Govt._Project_Time_Estimate_Sheet.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Construct Addition to Corrosion Control Facility Bldg 180 Federal contract opportunity
- Solicitation number
- F3QCCL6062A003
About this file
Government Project Time
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_1_of_2.pdf | ||
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_2_of_2.pdf | ||
| FA8501-16-R-0013-0003.pdf | ||
| Amendment_2_130401.pdf | ||
| RFI_Questions_and_Answers_Bldg_180_.docx | DOCX document | |
| Amendment_for_Bldg_180.pdf | ||
| RFI_Questions_and_Answers_for_Bldg_180__3.docx | DOCX document | |
| RFI_Questions_and_Answers_Bldg_180__2.docx | DOCX document | |
| UHHZ130401_Contractors_Site_Visit_Attendees.pdf | ||
| RFI's_and_Answers_for_Bldg_180.docx | DOCX document | |
| Master_Utility_Outage.pdf | ||
| Specifications_Vol._1_of_2.pdf | ||
| Specifications_Vol._2_of_2.pdf | ||
| Form_2519_-_Welding_ _Safety_Checklist.doc | DOC document | |
| Special_Warranty_Requirements.doc | DOC document | |
| FA8501-16-R-0013.pdf | ||
| Half_Size_Drawings.pdf | ||
| App_C_UHHZ_130401.pdf | ||
| 11-Mar-2016_Wage_Determination.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design-Build
GOVERNMENT PROJECT TIME ESTIMATE SHEET
| GENERAL NOTES | |
| 1.0 | Ktr = Contractor |
| 2.0 | TBD = Days and dates to be determined by the Ktr to meet the contracted total number of days. |
| 3.0 | The days shown below indicate the Government's best estimate at the number of days required for this project. The start work and total time are fixed in the contract. Dates shown as a number in the Ktr Minimum days column are minimums that the Ktr must allow for each of those steps. The TBD listings are for the Ktr to determine the number of days that the Ktr desires to use in each of those steps, with the Government estimate shown beside them - for reference only. |
| 4.0 | Note that disapproval of material submittals shall not be cause for contract time extensions: the full responsibility and cost for resubmittals and associated delays are on the Ktr. (See Spec 01300.) |
| TIME NOTES: | ||
| 1.0 | Start work time is Line F cumulative. This is the latest number of days by which the contractor must be actively working at the site. >>> | 110 |
| 2.0 | Total time of site work is thus Line K minus Line F. >>> | 365 |
| 3.0 | Total contract time for base bid at Line K. >>> | 475 |
| 4.0 |
| POST-AWARD TIME PERIODS | Ktr Minimum Days | Gov Days Estimate | Gov Accum Total |
| =============================== | ======== | ======== | ======== |
A Contract Award Date 0 0 0
B Kickoff/Preperformance Meeting and (usually) Notice to Proceed (NTP) TBD 30 30
C Material submittal and approval process 60 60 90
D Base authorization to purchase materials and start site work (provided material submittals are approved) 3 3 93
E Put materials, etc, on order. TBD 10 103
F Commence site work after receipt of enough materials to make consistent progress, and to mobilize to base work area. TBD 7 110
G Estimate for main body of work with full crew. TBD 300 410
H Delays for weather, etc. TBD 7 417
I Delays caused by Government inspection or other causes. 7 7 424
J Prefinal and Final Inspections (from day Inspector accepts request to day of Final Inspection). 21 21 445
K Complete punchlist items, final cleanup, and demobilization. TBD 30 475
NOTES FOR "MAIN BODY OF WORK" ABOVE:
&"Arial,Bold"UHHZ 130401 Additions/Alterations to Aircraft Corrosion Control Facility, Building #180