Sheet1
| AFSOAWC AIRCREW INSTRUCTION SUPPORT |
| FA0021-16-R-0002 |
| Questions and Answers RFP |
| GOV'T REF | NO. | REFERENCE | PG. NO. | PARA. NO | ISSUE / COMMENT | QUESTION | GOVERNMENT RESPONSE |
| Deltek | 1 | RFI | NA | NA | Is this RFI for the anticipated ATARS effort (for Hurlburt Field, Duke Field, Cannon AFB, Harrisburg ANGB, and other CONUS/OCONUS locations) which was split from the KDAM ATARS (Solicitation: FA862115R6328; now on Source Selection status) acquisition? Both tasks are currently being fulfilled via a contract with Lockheed Martin (FA822307D0001). | If FA0021-16-R-0002 is a separate effort, would you be willing to share the incumbent contract number and vendor name? | This effort was initially on ATARS II, but is going small business effective this contract. It is separate from KDAM and ATARS II. Your assessment that Lockheed Martin is conducting these services is correct |
| 2 | RFI | NA | NA | Sources Sought announcement states "Interested parties shall respond by 10/09/2015." | What information should we provide with our response to the sources sought announcement? | Contractors interested in the requirement should respond in the form of a Capability Statement to the POCs listed on the sources sought announcement. See revised Sources Sought announcement for more information. | |
| 3 | RFI | NA | NA | Collective Bargaining Agreement (CBA) | How can we obtain a copy of the CBAs? | CBAs will be provided as attachment to the RFP. | |
| 4 | RFI | NA | NA | DRAFT RFP indicates an issue date of 10/7/2015 with a proposal due date of 11/9/2015 | Are the dates correct? | Negative. The anticipated date for release of the RFP is 16 Oct with a suspense for proposals on 16 Nov. |