Govt._Project_Time_Estimate_Sheet.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Construct Addition to Corrosion Control Facility Bldg 180 Federal contract opportunity
Solicitation number
F3QCCL6062A003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Government Project Time

View the file

Other files for this federal contract opportunity

Other files attached to Construct Addition to Corrosion Control Facility Bldg 180, newest first.
File Type Posted
Revised_17_Jun_2016_-_Specifications_130401_-_Volume_1_of_2.pdf PDF
Revised_17_Jun_2016_-_Specifications_130401_-_Volume_2_of_2.pdf PDF
FA8501-16-R-0013-0003.pdf PDF
Amendment_2_130401.pdf PDF
RFI_Questions_and_Answers_Bldg_180_.docx DOCX document
Amendment_for_Bldg_180.pdf PDF
RFI_Questions_and_Answers_for_Bldg_180__3.docx DOCX document
RFI_Questions_and_Answers_Bldg_180__2.docx DOCX document
UHHZ130401_Contractors_Site_Visit_Attendees.pdf PDF
RFI's_and_Answers_for_Bldg_180.docx DOCX document
Master_Utility_Outage.pdf PDF
Specifications_Vol._1_of_2.pdf PDF
Specifications_Vol._2_of_2.pdf PDF
Form_2519_-_Welding_ _Safety_Checklist.doc DOC document
Special_Warranty_Requirements.doc DOC document
FA8501-16-R-0013.pdf PDF
Half_Size_Drawings.pdf PDF
App_C_UHHZ_130401.pdf PDF
11-Mar-2016_Wage_Determination.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design-Build

GOVERNMENT PROJECT TIME ESTIMATE SHEET

GENERAL NOTES
1.0Ktr = Contractor
2.0TBD = Days and dates to be determined by the Ktr to meet the contracted total number of days.
3.0The days shown below indicate the Government's best estimate at the number of days required for this project. The start work and total time are fixed in the contract. Dates shown as a number in the Ktr Minimum days column are minimums that the Ktr must allow for each of those steps. The TBD listings are for the Ktr to determine the number of days that the Ktr desires to use in each of those steps, with the Government estimate shown beside them - for reference only.
4.0Note that disapproval of material submittals shall not be cause for contract time extensions: the full responsibility and cost for resubmittals and associated delays are on the Ktr. (See Spec 01300.)
TIME NOTES:
1.0Start work time is Line F cumulative. This is the latest number of days by which the contractor must be actively working at the site. >>>110
2.0Total time of site work is thus Line K minus Line F. >>>365
3.0Total contract time for base bid at Line K. >>>475
4.0
POST-AWARD TIME PERIODSKtr Minimum DaysGov Days EstimateGov Accum Total
=======================================================

A Contract Award Date 0 0 0

B Kickoff/Preperformance Meeting and (usually) Notice to Proceed (NTP) TBD 30 30

C Material submittal and approval process 60 60 90

D Base authorization to purchase materials and start site work (provided material submittals are approved) 3 3 93

E Put materials, etc, on order. TBD 10 103

F Commence site work after receipt of enough materials to make consistent progress, and to mobilize to base work area. TBD 7 110

G Estimate for main body of work with full crew. TBD 300 410

H Delays for weather, etc. TBD 7 417

I Delays caused by Government inspection or other causes. 7 7 424

J Prefinal and Final Inspections (from day Inspector accepts request to day of Final Inspection). 21 21 445

K Complete punchlist items, final cleanup, and demobilization. TBD 30 475

NOTES FOR "MAIN BODY OF WORK" ABOVE:

&"Arial,Bold"UHHZ 130401 Additions/Alterations to Aircraft Corrosion Control Facility, Building #180