station (Port-O-John) or it will be blown over by high winds.

35) APPENDICES

(1) Appendix A: Division 1- GENERAL REQUIREMENTS PROJECT SPECIFICATIONS

(2) Appendix B: Required Construction Specifications City of San Antonio (COSA)

(3) Appendix G: Radioactive Material Request

(4) Appendix J: CAD and As-Built Information

(5) Appendix M: Digging Clearance

36) ATTACHMENTS

(1) Attachment 1: New pavement location map

(2) Attachment 2: Culvert map

(3) Attachment 3: New pavement at Water Supply Point map

(4) Attachment 4: Range entrance gate demolition

(5) Attachment 5: Assessing cleaning and water-repellant treatments for historic masonry buildings

(6) Attachment 6: Dangers of abrasive cleaning to historic buildings

(7) Attachment 7: Removing grafitti from historic masonry

(8) Attachment 8: Repointing mortar joints in historic masonry buildings

(9) Attachment 9: Special project procedures-CAD

(10) Attachment 10: Appendix C JBSA Lackland Environmental protection specification

(11) Attachment 11: COSA Specification 402 High Density Corrugated Pipe
(12) Attachment 12: COSA HMAC Specifications with TxDOT Language Highlighted
(13) Attachment 13: Wage Determination

END OF STATEMENT OF WORK

JBSF110004 14