RFI Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_1_of_2.pdf | ||
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_2_of_2.pdf | ||
| FA8501-16-R-0013-0003.pdf | ||
| Amendment_2_130401.pdf | ||
| RFI_Questions_and_Answers_Bldg_180_.docx | DOCX document | |
| Amendment_for_Bldg_180.pdf | ||
| RFI_Questions_and_Answers_for_Bldg_180__3.docx | DOCX document | |
| RFI_Questions_and_Answers_Bldg_180__2.docx | DOCX document | |
| UHHZ130401_Contractors_Site_Visit_Attendees.pdf | ||
| App_C_UHHZ_130401.pdf | ||
| 11-Mar-2016_Wage_Determination.pdf | ||
| Master_Utility_Outage.pdf | ||
| Specifications_Vol._1_of_2.pdf | ||
| Specifications_Vol._2_of_2.pdf | ||
| Form_2519_-_Welding_ _Safety_Checklist.doc | DOC document | |
| Special_Warranty_Requirements.doc | DOC document | |
| Govt._Project_Time_Estimate_Sheet.xlsx | XLSX spreadsheet | |
| FA8501-16-R-0013.pdf | ||
| Half_Size_Drawings.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI’S for Bldg 180, Project # 130401
FA8501-16-R-0013
Question1:
The Base Facility Standard is not referenced in section 28 31 01. Is it a part of this project? If so, which edition?
2) UFC 4-021-01 dated 9 April 2008 with Change 1 dated January 2010 notes in section 4-3.2.2 that "ACU and FACP supplied from different manufacturers" may be allowed. Will this be allowed for this project?
3) Sheet E-401, sheet note #2 lists the pre-recorded messages. These are different from the pre-recorder messages currently in effect for Robins AFB. Which set of messages should be used for this project?
4) Sheet E-401 also shows the SLC & the NIC circuits in separate conduits. Can these circuits be combined in the same conduit as long as the 40% fill is adhered to?
5) Sheet E-403 appears to designed around a base-wide MONACO system. Will this sheet be redesigned to reflect the Robins AFB Federal Signal :Big Voice" system?
Answer 1:
Below is Eugene Rusiecki (CEMP Electrical Engineer) responses to the Contractor's questions:
1) The Base Facility Standard is not referenced in section 28 31 01. Is it a part of this project? If so, which edition?
GOVT. RESPONSE: YES, Base Facility Standard, 23 June 2014 edition. This is mentioned in the SOW – 01005 on page 3 of 6, Section E (6th paragraph).
2) UFC 4-021-01 dated 9 April 2008 with Change 1 dated January 2010 notes in section 4-3.2.2 that "ACU and FACP supplied from different manufacturers" may be allowed. Will this be allowed for this project?
GOVT. RESPONSE: NO. Must be same brand and manufacturer and be network together as one system.
3) Sheet E-401, sheet note #2 lists the pre-recorded messages. These are different from the pre-recorder messages currently in effect for Robins AFB.
Which set of messages should be used for this project?
GOVT. RESPONSE: Shall use set of messages as specified in the Base Facility Standard.
4) Sheet E-401 also shows the SLC & the NIC circuits in separate conduits. Can these circuits be combined in the same conduit as long as the 40% fill is adhered to?
GOVT. RESPONSE: NO, must keep separate circuits.
5) Sheet E-403 appears to designed around a base-wide MONACO system. Will this sheet be redesigned to reflect the Robins AFB Federal Signal : Big Voice" system?
GOVT. RESPONSE: YES
Question 2:
Which waste management vendor(s) does Robins AFB use for dumpsters and trash removal? We would like to use a pre-cleared waste management vendor to supply a temporary job site dumpster for disposal of demolished components and construction debris.
Answer 2:
I spoke with Mr. James Phllips with CE Service Contracts just now. He indicated the SeaCoast Disposal is the waste dumpster and trash removal vendor used by the base. The local contact for SeaCoast is Nick @ 478-206-4941.
Question 3:
In regard to the above referenced project, the Bid Package has 4 lines items for price, with CLIN 0001 & 0002 being for renovation work and work for the addition, respectively.
Our question is in regard to the site work. Is there a specific way that we need to break those costs out and distributed among CLIN's 0001 & 0002, or should we just make that determination on our own, or should all site work and site utilities be placed in one particular CLIN?
Answer 3:
Per the Blank Bid Schedule I have on file (attached), all civil site work, utilities and aluminum canopy construction is listed under CLIN 0002.
image1.emf
130401_Bidding Schedule.docx
UHHZ 130401 ADDITION/ALTERATIONS TO AIRCRAFT CORROSION CONTROL FACILITY, BUILDING #180
BIDDING SCHEDULE
ITEM DESCRIPTION AMOUNT
0001 All Renovations to Project UHHZ 130401, Additions and $___________
Alterations to Aircraft Corrosion Control Facility, Building #180, In Accordance with the Drawings and Specifications as follows:
This bid amount reflects the total contract value of all renovation work. For the purpose of defining scope, this includes all labor and materials, including administration, overhead, taxes, bond and profit, required to complete all aspects of the work within the limit of the original building footprint. For systems such as mechanical, plumbing, electrical, fire protection, telecom and fire alarm, that traverse into the addition area, this price reflects the entire system value per that systems point of origin.
This price does not reflect any civil site work, utilities, or aluminum canopy construction.
0002 Additions to Project UHHZ 130401, Additions and Alterations $___________ to Aircraft Corrosion Control Facility, Building #180, In Accordance with the Drawings and Specifications as follows:
This bid amount reflects the total contract value of all building additions. For the purpose of defining scope, this includes all labor and materials, including administration, overhead, taxes, bond and profit, required to complete all aspects of the work outside the limits of the original building footprint. For systems such as mechanical, plumbing, electrical, fire protection, telecom and fire alarm, that traverse into the addition area, this price reflects the entire system value per that systems point of origin.
This price reflects all civil site work, utilities and aluminum canopy construction.
TOTAL ==> $___________
0003 Provide all labor and materials to complete the installation of $___________
(15) – 18”x18” ceiling mounted access hatches as indicated (total access hatch price) in the contract documents for All Renovations. Unit price is to be added or subtracted from the total bid amount should the total number of access hatches required differ from the specified number. Unit price is valid thru the duration of the construction contract.
0004 Provide all labor and materials to complete the installation of $___________
(3) – 18”x18” ceiling mounted access hatches as indicated (total access hatch price) in the contract documents for Additions. Unit price is to be added or subtracted from the total bid amount should the total number of access hatches required differ from the specified number. Unit price is valid thru the duration of the construction contract.
BIDDING COMPANY:
PERSON:
TITLE:
DATE:
NOTE: We strongly recommended the contractor visit the site to determine the complexity of the work and the amount of material required for this project. Field measurements may have been necessary to determine the size and quantity of materials. Conditions that the Contracting Officer decides would have been obvious or visible to the contractor on inspection at the site visit will not be considered under the Differing Site Conditions provision of the contract.