Atch_1_SOW_(Feb_2019).pdf
PDF 66 KB Posted
- Attached to
- Consolidated Back-Up Power Building 533 Federal contract opportunity
- Solicitation number
- FA252119BA009
About this file
Attachment 1 - Statement of Work (February 2019)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OF1419_(19BA009).pdf | ||
| Answers_w__Attachments_(19BA009__BU_Power_Req).pdf | ||
| Solicitation_Amendment_FA252119BA0090001_SF_30.pdf | ||
| Section_L_(Amd0001).pdf | ||
| Atch_2_BU_Power_Systems_(B533).pdf | ||
| Atch_6_Badge_Request_(45_SFS).pdf | ||
| Atch_9_Q_&_A_Template.doc | DOC document | |
| Atch_7_GPP_Certification_Form.pdf | ||
| Atch_3_BPS_Comm_Ctr_B533_drawings.pdf | ||
| Atch_4_CECC_Form_3052.xls | XLS spreadsheet | |
| Atch_5_WRR_(FL190001)_1Mar2019.pdf | ||
| Solicitation_-_FA252119BA009.pdf | ||
| Atch_8_Hazardous_Waste_Form.doc | DOC document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
February 2019
The work to be performed under this project consists of providing the labor, equipment and materials to remove critical loads from an existing 350 kW generator and connect them to an existing 600 kW generator.
PROJECT DESCRIPTION:
1) Install new breaker in existing switchboard DP-1.
2) Disconnect critical loads from existing 350 kW generator.
3) Install new conduit and wire to connect existing critical loads to existing switchboard DP-1.
4) Disconnect and remove existing 350 kW generator and associated automatic transfer switch and turn over to the Government.
5) Remove existing diesel fuel tank and turn over the government.
6) During outages provide portable generators as indicated on the drawings.
7) Location and connection of portable generators shall be coordinated with 45 CES and the 45th Comm Squadron.